Retainage calculator and ledger
How much is held back, what's due this period, and what's left to bill, laid out G702-style so you can check a pay app line by line. Then model retainage across the whole job: reductions, release, and what carrying it costs.
Watch the explainer · 2:10
Retainage explained: held, billed and released
- 0:00Earned, but held back
- 0:20How it's held on a pay app
- 0:40One illustrative pay app
- 1:04Flow-down and reductions
- 1:26Release at completion
- 1:47Retainage in os.construction
Read the transcript
Retainage is the share of each progress payment the owner holds back until the work is substantially complete, commonly five to ten percent. It's money you've already earned, held as security that the job gets finished and defects get fixed. The contract sets the rate, within any limits set by law.
On a pay app, retainage is held on the cumulative amount: work completed to date times the retainage rate, plus stored materials times the stored-materials rate. Payment due is completed and stored, less retainage, less previous certificates. So this period's retainage is the change in that running total.
Here's the sample Riverside job, Pay App number nine. Thirty-three million dollars is completed and stored to date. At ten percent, three point three million is held. Less twenty-seven point six million previously certified, the payment due is about two point oh eight million. This period's two point three one million of work added two hundred thirty-one thousand of retainage.
The GC usually withholds the same rate or more from its subs, so it isn't paying out money it hasn't received. Many contracts drop the rate, say from ten percent to five, once the job is fifty percent complete. Read the contract: it decides whether the lower rate applies only to work after the milestone, or to everything completed.
Release usually comes in a billing at substantial completion, less an amount held for punch list and closeout items. The rest follows at final completion, once closeout documents and final lien waivers are in. Many states cap retainage and set release deadlines, especially on public work. General information, not legal advice.
In os.construction, pay applications calculate retainage on every line, with separate rates for work and stored materials, and record retainage released. Accounting tracks retainage receivable and payable apart from ordinary receivables and payables.
Video page with chaptersMore in Construction concepts explained
Retainage over the whole job, period by period
Withheld every period, reduced at a milestone, released at substantial completion and at final. See the peak you carry and what it costs. Billings follow an S-curve; overwrite any period with your real numbers.
Retainage heldLive
- Peak held
- $0
- Cost to carry
- $0
- Total withheld
- $0
- Avg. time held
- 0 mo
- per dollar withheld
Ledger
| Period | Billed (edit) | Billed to date | Withheld | Released | Balance held | Net cash in |
|---|---|---|---|---|---|---|
Retainage rules by state: a starting point
General information, not legal advice. Verify the current statute. Each row is a short summary of the statute text on the official source linked, read on November 12, 2026. Summaries leave out exceptions (thresholds, bonds or securities in lieu of retainage, project types), statutes change, and your contract and project type decide what applies. Only rules we could confirm on an official legislature or government site are listed.
| Jurisdiction | Work | Rule (summary) | Statute |
|---|---|---|---|
| Federal (FAR) | Federal | Retainage only when the contractor has not made satisfactory progress, capped at 10% of the approved estimate and reducible near completion. Retained amounts are paid promptly once contract requirements are complete.FAC 2026-01, effective 3/13/2026. | FAR 32.103; 52.232-5(e)(official source, opens in a new tab) |
| Arizona | Public | 10% of each estimate. At 50% complete, half the retention is paid on request if progress is satisfactory, and no more than 5% is kept from later payments. Paid within 60 days after completion or notice of completion. | A.R.S. §34-221(C)(official source, opens in a new tab) |
| Arizona | Private | No percentage cap: the owner may withhold "a reasonable amount for retention". Paid within 7 days after the release-of-retention billing, submitted after substantial completion, is certified and approved. | A.R.S. §32-1182(D), (I)(official source, opens in a new tab) |
