Esc

↑↓ move↵ openIndex · Pagefind
Billing

Retainage

Definition

A percentage of each progress payment that the owner (or GC) holds back until the work is substantially or finally complete.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

Updated

Retainage on one pay application, and when it comes backA bar for work billed this period, $2,310,400, split into the payment for this period's work, $2,079,360, and 10 percent retainage, $231,040. Retainage from every pay app accumulates, $3,300,000 held to date on the sample job. Most is released at substantial completion, less a hold for open punch work, and the balance at final completion.PAY APP #9 · 10% RETAINAGEBilled $2,310,400Paid now $2,079,360Held $231,040HELD TO DATE$3,300,000Substantialmost released,less punch holdFinalbalance aftercloseoutIllustrative sample data.
Retainage is earned money held back on every pay app, then released at substantial and final completion under the contract terms.

Retainage is a percentage of each progress payment that the owner holds back from the contractor, and the contractor holds back from its subcontractors, until the work is substantially or finally complete. It is money already earned, withheld as security that the work will be finished and defects fixed. The contract sets the rate and release terms, within any limits set by law.

In the UK the same practice is called retention (or retention money), and in Canada the statutory version is called holdback. The mechanics look alike on a pay application, but the rules behind them differ, so check which one your contract and jurisdiction use.

How it works

  1. The contract sets the rate. The owner-contractor agreement (on AIA forms, the A101 or A102 agreement) states the retainage percentage, often separately for completed work and for stored materials, and any reduction point.
  2. Each pay app withholds it. On the G702 and G703, retainage is calculated on work completed and materials stored to date. The current payment due is the earned amount less retainage, less what was paid before.
  3. The contractor flows it down. Subcontracts usually withhold at the same rate or higher, so the GC is not paying subs money it hasn’t received.
  4. It may reduce. Many contracts drop the rate, for example from 10% to 5%, at 50% complete, or stop withholding further retainage at that point.
  5. It is released. At substantial completion the owner usually releases retainage less an amount for open punch and nonconforming work, and the rest at final completion once closeout is done. The contractor bills it as a retainage release.

Retainage, retention and holdback

Retainage (US) Retention (UK) Holdback (Canada)
Source of the rule Contract, capped by many state statutes and, on federal work, FAR Contract (for example JCT); no general statutory scheme Provincial lien statute, plus any contract holdback
Typical rate 5% to 10% JCT default 3% unless the particulars state another rate 10% basic holdback in Ontario (s. 22), with similar rules in other provinces
Main release point Substantial completion, then final completion Half at practical completion, half at end of rectification period Tied to substantial performance or completion and the lien period
What it secures Completion and correction of the work Completion and defects Lien claimants’ rights, not only the owner’s

The key difference is Canadian holdback. It is mandatory under the lien statute and protects subcontractors and suppliers who could otherwise lien the property. US retainage and UK retention are mostly contractual security for the owner.

Why it matters

Retainage is earned revenue sitting on someone else’s balance sheet. On a thin-margin job it can be larger than the entire profit, so a contractor can show a healthy job on the income statement and still be short of cash. It has to be tracked as retainage receivable and retainage payable, apart from ordinary AR and AP, so forecasts don’t count it as cash before it is released.

It is also a lever at closeout. The owner holds it until punch and closeout documents are done, and the GC holds its subs’ retainage until their work and paperwork are in. A late punch list or a missing final lien waiver can keep the money held for months.

Worked example

Illustrative, using Riverside Medical Center Pay App #9 sample data. Work completed and stored this period is $2,310,400. At 10% retainage:

  • Retainage this period: $2,310,400 × 10% = $231,040
  • Payment for this period’s work before prior-payment adjustments: $2,310,400 − $231,040 = $2,079,360
  • Retainage held to date on $33,000,000 completed and stored: $3,300,000

The GC withholds 10% from its subcontractors on their share of that work. If the contract dropped retainage to 5% at 50% complete, the same period would withhold $115,520 instead. Try your own numbers in the retainage calculator.

To see what retainage, owner payment terms and pay-when-paid do to a job month by month, use the construction cash flow projection template, which finds the peak cash need on an S-curve.

