CPM analytics in Insights: schedule performance across projects
The Schedule performance (CPM) pack turns every project's saved CPM calculation into critical, near-critical and negative-float counts, float bands, baseline variance, DCMA score and version trends, at project and portfolio scope.
The Schedule performance (CPM) pack in Insights reads the CPM calculations already saved in each project’s Planner. It never re-runs the engine. It turns them into metrics you can chart, filter, alert on and compare across a portfolio. Open it from Insights at company scope for every project, or from a single project.
What it measures
21 metrics, each calculated per project:
| Area | Metrics |
|---|---|
| Criticality | Activities, open activities, critical, near-critical (1 to 10 working days of float), negative float |
| Float distribution | Open activities by total float band: negative, zero, 1–10, 11–44, 45+ days, or not calculated |
| Against the baseline | Started late, finished late, forecast late, and finish variance in calendar days |
| Progress | Duration and earned duration in days, and duration-weighted percent complete |
| Hygiene | Milestones due, open ends, constraints, data-date age |
| Health | DCMA health score, failed checks, and the grade by project |
| Trends | Critical activities, negative float and finish variance by saved version, over the last 24 versions |
The baseline is the project’s most recent baseline of kind project, read from that version’s original saved calculation. Health comes from the latest saved DCMA health analysis of the current version. Without a baseline, the baseline figures are blank. Without a health analysis, health is blank. Neither is ever shown as zero.
Show the data as a table
| Item | Activities |
|---|---|
| Negative | 4 |
| Zero | 27 |
| 1–10 days | 41 |
| 11–44 days | 88 |
| 45+ days | 19 |
The pack
- Two KPI rows: critical, near-critical, negative float, finish against the baseline, percent complete and DCMA score; then forecast late, started late, finished late, milestones due, open ends and constraints.
- Float distribution, and the critical path trend by month calculated.
- A baseline variance table and a portfolio attention table, with finish variance bars highlighted past your slip threshold.
- DCMA grades by project and the critical path by version.
- Slip history from nightly snapshots, a slip against critical scatter and data-date age.
The finish-slip insight
The schedule_cpm_finish_slip rule raises a finding when a project’s calculated finish is later than its baseline by more than the company’s schedule slip days setting. It’s raised as critical when negative float is present.
Related
- Schedule analysis runs the health, risk, earned schedule and compare analyses behind these numbers.
- Analytics and BI covers dashboards, Explore, alerts and sharing.
Keep exploring
Related across os.construction
- GlossarySchedule BaselineA preserved reference plan used to compare later progress and forecast dates against the agreed planning basis.
- DocsSchedule: CPM planning, field tasks and the look-aheadPlan the project in a native critical path Planner or bring in a P6 or Microsoft Project file, then publish reviewed dates to the field task list your team reads as a list, 3-week look-ahead, calendar and Gantt.
- GlossaryCritical PathThe driving sequence of activities that determines a selected completion milestone under the schedule's logic, calendars, and settings.
- DocsGet started with the schedule PlannerCreate a CPM plan, add activities, logic and a calendar, save and calculate your first version, then read the critical path and run a health check.
- Free toolCritical path calculatorForward and backward pass, total and free float and the critical path for your activities, with every step shown.
- ExplainerHow the critical path worksForward pass, backward pass and float on an eight-activity network, then one slip moves the critical path.
Was this helpful?
Run it on your own project.
Start a 14-day free trial. Want a say in what ships next? Join the founding program.
14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →