Construction glossary.

236 terms that PMs, project accountants and CFOs use every day. Plain definitions, worked examples, and the mistakes that cost real money.

236 terms

A

Project management

Acceleration

Speeding up work to finish earlier than the current schedule allows, either because the owner directs it or because the owner denies a time extension the contractor was owed.

Accounting

Accounts payable

Money your company owes to subcontractors, suppliers and vendors for work, materials and services already billed.

Accounting

Accounts receivable

Money owners and clients owe your company for work you've billed, including retainage held until completion.

Accounting

Accrual

Recording a cost (or revenue) in the period it was incurred or earned, even if the invoice hasn't arrived or the cash hasn't moved.

Accounting

ACH (NACHA) file

The fixed-format file your bank accepts to send electronic payments through the ACH network, such as vendor payments and payroll direct deposit.

Project management

Activity Code

A user-defined classification, such as area, trade, phase or responsibility, assigned to schedule activities so they can be filtered, grouped and reported.

Contracts

Additional Insured

A party, like the GC or owner, added to someone else's liability policy by endorsement so that policy defends and covers them for claims arising from that party's work.

Accounting

Aging report

A report that groups open receivables or payables by how long they've been outstanding, such as current, 1–30, 31–60, 61–90 and over 90 days.

Technology

AI Agent

Software that uses an AI model to carry out multi-step tasks, like reading documents, checking data and drafting actions, toward a goal.

Billing

AIA G702

The AIA Application and Certificate for Payment: the one-page summary of a pay application, signed by the contractor and certified by the architect.

Billing

AIA G703

The AIA Continuation Sheet: the line-by-line detail of a pay application, showing progress and retainage for each schedule of values item.

Contracts

Allowance

A placeholder amount in the contract for a specific item not fully defined at bid time, reconciled against actual cost later.

Technology

API (Application Programming Interface)

A defined way for software systems to request and exchange data with each other without manual export and import.

Project management

Architect's Supplemental Instructions (ASI)

AIA G710 Architect's Supplemental Instructions (ASI): the architect's written instruction that clarifies the contract documents or orders a minor change with no change in contract sum or time.

Field

As-Built Drawings

Drawings marked up to show how the project was actually built, including every field change from the original design.

Accounting

ASC 606

The US GAAP standard for revenue from contracts with customers, which governs how contractors recognize revenue over time on construction contracts.

Project management

Assignments View

A schedule view with one row per resource assignment across all activities, showing units, costs, rates, dates and curves, for reviewing and editing resource loading in bulk.

Technology

Audit Trail

A permanent, time-stamped record of who created, changed or approved each piece of data, and what it was before.

Analytics

Average Deal Size

Total value of won pursuits divided by the number won: the typical size of the work you actually land.

B

Accounting

Back charge

A charge a contractor issues to a subcontractor or supplier for costs it incurred because of their defective work, damage, cleanup or failure to perform.

Analytics

Backlog

Contracted revenue not yet earned: the work a contractor has signed but not yet performed.

Accounting

Backup withholding

Withholding 24% of a reportable payment to a vendor who hasn't provided a valid taxpayer identification number, and remitting it to the IRS.

Project management

Ball in Court

Who has to act next on an RFI, submittal, punch item or other open record, so the item never waits without an owner.

Accounting

Bank reconciliation

Proving that the cash balance in your books agrees with the bank statement, after accounting for deposits in transit and outstanding checks.

Contracts

Bid Bond

A surety bond submitted with a bid that guarantees the bidder will sign the contract and provide performance and payment bonds if awarded.

Project management

Bid Leveling

Comparing subcontractor bids line by line, adjusting for scope gaps and exclusions, so they can be judged on equal terms.

Accounting

Bonding capacity

The maximum single-job and total work-on-hand a surety will bond for a contractor, based mainly on its financial strength and track record.

Technology

Building Information Modeling (BIM)

A process of creating and managing a shared 3D model of a building that carries data about its parts, not just geometry.

Field

Building Permit

Written permission from the local building authority to construct, alter or demolish a building, issued after plan review and subject to inspections and conditions.

Project management

Bulletin

A package of revised drawings and specifications the design team issues during construction, often with a request to price the changes.

Project management

Buyout

The process after award of turning the estimate into signed subcontracts and purchase orders, locking in actual costs and scope for each trade.

Accounting

Buyout Savings

The difference between a trade's budgeted cost and the actual amount committed at buyout, positive when the subcontract or PO comes in under budget.

C

Accounting

Cash-basis accounting

Recording revenue when cash is received and expenses when cash is paid, rather than when they are earned or incurred.

Contracts

Certificate of Insurance (COI)

A one-page summary, usually on an ACORD 25 form, that shows a contractor's insurance coverages, limits and policy dates.

Project management

Certificate of Occupancy (CO)

The document a local building authority issues stating a building complies with codes and approved plans and may legally be occupied.

Accounting

Certified payroll

A weekly payroll report, signed under penalty of law, that proves workers on a prevailing wage job were paid the required wages and fringes.

Project management

Change Event

Any occurrence on a project that might change cost, scope or schedule, logged before anyone knows whether it will become a change order.

Technology

Change Feed

A running, newest-first list of what happened to a shared record, such as a schedule's saves, calculations, baselines, imports and discussion, with who did it and what changed.

Project management

Change Order (CO)

A signed agreement between owner and contractor that changes the contract scope, price, time, or a combination of them.

Accounting

Chart of accounts

The numbered list of every account a company posts to, grouped into assets, liabilities, equity, revenue and expenses.

Project management

Closeout

The final phase of a project: work finished, documents delivered, final payments and lien waivers exchanged, and the job closed financially.

Project management

Commissioning (Cx)

A quality process that verifies building systems are designed, installed, tested and operating to meet the owner's requirements.

Accounting

Commitment

A contractual obligation to spend money, such as a subcontract or purchase order, tracked against the budget before any invoice arrives.

Accounting

Completed-Contract Method

An accounting method that recognizes all revenue and profit on a contract only when the job is complete, holding costs and billings on the balance sheet until then.

Billing

Conditional Lien Waiver

A lien waiver that only takes effect once the stated payment is actually received and clears.

Accounting

Consolidation

Combining the financial statements of several entities into one set for the group, eliminating intercompany balances and transactions.

Contracts

Construction Change Directive (CCD)

A written order from the owner directing a change in the work before owner and contractor agree on price or time.

Contracts

Construction Manager at Risk (CMAR)

A delivery method where the CM gives preconstruction advice, then commits to building the project for a guaranteed maximum price.

Contracts

Constructive Change

A change to the work the owner causes through words or conduct without issuing a formal change order, which can still entitle the contractor to more time or money.

Contracts

Contingency

Money set aside in a budget or contract to cover unknown costs and risks that are expected but can't be pinned down yet.

Accounting

Contract asset

Under ASC 606, revenue you have earned on a contract but not yet billed: in construction, the underbilling, or costs and estimated earnings in excess of billings.

Accounting

Contract liability

Under ASC 606, amounts billed or received before the revenue is earned: in construction, the overbilling, or billings in excess of costs and estimated earnings.

Accounting

Control account

A general ledger account whose balance must equal the total of a subledger, such as accounts payable or accounts receivable.

Accounting

Cost code

A code that classifies a cost by type of work, and usually by cost type, so budgets and actuals can be compared at a useful level of detail.

Analytics

Cost report

A job report showing, by cost code, the original and revised budget, committed cost, actual cost, cost-to-complete, forecast and variance.

Contracts

Cost-Plus Contract

A contract where the owner reimburses the contractor's actual costs plus a fee, either a percentage or a fixed amount.

Analytics

Cost-to-complete

The estimated remaining cost to finish a job, based on remaining commitments, remaining labor and known risks, not just budget minus actuals.

Accounting

Cost-to-cost method

Measuring a contract's progress as cost incurred to date divided by estimated total cost, then recognizing that percentage of the contract price as revenue.

Project management

Critical Path

The driving sequence of activities that determines a selected completion milestone under the schedule's logic, calendars, and settings.

Accounting

CSI MasterFormat

The Construction Specifications Institute's standard numbering system that organizes specifications into divisions like 03 Concrete and 26 Electrical.

D

Field

Daily Log

The superintendent's dated record of each day on site: weather, manpower, work performed, deliveries, inspections, visitors, delays and issues.

Project management

Data Date

The status cutoff separating recorded progress from the remaining work forecast in a schedule update.

Contracts

Davis-Bacon Act

US federal law requiring locally prevailing wages and fringe benefits on federally funded or assisted construction contracts over $2,000.

