Esc

↑↓ move↵ openIndex · Pagefind
Project management

Float

Definition

Calculated timing flexibility: total float relates to the schedule's late-date limit; free float relates to a successor's early start.

Topic: Scheduling

Updated

Total float and free float on a side pathA bar chart on a scale of 0 to 42 working days. C, utilities, runs days 5 to 13 with 11 days of total float and no free float. E, slab, runs days 13 to 19, followed by 11 days of float to day 30, so it has 11 days of total and free float. D, steel, runs days 15 to 30 and F, finish, runs days 30 to 42; both are critical with zero float. A dashed line at day 30 marks where D finishes and F can start, which is where the float on the C and E path runs out. C and E share the same 11 days.C UtilitiesTF 11 · FF 0E SlabTF 11 · FF 11D SteelcriticalF Finishcritical013193042C and E share one 11-day window.Slip C 4 days: finish holds, 7 left.
Float on a side path is shared, and it ends where the critical path picks the work up. Illustrative, working days.

Float is the amount of time an activity can slip, under the schedule’s calculation rules, before it affects something else. Total float is the slack before an activity delays the project finish or another late-date limit. Free float is the slack before it delays the early start of any successor. Activities with zero or negative total float are critical.

In a simple unconstrained network, total float describes how much an activity can move before delaying project completion. Constraints and multiple calendars can complicate that interpretation. Free float is always the narrower measure: an activity can have positive total float and no free float, because moving it would affect another activity before affecting completion.

How float is calculated

Float comes out of the critical path method:

  • A forward pass gives each activity its early start (ES) and early finish (EF).
  • A backward pass from the finish gives late start (LS) and late finish (LF).
  • Total float = LF − EF, which equals LS − ES.
  • Free float = the earliest ES of the activity’s successors − its own EF.

Scheduling software reports both in working days on the activity’s own calendar, so a day of float on a five-day calendar and a day on a seven-day calendar are not the same length of time.

Worked example

Illustrative: a small building shell, durations in working days, all finish-to-start.

Activity Duration ES EF LS LF Total float Free float
A Site work 5 0 5 0 5 0 0
B Foundations 10 5 15 5 15 0 0
C Underground utilities 8 5 13 16 24 11 0
D Steel frame 15 15 30 15 30 0 0
E Slab on grade 6 13 19 24 30 11 11
F Enclose and finish 12 30 42 30 42 0 0

C and E sit on a side path (A, C, E, F) that is 31 days long against a 42-day critical path, so both show 11 days of total float. That float is shared. It is not 11 days for C plus 11 days for E.

Free float tells the difference between them. C has zero free float: if it slips one day, E’s early start slips one day too. E has 11 days of free float: its only successor, F, can’t start until day 30 anyway, because the steel frame (D) finishes then.

So if C slips 4 days, E moves to days 17 to 23 and the finish stays at day 42, but the side path now has 7 days of total float left. If C slips 13 days, E finishes at day 32, F starts at day 32 and the finish moves 2 days to day 44.

These numbers assume the logic, durations and calendar stay as modeled. Work your own network, with every step written out, in the free critical path and total float calculator.

Negative float

When a schedule has a constraint, such as a contract completion date, the backward pass starts from that date instead of the calculated finish. If the forecast finish is later than the constraint, late dates come before early dates and total float goes negative. Minus 10 days of total float on an activity means its path is forecasting 10 working days late against that constraint. Negative float is a warning to plan a recovery or raise a time question, not a calculation error.

Why it matters

Float is a result of the whole network, not an independent allowance to spend on every activity. Activities on the same path share the same timing flexibility, and float changes between updates as progress, durations, constraints, calendars and logic change. A path with a few days of float can become critical after one slow month, which is why look-ahead schedules should watch near-critical work as well as the critical path.

The calculation does not establish who owns float or who may use it. Those questions depend on the contract and its interpretation. Neither positive float nor negative float determines a right to time or money by itself; that takes an analysis such as a time impact analysis and the contract’s terms.

Common mistakes

  • Adding the float of consecutive activities as if each were a separate buffer.
  • Assuming all zero-float activities form the driving path.
  • Reading float without checking which calendar it is measured on.
  • Ignoring the milestone, calendar or constraint that produced a float value.
  • Using constraints to hold activities in place, which manufactures float values that logic doesn’t support.
  • Treating a float calculation as an ownership or entitlement decision.

How os.construction handles it

The schedule Planner calculates total float and free float in working days for every activity, and the activity grid can sort and filter activities by total float. CPM analytics in Insights counts open work by float band across projects. Explore the interactive lab and the total float versus free float guide for a deeper explanation.

Watch the explainer · 1:53

Critical path and float in 2 minutes

  1. 0:00What sets the finish date
  2. 0:16An illustrative network
  3. 0:36The forward pass
  4. 0:57The backward pass
  5. 1:13Total float and free float
  6. 1:33Run it on your schedule
Read the transcript

The critical path is the chain of activities that sets the finish date. Delay one of them, and the finish moves by the same amount. To find it you need three things: the activities, their durations, and the logic of what waits for what.

Take an illustrative five-activity job. Foundations take three days. Then two paths run side by side: steel frame, six days, and underground utilities, two days, followed by a two-day utility inspection. The roof takes two days, and it waits for both paths.

The forward pass finds the earliest dates. Each activity starts when its last predecessor finishes, and early finish is early start plus duration. Steel finishes at day nine. The utility inspection finishes at day seven. The roof waits for the later one, so it starts at nine and finishes at eleven. The job takes eleven days.

The backward pass works back from day eleven to find the latest dates. The roof must start by day nine, so the inspection must finish by nine and start by seven, and the utilities must start by day five. One calendar, no date constraints.

Total float is late start minus early start. Foundations, steel and the roof have zero, so they're the critical path. The utility work has two days of total float, but it's shared. The utilities have no free float, because any slip pushes the inspection. The inspection has two days of free float.

Try your own activities in the free critical path calculator, which writes out every step of the math. In the os.construction schedule, the Planner calculates total and free float for every activity, and the longest path.

FAQ

What is float in a construction schedule?

Float is the amount of time an activity can slip under the schedule's calculation rules before it affects something else. Total float is how far it can slip before delaying the project finish or another late-date limit. Free float is how far it can slip before delaying the early start of any successor. Critical activities have zero or negative total float.

How do you calculate total float?

Total float equals late finish minus early finish, or late start minus early start. The early dates come from a forward pass through the network and the late dates from a backward pass from the finish. Scheduling software calculates it for every activity in working days on that activity's calendar.

What is the difference between total float and free float?

Total float measures slack against the project finish (or another late-date limit). Free float measures slack against the very next activities. An activity can have plenty of total float and zero free float: moving it would push its successor's early start, even though the project finish is still safe because the successor has float too.

What does negative float mean?

Negative float means the schedule's calculated dates can't meet a constraint, usually a contract completion date or milestone. An activity with minus 10 days of total float is forecasting 10 working days late against that constraint. It signals that the plan needs recovery or that a time extension question needs to be addressed.

Who owns float in a construction schedule?

It depends on the contract. Some contracts say float belongs to the project and is available to whichever party uses it first. Others reserve it for the owner or the contractor, or require float to be shown as a separate activity. Without a clause, practice and case law vary, so the calculation alone doesn't settle ownership.

Sources

Open file