How retainage moves through a job
Six pay apps, two tiers and two releases. Step through how the owner holds back part of every payment, how the GC does the same to its subs, what a reduction at 50% does, and how the money comes back at the end. Drag the slider to read any pay app.
What is retainage?
Retainage is a percentage of each progress payment held back until the work is complete, so the payer keeps leverage to get the job finished and fixed. The owner holds it from the general contractor, and the general contractor usually holds it from its subcontractors. It builds up with every pay app and comes back at the end, mostly at substantial completion and the rest at final completion.
Retainage does not change how much anyone is paid. It changes when. Step through one illustrative $3,000,000 job below, then drag the slider to see both balances after any pay app.
Owner to GC to subs, and back
Step 4 of 6: The balance peaks at the last pay app
- Billed this period
- $450,000
- Owner holds this period
- $22,500
- Owner holds, total
- $225,000
- Paid to GC
- $427,500
- GC holds from subs, total
- $180,000
- Paid to subs
- $243,000
Pay app 1 bills $300,000 of work. This contract holds 10%, so $30,000 stays with the owner and $270,000 is paid, before any other deductions. The held amount is the GC’s retainage receivable: earned and billed, but not collectible until it is released.
Subcontractors did 60% of each month’s work here, and their subcontracts also hold 10%. On pay app 3 the GC pays subs $324,000 of $360,000 and keeps $36,000. After three pay apps the owner holds $135,000 and the GC holds $81,000 of sub retainage, its retainage payable. Net, $54,000 of the GC’s own money is waiting.
This contract holds 5% on work billed after the job reaches 50% ($1,500,000). Pay app 4 crosses the line: the first $150,000 is held at 10% and the other $450,000 at 5%, so $37,500 is held instead of $60,000. The subcontracts here have no reduction, so the GC keeps holding 10% from subs.
After pay app 6 the job is fully billed. The owner holds $225,000, 7.5% of the $3,000,000 contract. The GC holds $180,000 from subs. The $45,000 difference is cash the GC has earned but is waiting for on its own account.
This contract releases retainage at substantial completion less 150% of the value of open punch work. A $20,000 punch list keeps $30,000 back and releases $195,000. The GC does the same downstream: $8,000 of open sub punch work keeps $12,000 and releases $168,000 to subs, on the timing the subcontracts and the law allow.
With the punch list done and closeout documents and final lien waivers in, the owner releases the last $30,000 and the GC releases the last $12,000 to subs. Both balances reach zero. In total the owner paid $3,000,000 and the GC paid subs $1,800,000: retainage changes when cash moves, not how much.
Every pay app and release, both tiers
Retainage is figured on cumulative work, so each period’s retainage is the new total held minus what was already held. With one flat rate that is just this period’s billing times the rate; the reduction is what makes pay app 4 different.
Retainage held = work completed to date at its rate(s) This period = retainage held − retainage held last period Net payment = billed this period − this period’s retainage Pay app 4 = $150,000 × 10% + $450,000 × 5% = $37,500 At substantial = $225,000 held − 150% × $20,000 punch = $195,000 released
| Stage | Owner to GC | GC to subs | GC net | ||||||
|---|---|---|---|---|---|---|---|---|---|
| Billed | Held (released) | Owner holds | Paid | Billed | Held (released) | GC holds | Paid | ||
| Pay app 1 | $300,000 | $30,000 | $30,000 | $270,000 | $180,000 | $18,000 | $18,000 | $162,000 | $12,000 |
| Pay app 2 | $450,000 | $45,000 | $75,000 | $405,000 | $270,000 | $27,000 | $45,000 | $243,000 | $30,000 |
| Pay app 3 | $600,000 | $60,000 | $135,000 | $540,000 | $360,000 | $36,000 | $81,000 | $324,000 | $54,000 |
| Pay app 4 | $600,000 | $37,500 | $172,500 | $562,500 | $360,000 | $36,000 | $117,000 | $324,000 | $55,500 |
| Pay app 5 | $600,000 | $30,000 | $202,500 | $570,000 | $360,000 | $36,000 | $153,000 | $324,000 | $49,500 |
| Pay app 6 | $450,000 | $22,500 | $225,000 | $427,500 | $270,000 | $27,000 | $180,000 | $243,000 | $45,000 |
| Substantial completion | – | ($195,000) | $30,000 | $195,000 | – | ($168,000) | $12,000 | $168,000 | $18,000 |
| Final completion | – | ($30,000) | $0 | $30,000 | – | ($12,000) | $0 | $12,000 | $0 |
| Total | $3,000,000 | $0 | – | $3,000,000 | $1,800,000 | $0 | – | $1,800,000 | – |
Two things to notice. Peak retainage, $225,000, is 7.5% of the contract, between the two rates, because only the second half of the work was held at 5%. And the GC’s net position stays positive the whole way: the owner always holds more of the GC’s money than the GC holds of its subs’, because the GC’s own work is held too. After the reduction the gap narrows, from $55,500 to $45,000: the GC still holds 10% of sub work, 6% of each month’s billing, while the owner now holds 5%.
The retainage calculator runs the same math on your own pay app, with work and stored-material rates, a reduction at a milestone (either reading) and a release ledger. The how to calculate retainage guide writes out the same six pay apps as a ledger.
Two ways to read “reduced to 5% at 50%”
The same clause can mean two different amounts of cash, so read it, and any statute, before the first pay app.
