Scheduling / CPM analytics in Insights: schedule performance across projects

CPM analytics in Insights: schedule performance across projects

The Schedule performance (CPM) pack turns every project's saved CPM calculation into critical, near-critical and negative-float counts, float bands, baseline variance, DCMA score and version trends, at project and portfolio scope.

On this page

The Schedule performance (CPM) pack in Insights reads the CPM calculations already saved in each project’s Planner. It never re-runs the engine. It turns them into metrics you can chart, filter, alert on and compare across a portfolio. Open it from Insights at company scope for every project, or from a single project.

What it measures

21 metrics, each calculated per project:

Area Metrics
Criticality Activities, open activities, critical, near-critical (1 to 10 working days of float), negative float
Float distribution Open activities by total float band: negative, zero, 1–10, 11–44, 45+ days, or not calculated
Against the baseline Started late, finished late, forecast late, and finish variance in calendar days
Progress Duration and earned duration in days, and duration-weighted percent complete
Hygiene Milestones due, open ends, constraints, data-date age
Health DCMA health score, failed checks, and the grade by project
Trends Critical activities, negative float and finish variance by saved version, over the last 24 versions

The baseline is the project’s most recent baseline of kind project, read from that version’s original saved calculation. Health comes from the latest saved DCMA health analysis of the current version. Without a baseline, the baseline figures are blank. Without a health analysis, health is blank. Neither is ever shown as zero.

Open activities by total float bandIllustrative sample data
Show the data as a table
Open activities by total float band (Illustrative sample data)
ItemActivities
Negative4
Zero27
1–10 days41
11–44 days88
45+ days19

The pack

  • Two KPI rows: critical, near-critical, negative float, finish against the baseline, percent complete and DCMA score; then forecast late, started late, finished late, milestones due, open ends and constraints.
  • Float distribution, and the critical path trend by month calculated.
  • A baseline variance table and a portfolio attention table, with finish variance bars highlighted past your slip threshold.
  • DCMA grades by project and the critical path by version.
  • Slip history from nightly snapshots, a slip against critical scatter and data-date age.

The finish-slip insight

The schedule_cpm_finish_slip rule raises a finding when a project’s calculated finish is later than its baseline by more than the company’s schedule slip days setting. It’s raised as critical when negative float is present.

  • Schedule analysis runs the health, risk, earned schedule and compare analyses behind these numbers.
  • Analytics and BI covers dashboards, Explore, alerts and sharing.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file