Common mistakes

  • Counting retainage as cash. It belongs at the substantial and final completion milestones in a cash forecast, not next month.
  • Not tracking retainage payable. Subs’ retainage comes due at closeout, and it should not be a surprise.
  • Missing the release triggers. Reduction at 50%, partial release at substantial completion and statutory deadlines all need someone to bill them.
  • Withholding more than the law allows. Many states cap rates and set prompt release deadlines, especially on public work. Excess withholding can carry interest or penalties.
  • One rate where the contract has two. Some contracts set different rates for completed work and stored materials.

This is general information, not legal advice. Retainage, retention and holdback rules vary by state, province and contract; check your contract and local law.

In Canada the equivalent is a statutory holdback; Ontario requires 10% at every tier and now releases it annually on longer contracts. See holdback vs retainage.

How os.construction handles it

Payment applications calculate retainage per G703 line, with separate work and materials retainage rates when the contract calls for them, and record any retainage released in a period. In Accounting, retainage is tracked in separate ledger accounts on the AR and AP sides; see Accounts receivable and Accounts payable. The concept page Pay apps, SOV and retainage walks through Pay App #9 in full.

Watch the explainer · 2:10

Retainage explained: held, billed and released

  1. 0:00Earned, but held back
  2. 0:20How it's held on a pay app
  3. 0:40One illustrative pay app
  4. 1:04Flow-down and reductions
  5. 1:26Release at completion
  6. 1:47Retainage in os.construction
Read the transcript

Retainage is the share of each progress payment the owner holds back until the work is substantially complete, commonly five to ten percent. It's money you've already earned, held as security that the job gets finished and defects get fixed. The contract sets the rate, within any limits set by law.

On a pay app, retainage is held on the cumulative amount: work completed to date times the retainage rate, plus stored materials times the stored-materials rate. Payment due is completed and stored, less retainage, less previous certificates. So this period's retainage is the change in that running total.

Here's the sample Riverside job, Pay App number nine. Thirty-three million dollars is completed and stored to date. At ten percent, three point three million is held. Less twenty-seven point six million previously certified, the payment due is about two point oh eight million. This period's two point three one million of work added two hundred thirty-one thousand of retainage.

The GC usually withholds the same rate or more from its subs, so it isn't paying out money it hasn't received. Many contracts drop the rate, say from ten percent to five, once the job is fifty percent complete. Read the contract: it decides whether the lower rate applies only to work after the milestone, or to everything completed.

Release usually comes in a billing at substantial completion, less an amount held for punch list and closeout items. The rest follows at final completion, once closeout documents and final lien waivers are in. Many states cap retainage and set release deadlines, especially on public work. General information, not legal advice.

In os.construction, pay applications calculate retainage on every line, with separate rates for work and stored materials, and record retainage released. Accounting tracks retainage receivable and payable apart from ordinary receivables and payables.

FAQ

What is retainage in construction?

Retainage is a percentage of each progress payment that the owner withholds from the contractor, and the contractor withholds from its subcontractors, until the work is substantially or finally complete. It is earned money held as security that the contractor will finish the job and correct defects. The contract sets the rate and the release terms, within any limits set by law.

What is a typical retainage percentage?

Rates of 5% to 10% are common in the US, and many contracts reduce the rate once the job is about half complete. Many states cap retainage on public work and some on private work too. On federal construction, FAR 32.103 caps retainage at 10% and says it should be withheld only when progress is not satisfactory.

When is retainage released?

Usually at substantial completion, less an amount held for open punch list and nonconforming work, with the balance at final completion. Release often depends on closeout items such as final lien waivers, consent of surety and warranties. Some contracts and statutes require partial release earlier, for example when a subcontractor's scope is finished.

Is retainage the same as retention?

Yes. Retention is the UK term for the same practice. Under JCT contracts the default retention rate is 3% unless the contract particulars say otherwise, with half usually released at practical completion and half at the end of the rectification period. In Canada, statutory holdback under provincial lien acts plays a similar role.

How is retainage recorded in accounting?

A contractor records retainage it is owed as retainage receivable and retainage it holds from subcontractors as retainage payable, separately from ordinary receivables and payables. It is billed and recognized as revenue, but it is not cash until released, so cash forecasts should place it at the release milestone.

Sources

See it in the app

Retainage in os.construction

Pay apps calculate retainage per line, with separate work and materials rates and any retainage released. Read the guide: Payment applications.

  1. 1Billed
  2. 2Retainage held
  3. 3Released
  4. 4Paid

Try it on the sample project in a free trial.

Start free trial Sign in
Open file