Esc

↑↓ move↵ openIndex · Pagefind

Over/under billing (WIP) calculator

Are you billing ahead of the work or financing the owner's job? Percent complete, earned revenue and the over/under number your bonding agent will ask about, with the details an auditor checks: pending change orders, uninstalled materials and loss jobs.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link

Job inputs

$
Original contract plus approved change orders.
$
Current estimate at completion, not the original bid.
$
$
Gross billings, before retainage is withheld.
Method, change orders, materials and bid margin
$
Unapproved COs are variable consideration. Leave them out unless a significant reversal isn’t probable.
$
Bought and on site but not installed. Left out of progress either way.
%
Optional. Shows fade from bid.

ResultsLive

Gauge of billing position: under billed on the left, over billed on the rightUNDERBALANCEDOVER
% complete
0%
Earned revenue
$0
Over / (under)
$0
Projected GP
$0
GP to date
$0
Loss provision
$0
Cost to complete
$0
Backlog
$0

    Sample inputs (sample data): Riverside Medical Center, Job #24-118, plus two illustrative jobs in multi-job mode.

    See it in the app

    Method

    How this is calculated

    Animated explainerHow over and under billing happensOne illustrative $10M job, month by month. Earned revenue follows cost; billing follows the schedule of values. The space between them is the over/under on your WIP.
    Earned revenue and billings over twelve months, with the over and under billing gap shaded
    Earned Billed Over Under

    Complete. Billed equals earned equals the $10.4M contract, so over/under is zero.

    1. Month 1–3Front-loaded billingMobilization and general conditions bill early: over billed.
    2. Month 5–6Cost runs aheadMaterials and subs post faster than SOV lines bill: under billed.
    3. Month 7–8Unapproved changeCost in, revenue constrained until the CO is signed: under billed.
    4. Month 9CO approvedThe change is billed with a catch-up: over billed again.
    5. Month 12CloseoutBilled = earned = contract. The gap closes.

    Contractors recognize revenue as the work gets done (percentage of completion, ASC 606 over time). Billing follows the schedule of values, so the two drift apart. The gap is over billing or under billing.

    Contract revenue = contract + pending COs (only if included)
    % complete       = (cost to date − uninstalled) ÷ est. total cost
                       units: units complete ÷ total units
                       physical: observed % complete
    Earned revenue   = contract revenue × % complete
    Over / (under)   = billed to date − earned revenue
    Projected GP     = contract revenue − est. total cost
    GP to date       = earned revenue − cost recognized − loss provision
    Loss provision   = if GP < 0: (earned − cost recognized) − projected GP
    Cost to complete = est. total cost − cost to date
    Backlog          = contract revenue − earned revenue

    Reading the result

    • Over billed (billings in excess of costs and estimated earnings) is a liability. You’ve been paid for work you still owe. Good for cash, but it can hide a fading job.
    • Under billed (costs and estimated earnings in excess of billings) is an asset. You’ve done work you haven’t billed. Persistent under billing often means unbilled change orders, a front-loaded cost, or an estimate that’s too low.
    • Loss jobs recognize the whole projected loss now. The loss provision is the part % complete hasn’t booked yet.

    Why the estimate matters most

    Cost-to-cost is only as good as the estimated total cost. If the estimate is stale, % complete is inflated, earned revenue is overstated and under billing looks better than it is. Update cost to complete before you run WIP. If cost to date is already past the estimate, progress is capped at 100% and flagged. Units and physical methods show cost-to-cost alongside, so you can see when the two disagree.

    Watch the explainer · 1:55

    Cost-to-cost percent complete: when it lies

    1. 0:00One formula, one assumption
    2. 0:21An illustrative job
    3. 0:37Material bought, not installed
    4. 0:56A stale cost to complete
    5. 1:16Get a second opinion
    6. 1:37Percent complete in os.construction
    Read the transcript

    Most contractors measure percent complete with the cost-to-cost method: cost to date divided by estimated total cost. It's simple, and auditors know it. It also assumes every dollar spent is the same amount of progress. When that isn't true, earned revenue and over and under billing are wrong too.

    Take an illustrative job: a ten million dollar contract with nine million dollars of estimated cost, a ten percent margin. With three point six million dollars spent, the job is forty percent complete, and you've earned four million dollars of revenue.

    Now the mechanical sub buys six hundred thousand dollars of rooftop units early. The invoice posts, and cost to date jumps to four point two million. Percent complete jumps to about forty-seven percent, and about six hundred sixty-seven thousand dollars more revenue is recognized for equipment sitting in a warehouse.

    The bigger risk is the forecast. Later, five point four million is spent. If the cost to complete still says three point six million, the job looks sixty percent complete with a ten percent margin. An honest forecast of four point three million makes it about fifty-six percent, with a three percent margin.

    Unaccrued costs, rework and miscoded invoices distort it too. The fix is a cross-check. Compare cost-to-cost with the field's physical percent complete and with billing, and ask why when they spread apart. Uninstalled materials can be tracked separately, and your accountant sets the policy for leaving them out.

    In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.

    Uninstalled materials and pending change orders

    Uninstalled materials sit in cost to date without showing progress, so they come out of the measure. By default their cost waits until installed; ticking “at cost” recognizes revenue equal to the cost with no margin, as in ASC 606-10-55-187 (Example 19). Pending change orders stay out of revenue unless you judge the constraint met.

    Multi-job mode is a quick sum. For a full schedule with prior-period fade, surety ratios and Excel export, use the WIP schedule workbench, and for the reading behind it see over billing vs under billing and construction WIP software.

    Questions

    How do you calculate over and under billing?

    Divide cost to date by estimated total cost to get percent complete (cost-to-cost). Multiply the contract value by percent complete to get earned revenue. Subtract earned revenue from billed to date: a positive number is over billing, a negative number is under billing.

    Is under billing good or bad?

    Neither on its own. Under billing is an asset, but it means you are financing the owner’s job. Persistent under billing usually points to unbilled change orders, a front-loaded cost, or an estimate that is too low, which also inflates percent complete.

    Should pending change orders be in the contract value?

    Approved change orders, yes. Pending or unapproved ones are variable consideration under ASC 606: include them only to the extent a significant reversal of revenue is not probable. This calculator leaves them out unless you tick the box.

    What happens when a job is projected to lose money?

    The whole projected loss is recognized now. Earned revenue stays contract × percent complete, and a loss provision books the part of the loss that percent complete hasn’t recognized yet, so gross profit to date shows the full loss.

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file