| California | Public | Retention capped at 5% of each payment and of the contract price, flowing down to subs, unless the awarding body finds before bid that the project is "substantially complex".Read in the Legislature's official bulk data (file dated 2026-11-08). | Pub. Contract Code §7201(b)(official source, opens in a new tab) |
| California | Public | Retention released within 60 days after completion; the agency may withhold 150% of a disputed amount. The prime pays subs their share within 7 days of receiving it. | Pub. Contract Code §7107(official source, opens in a new tab) |
| California | Private | For contracts entered into on or after January 1, 2026, retention is capped at 5% of each payment and of the contract price, flowing down to subs (SB 61). Exceptions: residential projects of four stories or less that are not mixed-use, and a sub that fails to furnish a bond required at bid time. Contracts signed earlier keep their agreed rate. The owner pays retention within 45 days after completion (may withhold 150% of a good-faith disputed amount); the direct contractor pays each sub its share within 10 days of receipt.Cap added by SB 61 (Stats. 2025, ch. 49). Confirm the exception wording against the enacted text. | Civ. Code §8811, §8812, §8814(official source, opens in a new tab) |
| Colorado | Public | On contracts over $150,000, at least 95% of completed work is paid, so up to 5% is withheld until satisfactory completion and final acceptance. Final settlement within 60 days after final acceptance.Checked against the 2024 official (uncertified) printout, the latest available. | C.R.S. §24-91-103(1)(official source, opens in a new tab) |
| Florida | Public | Public entities: no more than 5% of each progress payment. Does not apply to contracts of $200,000 or less.The older 10%-until-50% rule was removed; last amended ch. 2023-134. | Fla. Stat. §255.078(official source, opens in a new tab) |
| Florida | Public | Local governments: no more than 5% of each progress payment on contracts over $200,000. The balance, including retainage, is due within 20 business days after the punch list is created, less 150% of the cost to complete listed items. | Fla. Stat. §218.735(7)–(8)(official source, opens in a new tab) |
| Illinois | Public | Bonded local public works: no more than 10% until 50% complete, then no more than 5%; the same caps apply prime to sub.P.A. 104-168, effective 6/1/2027, extends the cap to most State agencies. | 30 ILCS 550/1(official source, opens in a new tab) |
| Illinois | Private | Up to 10% until 50% complete, then no more than 5%. Excludes contracts using public funds and residential buildings of 12 or fewer units. | 815 ILCS 603/20(official source, opens in a new tab) |
| Massachusetts | Public | Public building contracts: up to 5% of each periodic payment. The balance is due within 65 days after completion or substantial completion, less amounts for claims and unfinished work. | M.G.L. c.30 §39K(official source, opens in a new tab) |
| Massachusetts | Public | Public ways and public works: up to 5% of each periodic payment. Within 65 days after substantial completion, all but 1% of retainage is paid, less the cost of unfinished work. | M.G.L. c.30 §39G(official source, opens in a new tab) |
| New York | Public | Municipal public works: no more than 5% of each progress payment (up to 10% only if performance and payment bonds are not required). At substantial completion, the balance less twice the value of remaining items is paid. | Gen. Mun. Law §106-b(official source, opens in a new tab) |
| New York | Private | No more than 5% of the contract sum on private projects of $150,000 or more, flowing down to subs. Released within 30 days after final approval of the work, with interest if late. | Gen. Bus. Law §756-c(official source, opens in a new tab) |
| North Carolina | Public | No retainage if total project costs are under $150,000; otherwise no more than 5%. At 50% complete, with surety consent and satisfactory work, no further retainage. Released within 60 days after the pay request following substantial completion.Last amended by S.L. 2026-9. | G.S. 143-134.1(b1)(official source, opens in a new tab) |
| Ohio | Public | Partial payments for labor are at least 96% of approved estimates, so no more than 4% is withheld on labor. Retainage on an accepted major portion is paid within 30 days; the balance within 30 days after final completion.153.12 as effective 9/17/2026; 153.13 as effective 9/30/2025. | R.C. 153.12(A), 153.13(official source, opens in a new tab) |
| Ohio | Private | No statutory percentage cap. A contractor pays subcontractors their share of retainage within 10 days of receiving it, or sooner if the contract says so; late payment carries 18% a year interest. | R.C. 4113.61(A)(3)(official source, opens in a new tab) |
