The duration type tells P6 what to recalculate when you change one of an assignment’s three linked values: duration, units and units per time, where units = duration × units per time. It holds some of them steady and works out the other.
Worked example
Illustrative: a task has 80 hours of labor at 8 hours per day over 10 days. You raise the units per time to 16 hours per day.
- Fixed Units: units stay at 80, so the duration drops to 5 days.
- Fixed Duration and Units/Time or Fixed Duration and Units: duration stays at 10 days, so units rise to 160 hours.
- Fixed Units/Time: the new rate stays, and the units or duration are recalculated to match it.
Why it matters
The same edit can shorten an activity, raise its cost or leave its dates alone, depending on the duration type. Schedulers who don’t check it are surprised when a resource change moves the critical path, or when it doesn’t.
Common mistakes
- Expecting a duration-type change on its own to move dates.
- Leaving a Fixed Duration type on effort-driven work, so adding a crew raises the cost instead of shortening the work.
- Editing units on a Fixed Duration activity and expecting the duration to change.
How os.construction handles it
The Planner applies P6’s rules when you edit units, duration or units per time in Activity Details or the Assignments view, and the duration type round-trips through XER and P6 XML. The calculation reads stored durations, as P6 does. See Duration types.
FAQ
What are the four duration types?
Fixed Duration and Units/Time, Fixed Duration and Units, Fixed Units, and Fixed Units/Time. Each one holds some of duration, units and units per time steady and recalculates another when you edit one of them.
Does the duration type change scheduled dates?
Not directly. The schedule calculation reads the stored durations. The duration type acts when units, duration or units per time are edited, and the resulting duration is what the calculation then uses.
Which duration type suits crew-driven work?
Fixed Units is common when the total effort is known and adding resources should shorten the work. Fixed Duration types suit work with a set time window, such as curing or a hire period.