Project management

DCMA 14-Point Assessment

Fourteen schedule-quality screening metrics (logic, leads, lags, constraints, float, durations, dates, resources, missed tasks, CPT, CPLI and BEI) from DCMA guidance.

Contracts

Delay Claim

A documented request for contractual relief associated with delay, supported by records, schedule analysis, and the applicable contract.

Accounting

Depreciation

Spreading the cost of a long-lived asset, such as construction equipment, over the years it is used, as an expense each period.

Contracts

Design-Bid-Build

The traditional delivery method: the owner hires a designer to complete the drawings, bids them to contractors, then signs a separate construction contract.

Contracts

Design-Build

A delivery method where one entity holds a single contract with the owner for both design and construction.

Contracts

Differing Site Conditions

Physical conditions at the site that differ materially from the contract documents or from what's normally encountered, entitling the contractor to an adjustment.

Technology

Digital Twin

A digital model of a physical asset or project that stays connected to real-world data, so it reflects current conditions.

Accounting

Double-entry accounting

The bookkeeping system in which every transaction is recorded as equal debits and credits, so the books always balance.

Project management

Duration Type

A P6 activity setting that decides which of duration, units and units per time is recalculated when one of the others is edited.

E

F

Accounting

FICA

The Federal Insurance Contributions Act taxes, Social Security and Medicare, paid by both employee and employer on wages.

Field

Field Mode (Offline Sync)

A way to keep a schedule on a phone, record progress on site without signal, and sync the updates as one new version when the connection returns.

Field

Field Order

A written order issued in the field directing a contractor to do specific work right away, usually minor, with price and time settled afterward if needed.

Contracts

Final Completion

The point when all contract work, punch list and closeout requirements are done and final payment becomes due.

Project management

Financial Period

A named date range, usually a month, that a schedule's actual units and costs are stored into, so cost performance can be reported per period rather than only to date.

Accounting

Fiscal period

A defined slice of the fiscal year, usually a month, that entries post into and that can be opened, soft-closed or closed.

Project management

Float

Calculated timing flexibility: total float relates to the schedule's late-date limit; free float relates to a successor's early start.

Contracts

Flow-Down Clause

A subcontract provision that binds the subcontractor to the GC's obligations under the prime contract, as they apply to the sub's work.

Contracts

Force Majeure

A contract clause that excuses delay (and sometimes performance) caused by events beyond either party's control, like severe weather, war or epidemics.

Accounting

Form 1099-NEC

The IRS information return for reporting payments to non-employees, such as subcontractors, for services in the course of your business.

Accounting

Form W-9

The IRS form a vendor gives you to certify its name, entity type and taxpayer identification number, used for 1099 reporting.

Accounting

FUTA and SUTA

Federal and state unemployment taxes paid by employers on a limited amount of each employee's wages.

G

H

I

J

L

Accounting

Labor burden

The cost of employing a worker beyond base wage: payroll taxes, workers' comp, insurance and benefits, as a percent or per-hour add-on.

Project management

Layout (Schedule View)

A saved arrangement of a schedule view: its columns, filters, grouping, sort, Gantt settings and panes, reusable by one person, a project team or the whole company.

Analytics

Lead Conversion Rate

The share of incoming inquiries that become real pursuits: inquiries converted to an opportunity divided by inquiries received.

Project management

Lessons Learned

What completed work shows about how long similar work really takes, recorded so the next plan starts from evidence rather than habit.

Billing

Lien Waiver

A document in which a contractor, sub or supplier gives up its right to file a mechanics lien for a stated amount or period, usually in exchange for payment.

Contracts

Limited Notice to Proceed (LNTP)

An owner's written authorization for a contractor to start only named early work, often up to a dollar cap, before the full notice to proceed.

Project management

Line of Balance

A location-based schedule chart that plots locations against time, with one sloped line per trade, so you can see each crew moving through the building and where two trades collide.

Contracts

Liquidated Damages (LDs)

A fixed amount per day, set in the contract, that the contractor owes the owner for finishing late.

Project management

Longest Path

The chain of driving relationships from the data date to the project finish; it can differ from the set of activities with zero total float.

Project management

Look-Ahead Schedule

A short-range schedule, usually two to six weeks, that breaks the master schedule into the specific tasks crews will perform next.

Accounting

Loss provision

On a contract expected to lose money, the immediate recognition of the full anticipated loss, not just the share of it incurred so far.

Contracts

Lump Sum Contract

A contract where the contractor agrees to deliver a defined scope for one fixed price, keeping savings and absorbing overruns.

M

N

O

P

Project management

Pacing

A deliberate slowing of non-critical work in response to a delay on another path, so it isn't counted as concurrent delay.

Billing

Pay Application (Pay App)

A contractor's periodic, itemized request for payment based on work completed and materials stored against the schedule of values.

Contracts

Pay-When-Paid

A subcontract clause that sets the timing of sub payment to follow the GC's receipt of payment from the owner.

Contracts

Payment Bond

A surety bond that guarantees the contractor will pay its subcontractors, laborers and suppliers on the project.

Accounting

Payment run

A batch process that selects approved bills due for payment, applies holds, gets release approval, and produces checks or electronic payments.

Analytics

Percent complete (cost-to-cost)

A job's progress measured as cost incurred to date divided by total estimated cost; the most common basis for recognizing contract revenue.

Project management

Percent Plan Complete (PPC)

The share of a week's commitments that were finished as promised, used in the Last Planner System to measure how reliable short-term planning is.

Contracts

Performance Bond

A surety bond that guarantees the contractor will complete the work according to the contract, or the surety will step in.

Project management

Performance Factor

A multiplier applied to the budget of remaining work to estimate what it will actually cost: 1, a custom value, 1/CPI or 1/(CPI × SPI).

Analytics

Pipeline Value

The total estimated value of every open pursuit: work you're chasing that hasn't been won or lost yet.

Accounting

Positive pay

A fraud control in which you send your bank a list of issued checks, and the bank pays only checks that match it.

Project management

Potential Change Order (PCO)

A priced proposal for a change, submitted to the owner for approval before it becomes an executed change order.

Project management

Preconstruction

The planning phase before construction starts, when the builder estimates, prices, sequences and buys out the work so the project can be built for the budget and schedule the owner expects.

Billing

Preliminary Notice

A notice a sub or supplier sends early in a job to preserve its lien rights, telling the owner and GC it is furnishing labor or materials.

Project management

Prequalification

Screening contractors or subcontractors on safety, finances, experience and capacity before they're allowed to bid.

Accounting

Prevailing wage

The minimum hourly wage and fringe benefits that must be paid to each labor classification on covered public construction projects.

Project management

Program (Schedule)

A group of related projects whose schedules are linked and managed together, so a delay on one project can be traced into the others.

Project management

Progress Line

A line drawn down a Gantt chart through the data date that bends out to each activity's progress point, showing at a glance which work is ahead of plan and which is behind.

Project management

Progress Override

A progress setting that releases the logic into an out-of-sequence activity, so its remaining work continues from the data date.

Project management

Progress Spotlight

A P6 view feature that highlights the activities that should have progressed between the current data date and a new one, as a guide for statusing.

Project management

Prospective Time Impact Analysis

A forward-looking time impact analysis, done near the time of a delay event, that inserts an agreed fragnet into the current schedule update to estimate its effect on completion.

Field

Punch List

The list of incomplete or defective items that must be fixed before the owner accepts the work and final payment is released.

Accounting

Purchase order

A document issued to a supplier that authorizes a purchase of materials, equipment or services at agreed quantities and prices.

Accounting

Purchase Requisition

An internal request to buy something, with what is needed, why, the cost code and an estimate, approved before a purchase order is issued.

Q

R

Accounting

Regular rate of pay

Under the FLSA, the hourly rate used to calculate overtime, which includes most compensation for the workweek, not just the base rate.

Project management

Request for Information (RFI)

A formal written question from the contractor to the design team asking them to clarify, fill a gap in, or resolve a conflict in the contract documents.

Project management

Resource Usage Profile

A time-phased chart of a resource's planned and remaining units or cost per day, week or month, often with cumulative curves and the resource's limit, used to spot over-allocation.

Billing

Retainage

A percentage of each progress payment that the owner (or GC) holds back until the work is substantially or finally complete.

Accounting

Retainage payable

Retainage you have withheld from subcontractors' pay apps, owed to them once release conditions are met.

Accounting

Retainage receivable

Retainage the owner has withheld from your pay applications: billed and earned, but not collectible until release.

Billing

Retainage Release

Billing and paying out the retainage held on a contract, usually at substantial or final completion, once the contractual conditions are met.

Accounting

Retained earnings

The cumulative profits a company has kept rather than distributed, increased each year by the closing entry that moves net income into equity.

Project management

Retained Logic

A progress setting where an out-of-sequence activity's remaining work still waits for its unfinished predecessors.

Accounting

Revenue Recognition (ASC 606)

The accounting rules for when and how much revenue to record. Under ASC 606, most construction contracts recognize revenue over time as work progresses.

Accounting

Reversing entry

A journal entry that exactly mirrors an earlier one, swapping debits and credits, to cancel it or to undo an accrual in the next period.

Contracts

RFP vs. RFQ

An RFQ asks contractors to submit qualifications so the owner can shortlist; an RFP asks for a proposal with approach and often price. In trade buying, RFQ can also mean request for quotation.

Project management

Risk Register

A list of identified project risk events, each with an owner, probability, impact and mitigation, that can feed a quantitative schedule risk analysis.

Technology

Row-Level Security

Filtering data row by row so each person sees only the records they're allowed to see, in every report and query.

S

Analytics

Sales Cycle

How long a pursuit takes from first entry to a win, averaged over won pursuits.

Project management

Schedule Baseline

A preserved reference plan used to compare later progress and forecast dates against the agreed planning basis.

Project management

Schedule Calendar

The working-time rules a scheduling calculation uses to place activity durations on actual dates.

Billing

Schedule of Values (SOV)

The breakdown of the contract sum into line items with assigned values, used as the basis for progress billing.

Contracts

Scope of Work

The written description of the work a contractor or subcontractor must perform, including what is included, what is excluded and the standards it must meet.

Accounting

Segregation of duties

Splitting key steps of a transaction, such as entering, approving, paying and reconciling, between different people so no one person can both commit and conceal an error or fraud.

Technology

Semantic Layer (Metric Catalog)

A governed list of business metrics, each defined once with its formula, unit and allowed groupings, that every dashboard and query reads from.

Contracts

Shared Savings (GMP Savings Split)

A cost-plus-fee with GMP provision that splits any amount by which final cost comes in under the guaranteed maximum price between owner and contractor.

Technology

Single Source of Truth (Data Core)

One authoritative record for each piece of data, so every team and report reads the same number instead of copies.

Project management

SPI(t)

Earned Schedule's time-based Schedule Performance Index: earned schedule divided by actual time. Below 1.00 means the work is behind the baseline.

Contracts

Stop Payment Notice

A claim served on an owner or construction lender that requires them to withhold enough undisbursed project funds to cover an unpaid sub or supplier.

Project management

Store Period Performance

A P6 action that records a schedule's actual units and costs, and earned and planned value, into a financial period, so per-period figures survive later updates.

Billing

Stored Materials

Materials delivered and stored on site or in an approved off-site location but not yet installed, which may be billed if the contract allows.

Contracts

Subcontract

A contract between the prime contractor and a trade contractor to perform a defined part of the prime contract's scope.

Contracts

Subcontractor Default Insurance (SDI)

A policy bought by a general contractor that reimburses it for the costs when an enrolled subcontractor fails to perform.

Accounting

Subledger

A detailed ledger, such as AP, AR, retainage or job cost, whose total ties to a control account in the general ledger.

Project management

Submittal

Shop drawings, product data, samples or other documents a contractor sends to the design team for review before buying or installing materials.

Project management

Submittal Register

The master list of every submittal a project requires, with spec section, responsible sub, required dates and review status.

Contracts

Substantial Completion

The point when the work is complete enough for the owner to occupy or use it for its intended purpose.

Contracts

Surety

The company that issues construction bonds, guaranteeing to the owner that the contractor will perform and pay, and expecting the contractor to repay any loss.

Project management

Suspend and Resume

Dates that record a pause in started work: the suspend date when it stopped and the resume date when its remaining work restarts.

T

Project management

Takeoff

The process of measuring and counting quantities of materials and work from drawings to build an estimate.

Project management

Takt Time

The fixed time each trade gets in each zone in takt planning, so trades move through the building in a steady rhythm, like the carriages of a train.