| Oregon | Public | Up to 5% of each progress payment. After 50% completion the agency may reduce or end retainage for satisfactory work, on written application with surety approval. Paid with final payment; 1.5% a month interest starts 30 days after completion and acceptance. | ORS 279C.570(7)–(8)(official source, opens in a new tab) |
| Pennsylvania | Public | No more than 10% until 50% complete; then half the retained amount is returned (architect approval, satisfactory progress) and no more than 5% is held. Paid within 45 days after substantial completion, less 1.5× remaining minor items. | 62 Pa.C.S. §3921(a), §3941(a)(official source, opens in a new tab) |
| Pennsylvania | Private | No percentage cap. Retainage is paid within 30 days after final acceptance; contractors pay subs within 14 days of receiving it. Excludes projects of 6 or fewer residential units. | Contractor and Subcontractor Payment Act §9 (73 P.S. §509)(official source, opens in a new tab) |
| Texas | Public | No more than 10% on contracts under $5 million and 5% on $5 million or more (10% for dams). Not held after the work is complete, including the warranty period, except for a bona fide dispute.Contracts under $400,000 are exempt (§2252.033). | Gov't Code §2252.032(official source, opens in a new tab) |
| Virginia | Public | At least 95% of the earned sum is paid when due, so no more than 5% is retained; this extends to subcontracts on public projects. The section sets no release deadline. | Va. Code §2.2-4333(official source, opens in a new tab) |
| Washington | Public | Up to 5% of earned moneys is reserved as a trust fund. The contractor may ask to reduce it to 100% of the remaining work's value. Paid 60 days after all contract work is complete, subject to lien and tax clearances. | RCW 60.28.011(official source, opens in a new tab) |
Not listed doesn't mean no rule: it means we haven't verified that state's text on an official source yet. Private-work rules often come from prompt payment acts and may set release timing without a percentage cap. For federal contracts, check the contract's payment clauses and the FAR. Georgia, among others, has changed its public rule in recent years; we list a state only once its current text is confirmed.
When the spreadsheet stops scaling
Retainage tracked on the pay app, not in a side spreadsheet.
- Work and materials retainage are set separately on each pay app and calculated per line.
- Retainage released is entered on the pay app, so the summary and the balance held stay right.
- Subcontractor retainage is held on sub invoices against the same commitments.
- Build the bill with the free pay application builder first, if you like: same math.
Sample inputs: Riverside Medical Center, Pay App #9 (sample data). $2,310,400 of work this period at 10% retainage = $231,040 held.
How this is calculated
Retainage (retention) is the share of each payment the owner holds back until the job is substantially complete. This tool follows the common G702-style summary layout (not an AIA document). To build the whole bill line by line, use the pay application builder.
Completed & stored = work completed + stored materials Retainage held = work completed × rate + stored × stored rate Earned less ret. = completed & stored − retainage held (line 6) Payment due = line 6 − previous certificates (line 8) Balance to finish = contract sum − line 6 (line 9)
Retainage reduction
Many contracts drop retainage from 10% to 5% once the job is 50% complete. There are two common ways to do it:
- Work above the milestone only: the first 50% of the contract stays at 10%, everything after is held at 5%. Retainage held = contract × 50% × 10% + (completed − contract × 50%) × 5%.
- All completed work: the owner releases retainage down to 5% of everything completed. Retainage held = completed × 5%. This usually comes with a release of the excess on the next pay app.
Public work often caps retainage by statute, and some states require release within a set period after substantial completion: see the state reference table. Treat this as a calculator, not legal advice. More on the paperwork that gates release: the monthly retainage follow-up and lien waivers. To watch retainage build from owner to GC to subs and come back at substantial and final completion, read how retainage moves through a job.
What "payment due" doesn't include
Line 8 is what's certified, not what lands in the bank. Owners can still hold for missing lien waivers, disputed items or back charges.
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →