Estimate at completion calculator
Where does this job land? Four ways to forecast it side by side: CPI, CPI × SPI, remaining work at budget rate, and the PM's bottom-up estimate. With variance, TCPI, margin fade, a sensitivity grid and the month-by-month trend, so you can see when a forecast is wishful.
Sample inputs (illustrative): a $4.8M job with a $4.25M budget, 58% physically complete against 62% planned, $2.61M spent, PM estimate to complete $1.89M, with six months of history.
Prefer a spreadsheet? Get the free job cost report template for Excel
How this is calculated
Earned value turns "how far along are we and what did it cost" into three numbers: planned value (PV, budgeted cost of work scheduled), earned value (EV, budgeted cost of work performed) and actual cost (AC). Every EAC method is AC plus a guess about the remaining work, BAC − EV.
| Method | Formula | Assumes |
|---|---|---|
| Remaining at budget rate | AC + (BAC − EV) | Past overrun was a one-off; the rest goes to plan. |
| CPI to date | AC + (BAC − EV) ÷ CPI | The rest performs like the work so far. Equals BAC ÷ CPI. |
| CPI × SPI | AC + (BAC − EV) ÷ (CPI × SPI) | Schedule slip also costs money (extended general conditions, acceleration). |
| Weighted | AC + (BAC − EV) ÷ (w·CPI + (1−w)·SPI) | A blend you choose; weight toward CPI on cost-driven work. |
| Management ETC | AC + ETC | The PM's bottom-up count of what's left is right. |
EV = BAC × earned % PV = BAC × planned % CPI = EV ÷ AC SPI = EV ÷ PV CV = EV − AC SV = EV − PV VAC = BAC − EAC ETC = EAC − AC TCPI (to BAC) = (BAC − EV) ÷ (BAC − AC) TCPI (to an EAC) = (BAC − EV) ÷ (EAC − AC) Projected margin = (contract − EAC) ÷ contract Fade = bid margin − projected margin
How experts use the comparison
- The PM's number is the forecast of record; the indices audit it. If management EAC sits below every index method, the forecast assumes a turnaround. TCPI says how big: the remaining work has to run at that efficiency.
- Percent complete is the weakest input. Overstated progress inflates EV, CPI and every index EAC at once. The sensitivity grid shows what five points of optimism are worth in margin.
- Watch the trend, not the snapshot. An EAC that creeps up every month is fade in slow motion. Catch it at 30% complete and it is a conversation; at 90% it is a write-down.
- Early indices are noisy. In the first months small dollar amounts swing CPI and SPI; weigh the bottom-up estimate more until enough work is in place.
On a cost-to-cost WIP schedule EAC is the estimated total cost that drives percent complete and earned revenue. Read when cost-to-cost percent complete lies and why WIP shouldn't be a month-end project, and see margin fade and earned value in the glossary.
How to calculate estimate at completion with this calculator
- Enter budget and actuals. Enter the contract value, the current budget at completion (BAC, including approved change order cost) and actual cost to date (AC).
- Enter earned and planned progress. Enter physical percent complete (earned value) and the percent complete the schedule planned by today (planned value).
- Enter the PM's estimate to complete. Enter the bottom-up estimate to complete from the project manager: remaining labor, open commitments and material still to buy.
- Compare the methods. Read EAC, variance at completion, projected margin and the efficiency each method implies for the remaining work, side by side, and pick the forecast of record.
- Test the forecast. Check TCPI against CPI, the sensitivity grid for percent-complete error and productivity, and the month-by-month trend.
Questions experts ask
How do you calculate estimate at completion (EAC)?
EAC is actual cost to date plus the estimated cost to complete the remaining work. Common methods: remaining work at budget rate, AC + (BAC − EV); CPI method, AC + (BAC − EV) ÷ CPI, which equals BAC ÷ CPI; composite, AC + (BAC − EV) ÷ (CPI × SPI); and management ETC, AC plus a bottom-up estimate to complete.
Which EAC formula is most accurate?
None is always right. The CPI method assumes the rest of the job performs like the work so far. CPI × SPI also penalizes schedule slip and usually produces a higher EAC when both indices are below 1. A bottom-up management ETC should be the forecast of record, checked against the index methods: if it is well below all of them, ask what will change.
What is TCPI?
The to-complete performance index is the cost efficiency the remaining work must achieve to hit a target: (BAC − EV) ÷ (BAC − AC) to finish on budget, or (BAC − EV) ÷ (EAC − AC) for a given EAC. Comparing TCPI with CPI to date tests whether a forecast is realistic: a TCPI well above the CPI means the forecast assumes the remaining work will be done more efficiently than the work so far.
What is the difference between EAC, ETC and VAC?
ETC (estimate to complete) is the cost still to spend. EAC (estimate at completion) is cost to date plus ETC. VAC (variance at completion) is budget at completion minus EAC: negative means an overrun.
How do CPI and SPI work on a construction job?
CPI is earned value divided by actual cost: below 1 means you are spending more than budgeted for the work in place. SPI is earned value divided by planned value: below 1 means less work is in place than the schedule planned. Earned value should come from physical progress, not cost spent divided by budget, or CPI is always 1.
How does EAC relate to margin fade and WIP?
Projected margin is contract minus EAC, divided by contract. The drop from bid margin is fade. On a cost-to-cost WIP schedule, EAC is the estimated total cost that sets percent complete and earned revenue, so an optimistic EAC overstates revenue and hides underbilling or fade until later.
Sources
Checked Nov 12, 2026. Formulas are standard earned value relationships; the tolerance for flagging TCPI is your setting, not a published threshold.
- Cost Estimating and Assessment Guide (GAO-20-195G), U.S. Government Accountability Office (Mar 12, 2020).Used for: earned value management practice: index-based EACs (cumulative CPI, CPI × SPI, weighted indices) and comparing TCPI with CPI to test whether an EAC is realistic.
When the spreadsheet version stops scaling
Make the PM's forecast the one the WIP uses.
The weakest link in any EAC is a forecast typed into a spreadsheet nobody can trace. In os.construction, PMs save dated cost-to-complete inputs against the same budget and cost codes the books use.
- PM cost-to-complete inputs are dated and freeze for the period once approved or soft-closed (live).
- WIP snapshots show a calculation trace on every job and link to the forecast and job cost (live).
- Commitments, direct costs and approved change orders land on the cost code they belong to (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →