Esc

↑↓ move↵ openIndex · Pagefind

Estimate at completion calculator

Where does this job land? Four ways to forecast it side by side: CPI, CPI × SPI, remaining work at budget rate, and the PM's bottom-up estimate. With variance, TCPI, margin fade, a sensitivity grid and the month-by-month trend, so you can see when a forecast is wishful.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link

Inputs

Budget & actuals
$
$
BAC is the current cost budget, including approved change order cost, so budget and contract compare like with like.
$
Progress
% complete
% complete
Earned % from installed quantities or milestones, not cost ÷ budget (that makes CPI 1 by definition). Planned % from the baseline schedule; leave 0 to skip SPI methods.
Forecast inputs
$
Bottom-up: remaining labor, open commitments, material still to buy.
% CPI
For the weighted method; the rest is SPI.
over CPI
Your threshold for flagging a forecast.

ResultsLive

Estimate at completion
$0
Variance at completion
$0
Projected margin
0%
CPI
—
SPI
—
TCPI to BAC
—
TCPI to forecast
—
Cost variance
—
Schedule variance
—

Methods side by side

Estimate at completion by method compared with the budget at completion
MethodEACVACMarginImplied TCPI

    Sensitivity: projected marginLive

    Rows: what if the earned percent complete is off by a few points? Columns: cost efficiency on the remaining work. The highlighted cell is today's inputs at CPI to date.

    Trend: how the forecast movedLive

    One row per month, cumulative to date. Paste rows as month, planned %, earned %, actual cost, PM EAC (PM EAC optional), from a spreadsheet or CSV.

    MonthPlanned %Earned %Actual cost $PM EAC $CPISPIEAC (CPI)Remove
    Estimate at completion by month: CPI method, CPI times SPI, PM forecast and budget
    EAC (CPI)EAC (CPI × SPI)PM EACBudget (BAC)

    Sample inputs (illustrative): a $4.8M job with a $4.25M budget, 58% physically complete against 62% planned, $2.61M spent, PM estimate to complete $1.89M, with six months of history.

    Prefer a spreadsheet? Get the free job cost report template for Excel

    See it in the app

    Method

    How this is calculated

    Earned value turns "how far along are we and what did it cost" into three numbers: planned value (PV, budgeted cost of work scheduled), earned value (EV, budgeted cost of work performed) and actual cost (AC). Every EAC method is AC plus a guess about the remaining work, BAC − EV.

    MethodFormulaAssumes
    Remaining at budget rateAC + (BAC − EV)Past overrun was a one-off; the rest goes to plan.
    CPI to dateAC + (BAC − EV) ÷ CPIThe rest performs like the work so far. Equals BAC ÷ CPI.
    CPI × SPIAC + (BAC − EV) ÷ (CPI × SPI)Schedule slip also costs money (extended general conditions, acceleration).
    WeightedAC + (BAC − EV) ÷ (w·CPI + (1−w)·SPI)A blend you choose; weight toward CPI on cost-driven work.
    Management ETCAC + ETCThe PM's bottom-up count of what's left is right.
    EV  = BAC × earned %          PV  = BAC × planned %
    CPI = EV ÷ AC                  SPI = EV ÷ PV
    CV  = EV − AC                  SV  = EV − PV
    VAC = BAC − EAC                ETC = EAC − AC
    TCPI (to BAC)      = (BAC − EV) ÷ (BAC − AC)
    TCPI (to an EAC)   = (BAC − EV) ÷ (EAC − AC)
    Projected margin   = (contract − EAC) ÷ contract
    Fade               = bid margin − projected margin

    How experts use the comparison

    • The PM's number is the forecast of record; the indices audit it. If management EAC sits below every index method, the forecast assumes a turnaround. TCPI says how big: the remaining work has to run at that efficiency.
    • Percent complete is the weakest input. Overstated progress inflates EV, CPI and every index EAC at once. The sensitivity grid shows what five points of optimism are worth in margin.
    • Watch the trend, not the snapshot. An EAC that creeps up every month is fade in slow motion. Catch it at 30% complete and it is a conversation; at 90% it is a write-down.
    • Early indices are noisy. In the first months small dollar amounts swing CPI and SPI; weigh the bottom-up estimate more until enough work is in place.

    On a cost-to-cost WIP schedule EAC is the estimated total cost that drives percent complete and earned revenue. Read when cost-to-cost percent complete lies and why WIP shouldn't be a month-end project, and see margin fade and earned value in the glossary.

    How to calculate estimate at completion with this calculator

    1. Enter budget and actuals. Enter the contract value, the current budget at completion (BAC, including approved change order cost) and actual cost to date (AC).
    2. Enter earned and planned progress. Enter physical percent complete (earned value) and the percent complete the schedule planned by today (planned value).
    3. Enter the PM's estimate to complete. Enter the bottom-up estimate to complete from the project manager: remaining labor, open commitments and material still to buy.
    4. Compare the methods. Read EAC, variance at completion, projected margin and the efficiency each method implies for the remaining work, side by side, and pick the forecast of record.
    5. Test the forecast. Check TCPI against CPI, the sensitivity grid for percent-complete error and productivity, and the month-by-month trend.

    Questions experts ask

    How do you calculate estimate at completion (EAC)?

    EAC is actual cost to date plus the estimated cost to complete the remaining work. Common methods: remaining work at budget rate, AC + (BAC − EV); CPI method, AC + (BAC − EV) ÷ CPI, which equals BAC ÷ CPI; composite, AC + (BAC − EV) ÷ (CPI × SPI); and management ETC, AC plus a bottom-up estimate to complete.

    Which EAC formula is most accurate?

    None is always right. The CPI method assumes the rest of the job performs like the work so far. CPI × SPI also penalizes schedule slip and usually produces a higher EAC when both indices are below 1. A bottom-up management ETC should be the forecast of record, checked against the index methods: if it is well below all of them, ask what will change.

    What is TCPI?

    The to-complete performance index is the cost efficiency the remaining work must achieve to hit a target: (BAC − EV) ÷ (BAC − AC) to finish on budget, or (BAC − EV) ÷ (EAC − AC) for a given EAC. Comparing TCPI with CPI to date tests whether a forecast is realistic: a TCPI well above the CPI means the forecast assumes the remaining work will be done more efficiently than the work so far.

    What is the difference between EAC, ETC and VAC?

    ETC (estimate to complete) is the cost still to spend. EAC (estimate at completion) is cost to date plus ETC. VAC (variance at completion) is budget at completion minus EAC: negative means an overrun.

    How do CPI and SPI work on a construction job?

    CPI is earned value divided by actual cost: below 1 means you are spending more than budgeted for the work in place. SPI is earned value divided by planned value: below 1 means less work is in place than the schedule planned. Earned value should come from physical progress, not cost spent divided by budget, or CPI is always 1.

    How does EAC relate to margin fade and WIP?

    Projected margin is contract minus EAC, divided by contract. The drop from bid margin is fade. On a cost-to-cost WIP schedule, EAC is the estimated total cost that sets percent complete and earned revenue, so an optimistic EAC overstates revenue and hides underbilling or fade until later.

    Sources

    Checked Nov 12, 2026. Formulas are standard earned value relationships; the tolerance for flagging TCPI is your setting, not a published threshold.

    1. Cost Estimating and Assessment Guide (GAO-20-195G), U.S. Government Accountability Office (Mar 12, 2020).Used for: earned value management practice: index-based EACs (cumulative CPI, CPI × SPI, weighted indices) and comparing TCPI with CPI to test whether an EAC is realistic.

    When the spreadsheet version stops scaling

    Make the PM's forecast the one the WIP uses.

    The weakest link in any EAC is a forecast typed into a spreadsheet nobody can trace. In os.construction, PMs save dated cost-to-complete inputs against the same budget and cost codes the books use.

    • PM cost-to-complete inputs are dated and freeze for the period once approved or soft-closed (live).
    • WIP snapshots show a calculation trace on every job and link to the forecast and job cost (live).
    • Commitments, direct costs and approved change orders land on the cost code they belong to (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file