- Work above the milestone only (used here). Work billed until the job is 50% complete stays at 10%; only work after it is held at 5%. Pay app 4 holds $37,500, the balance reaches $172,500, and the job ends at $225,000, 7.5% of the contract.
- All completed work drops to the new rate. At the milestone, the rate on everything billed so far becomes 5% and the excess already held is released. Pay app 4 would hold 5% of $1,950,000, or $97,500, giving back $37,500 of the $135,000 already held. The job ends at $150,000, $75,000 less.
- Conditions often apply. Owners commonly require satisfactory progress, no open claims or the surety’s consent before reducing, and some public statutes set the rate and the method outright. A reduction on the prime contract does not reduce subcontract retainage unless the subcontract or the law says so.
Where the law steps in
Retainage rules vary by state and between public and private work, and they are written most often about the flow-down to subcontractors. A few examples, as general information:
- Federal contracts. The government withholds retainage only when progress is not satisfactory, generally up to 10% (FAR 52.232-5). The Prompt Payment Act requires primes to pay subs within 7 days of being paid and lets them agree retainage terms in the subcontract (31 U.S.C. §3905).
- California public works. Retention is capped at 5% of each payment and of the contract price, and the cap applies at every tier (Public Contract Code §7201).
- California private works. For contracts entered into on or after January 1, 2026, retention is capped at 5% of each payment and of the contract price, with exceptions (Civil Code §8811, added by SB 61). Once paid retention, the direct contractor has 10 days to pay each sub its share (Civil Code §8814).
The retainage rules by state table on the calculator page lists more, each linked to its statute. Under rules like these, the 10% held from subs in this example might not be allowed. That is why the example calls it a subcontract term and not a rule.
In os.construction, pay apps calculate retainage at the application’s rate, with separate rates for work and stored materials, roll it forward from application to application, and carry a Retainage Released line for amounts you release. On the sub side, sub invoices withhold retainage at the commitment’s rate and track it as withheld to date. Automatic reductions and release workflows are Planned; today you set the rate on the application.
Common questions
How does retainage work in construction?
The owner holds back a percentage of each progress payment, commonly 5% to 10%, until the work is complete. The general contractor usually does the same to its subcontractors under their subcontracts. The held amounts build up over the job and are released later, typically most of it at substantial completion less a holdback for the punch list, and the rest at final completion. Rates, reductions and release terms come from the contract and, on many jobs, state or federal law.
What does “10% reduced to 5% at 50% complete” mean?
It depends on the contract wording. In the reading used here, work billed until the job reaches 50% is held at 10% and work billed after it at 5%, so total retainage ends at 7.5% of the contract. In the other common reading, the rate on all completed work drops to 5% at the milestone and the excess already held is released, so total retainage ends at 5%. On this $3,000,000 example that is a $75,000 difference at completion. Some statutes set the method, and owners often require satisfactory progress or surety consent first.
When is retainage released?
Typically in two pieces: a release at substantial completion, less a holdback for open punch list and closeout items, and the balance at final completion once closeout documents and final lien waivers are in. Holding 150% of the value of open punch work is a common contract term and appears in some state statutes, but it is not universal. Many public statutes and some private prompt payment laws also set deadlines to release retainage and to pass subcontractors their share once the contractor is paid.
Can a general contractor hold more retainage from subs than the owner holds from the GC?
It depends on the subcontract and the law where the project is. Where no statute applies, the subcontract governs, which is why the example GC can keep holding 10% from subs after the owner’s rate drops. Several states cap subcontract retainage at the rate the owner withholds from the prime or apply a public-work cap at every tier; California’s public works cap, for example, applies at each tier. Check the statute before you set subcontract terms.
How is retainage recorded in the books?
The contractor records the full billing as earned, with the held part as retainage receivable, kept separate from current receivables because it is not collectible until release. Retainage the contractor holds from subs is retainage payable. A release billing moves the released amount from retainage receivable to accounts receivable. Presentation on the balance sheet depends on your accounting framework; check it with your CPA.
Keep going
Sources and further reading
- FAR 52.232-5: payments and retainage under federal fixed-price construction contracts.
- 31 U.S.C. §3905: prompt payment to subcontractors on federal construction contracts.
- Cal. Public Contract Code §7201 and Civil Code §8811: California public and private retention caps.
General information only. Every figure on this page is illustrative.
Keep exploring
Related across os.construction
- GlossaryRetainage receivableRetainage the owner has withheld from your pay applications: billed and earned, but not collectible until release.
- GlossaryRetainageA percentage of each progress payment that the owner (or GC) holds back until the work is substantially or finally complete.
- Free toolCash flow projection templateFree construction cash flow projection for Excel.
- DocsCloseout and retainage releaseHow AR retainage release and contract closeout checklists work today, what remains unautomated, and why contract and jurisdiction terms must be configured per project.
- Free toolRetainage calculatorRetainage held, released and net payment on a pay app.
- PlatformRetainage tracking (use case)How os.construction handles retainage tracking on one record.
Want this on live job data?
In os.construction, pay apps calculate retainage at the application’s rate, with separate rates for work and stored materials and a Retainage Released line, and sub invoices withhold retainage at each commitment’s rate.
14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →
General information, not legal or accounting advice. The job and every figure on this page are illustrative. Retainage rates, reductions, punch list holdbacks, release deadlines and flow-down rules depend on your contract and the law where the project is.