Resource Usage Profile

Definition

A time-phased chart of a resource's planned and remaining units or cost per day, week or month, often with cumulative curves and the resource's limit, used to spot over-allocation.

Topic: Scheduling

A resource usage profile spreads each assignment’s units or cost over the working days its activity spans, then adds them up per interval for one resource or a group. Bars show the amount in each interval; cumulative curves show the running total; and a limit line shows the resource’s maximum units per time. Intervals above the limit are over-allocated. The resource usage spreadsheet shows the same figures as a table.

How an assignment spreads over its span depends on its curve. A linear curve spreads evenly; bell-shaped, front-loaded or back-loaded curves weight the middle, start or end, while keeping the total the same.

Worked example

Illustrative: an electrical crew can work 10 units a day. Two overlapping activities each assign 6 units a day during the week of 9 November, so the weekly profile shows 60 units against a limit of 50, marked over-allocated. Moving one activity a week later, within its float, brings both weeks under the limit.

Why it matters

A schedule can be logically correct and still impossible to staff. The usage profile shows where demand outruns the crew, equipment or budget you actually have, before the field finds out.

How os.construction handles it

Resource Usage in the Planner shows the profile or spreadsheet of the selected activity’s resources, or any you choose, in units or cost by day, week or month. It phases over the last calculated dates and the activity calendar, applies assignment curves, and marks intervals where daily remaining units exceed the resource’s limit. Retained resource histograms and leveling proposals are separate. See Resources and costs.