An earned value technique turns an activity’s progress into earned value (BCWP): the share of its budget at completion that counts as earned. The technique gives a performance percent complete, and earned value is the budget times that percent. P6 sets it for the project and lets each WBS element override it.
| Technique | Earned |
|---|---|
| Activity percent complete | The activity’s percent complete, under its duration, physical or units type |
| 0 / 100 | Nothing until the activity finishes |
| 50 / 50 | Half at the start, the rest at the finish |
| Custom percent complete | A set percentage at the start, the rest at the finish |
| WBS milestones percent complete | The weighted milestones of the WBS element that’s complete |
| Activity percent complete using resource curves | The percent complete mapped through each assignment’s resource curve |
Worked example
Illustrative: a $40,000 activity is 30% complete at the data date. Under activity percent complete it has earned $12,000. Under 50/50 it has earned $20,000, because it has started. Under 0/100 it has earned nothing. With $15,000 spent, CPI is 0.80, 1.33 or 0 depending only on the technique.
Why it matters
The technique changes every earned value figure downstream: CPI, SPI, estimate at completion and the period’s reported performance. Reports that compare projects should say which technique each one uses.
Common mistakes
- Using 50/50 on long activities, which front-loads earned value by half the budget on day one.
- Changing the technique mid-project without saying so, so past and current CPI don’t compare.
- Reading percent-complete-based earned value as physical progress when the percent complete type is duration.
How os.construction handles it
All six techniques apply to the Planner’s Earned Value columns, the Costs & EVM dashboard and Store Period Performance, together with P6’s five ETC techniques. A WBS element can carry its own technique, and each stored period records the technique it used. See Earned value techniques.
Watch the explainer · 2:02
Earned value explained: PV, EV, AC, CPI and SPI
- 0:00Three numbers, one status date
- 0:20Planned value
- 0:38Earned value and actual cost
- 0:57Variances, CPI and SPI
- 1:20Forecast the finish
- 1:39Earned value in os.construction
Read the transcript
Earned value compares three numbers at the same status date: what you planned to do, what you actually did, and what it cost. Spending against the budget alone can't tell you whether a job is under budget or just behind. Earned value can, because it measures progress in budget dollars.
Start with the budget at completion. Take an illustrative control account with a budget of one point two million dollars, spread over a ten month baseline schedule. Planned value is the budget for the work scheduled by each date. At the end of month six, planned value is seven hundred twenty thousand dollars.
Earned value is the budget for the work actually done. The team has completed half the scope, so earned value is fifty percent of one point two million: six hundred thousand dollars. Actual cost is what that work really cost, from job cost with accruals: six hundred sixty thousand dollars.
Now read the gaps. Cost variance is earned value minus actual cost: minus sixty thousand, so the work cost more than its budget. Schedule variance is earned value minus planned value: minus one hundred twenty thousand. As ratios, CPI is zero point nine one and SPI is zero point eight three. Below one is worse than plan.
If cost efficiency stays where it is, the estimate at completion is the budget divided by CPI: one point three two million dollars, one hundred twenty thousand over budget. One caution: SPI is a ratio of money, not time. It drifts back to one as the job finishes, so don't read it as a finish date.
In os.construction Scheduling, the Planner shows earned value for each activity against the project baseline, with variances, CPI, SPI and the estimate at completion. Storing period performance keeps each period's figures as a permanent record.
Video page with chaptersMore in Construction concepts explained
FAQ
What are P6's six earned value techniques?
Activity percent complete, 0/100, 50/50, custom percent complete, WBS milestones percent complete, and activity percent complete using resource curves.
Which technique should short activities use?
Short activities that start and finish within a reporting period often use 0/100 or 50/50, because partial credit adds little information and invites optimism.
Does the technique change actual cost or the schedule?
No. It changes earned value, and so CPI, SPI and any forecast built on them. Actual cost and dates are unchanged.