A three-week look-ahead that clears constraints first.
The master schedule says what has to happen. The look-ahead says who does it in the next three weeks, where, and what has to be cleared first: the RFI, the submittal, the delivery, the inspection.
Three-week look-ahead template
os.construction · free template- Project
- Week starting
- Prepared by
- Master schedule data date
Activities
| Activity | Area | Trade / crew | Start | Finish | Week 1 | Week 2 | Week 3 | Constraints to clear | Status |
|---|---|---|---|---|---|---|---|---|---|
| L2 east interior framing (SAMPLE · delete this row) | L2 east | Framing | X | X | None | On track | |||
| L2 east MEP rough-in | L2 east | Mech / elec / plumb | X | X | RFI-212 answer; damper delivery | At risk | |||
| L1 slab-on-grade pour, area C | L1 area C | Concrete | X | Pre-pour inspection; under-slab sign-off | On track | ||||
Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/three-week-look-ahead
Using the three-week look-ahead template
- Start from the current master schedule. Pull every activity that starts, runs or finishes in the next three weeks.
- Break each one down to the level a foreman plans at: an area, a crew, the days it runs.
- For each activity list what must be true before it can start: answered RFIs, approved submittals, material on site, inspections passed, the previous trade out of the way.
- Review it with the trades every week, in the coordination meeting, and give every constraint an owner and a date.
- Roll it forward one week at a time. Anything that slipped goes back to the scheduler to update the master.
- Master scheduleKept by the scheduler
- Three-week look-aheadActivities by area and crew
- Constraints clearedRFIs, submittals, deliveries, inspections
- Weekly coordination meetingTrades commit to the week
- Progress recordedSlips go back to the masterRoll forward: back to “Three-week look-ahead”
Text version
- Master schedule: Kept by the scheduler
- Three-week look-ahead: Activities by area and crew
- Constraints cleared: RFIs, submittals, deliveries, inspections
- Weekly coordination meeting: Trades commit to the week
- Progress recorded: Slips go back to the master
Roll forward: from “Progress recorded” back to “Three-week look-ahead”.
Do this in os.construction instead of a spreadsheet
The Schedule tool in os.construction imports a Primavera P6 XER or Microsoft Project XML file and shows it as a 3-Week Lookahead: activities grouped into This Week, Next Week and Week After, flagged Overdue or At Risk. Supers update percent complete and actual dates on each activity, submittals can be linked to the activity they feed, and each new import becomes a new revision. Import is one way: keep the master in your scheduling tool.
Try it on the sample project
Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.
Questions about the three-week look-ahead template
What is a three-week look-ahead?
A short-range schedule pulled from the master schedule that shows the next three weeks of work in enough detail for the field to plan crews, deliveries and inspections.
Who prepares the look-ahead?
Usually the superintendent, with the trade foremen, from the scheduler’s current master schedule.
What are constraints?
Anything that has to be true before an activity can start: an answered RFI, an approved submittal, material on site, a passed inspection, access from the previous trade.
How is it different from the master schedule?
The master schedule covers the whole job at activity level and is the contract record. The look-ahead is a working tool for the next few weeks, at the level the field plans.
Can I edit the schedule in os.construction and send it back to P6?
No. Import is one way: keep the master in your scheduling tool and re-import each update.
Keep going
- GlossaryCritical Path
- GlossaryFloat
- GlossaryLook-Ahead Schedule
- Free resourceMeeting minutes template
- TemplatePunch list template
- TemplateMeeting minutes template
- TemplateInspection checklist starter pack
- TemplateT&M ticket template
- TemplateRFI writing checklist
- TemplateDaily log checklist
- TemplateChange event log
- TemplateSafety observation log
- TemplateAction item tracker
Keep exploring
Related across os.construction
- DocsSchedule: import, look-ahead and GanttImport a P6 XER or Microsoft Project XML schedule, read it as a list, 3-week look-ahead, calendar or Gantt, and update progress on each activity.
- PlatformRole guide: SuperintendentA superintendent’s week in os.construction.
- ExplainerThe 3-week look-ahead: catching overdue and at-risk workRun the weekly look-ahead in os.construction: read Overdue and At Risk flags, move the data date, update progress, and take the right list to the meeting.
- PlatformCourse: run your first projectSeven 10-minute lessons on the sample project: RFIs, daily log, meetings, punch, changes and pay apps.
- Free toolMeeting minutes templateFree OAC and weekly meeting minutes template.
- Free toolDaily log checklistFree daily report checklist for superintendents.