Project management

Temporary Certificate of Occupancy (TCO)

A time-limited certificate from the building department that allows all or part of a building to be occupied before every item is finished, as long as occupied areas are safe.

Project management

Three-Point Estimate

An activity duration given as optimistic, most likely and pessimistic values, used to describe uncertainty for schedule risk analysis.

Accounting

Three-way match

An AP control that checks an invoice against its purchase order and the receiving record before payment is approved.

Contracts

Time and Materials Contract

A contract where the owner pays for labor at agreed hourly rates plus materials at cost with a markup, usually capped by a not-to-exceed amount.

Field

Time and Materials Ticket (T&M Ticket)

A daily field record of labor hours, materials and equipment used on extra work, signed by the other party as backup for payment.

Project management

Time Impact Analysis

A schedule modeling method that inserts an event into a selected schedule and compares the calculated milestone dates.

Project management

Trace Logic

A small network diagram of one activity's predecessors and successors, a chosen number of levels deep, used to follow logic through a schedule.

Project management

Transmittal

A cover record that lists exactly which documents, drawings or samples were sent, to whom, when, how and for what purpose.

Accounting

Trial balance

A list of every account's debit or credit balance at a date; total debits equal total credits.

U

Billing

Unconditional Lien Waiver

A lien waiver that takes effect immediately on signing, confirming payment has already been received for the stated amount.

Billing

Under billing

When revenue earned to date exceeds billings to date; recorded as an asset called costs and estimated earnings in excess of billings.

Accounting

Uninstalled materials

Materials delivered to or stored for a job but not yet installed; under ASC 606 they can be excluded from cost-to-cost progress and recognized at zero margin.

Accounting

Union fringe

Per-hour contributions a union contractor pays into health, pension, annuity and training funds, as set by the collective bargaining agreement.

Contracts

Unit Price Contract

A contract where the owner pays a fixed price per unit of work (per cubic yard, linear foot, ton) times the actual quantity installed.

Project management

Units Percent Complete

Progress measured as actual resource units over the units expected at completion, across an activity's labor and nonlabor assignments.

Project management

Update Period (Schedule Update)

The interval between two schedule data dates, usually a month, for which progress is recorded, checked, explained in a narrative and submitted for review.

Accounting

Use tax

Tax you owe your state on taxable purchases when the seller didn't charge sales tax, commonly on out-of-state material purchases.

Project management

User-Defined Field (UDF)

A custom field added to schedule activities, such as text, a number, a cost, a date or an indicator, for information the standard fields don't hold.

V

W

Accounting

Wage garnishment

A legal order requiring an employer to withhold part of an employee's earnings and send it to a creditor, a child support agency or a taxing authority.

Contracts

Waiver of Subrogation

An agreement that an insurer, after paying a claim, won't sue the other contracting party to recover what it paid.

Project management

Warranty Period

The time after completion during which the contractor must correct defective work, typically one year from substantial completion plus any longer manufacturer or specified warranties.

Project management

Weather Allowance

Working days a schedule sets aside for normal bad weather, usually by month and applied only to weather-sensitive work.

Technology

Webhook

An automatic message one system sends to a URL you choose the moment a specific event happens, like a change order being approved.

Project management

Weekly Work Plan

The set of commitments each trade makes for the coming week in the Last Planner System, drawn from make-ready work in the lookahead and assessed at the end of the week.

Analytics

Weighted Pipeline

The sum of each open pursuit's estimated value multiplied by its probability of winning: a probability-weighted forecast of new work.

Accounting

WH-347

The US Department of Labor's optional form for the weekly certified payroll that contractors on Davis-Bacon covered projects submit.

Analytics

Win Rate

Pursuits won divided by pursuits decided (won plus lost). Open pursuits are left out.

Project management

Windows Analysis

A retrospective delay analysis that measures how the forecast completion moved in each period between consecutive schedule updates, and why.

Analytics

WIP schedule

A monthly report that compares each open job's earned revenue to its billings to show over billing, under billing and projected profit.

Project management

Work Breakdown Structure

A hierarchy that breaks the whole scope of a project into smaller, manageable pieces of work, used to organize the schedule, the budget and progress reporting.

Contracts

Wrap-Up Insurance (OCIP / CCIP)

A single insurance program that covers the owner, GC and enrolled subcontractors for a project, bought by the owner (OCIP) or the contractor (CCIP).