Scheduling / Scheduling: CPM planning, analysis and evidence in one workspace

Scheduling: CPM planning, analysis and evidence in one workspace

A native critical path scheduling workspace with a P6-validated engine, P6-style layouts and views, Line of Balance and takt planning, Last Planner weekly work plans, activity discussion and a change feed, P6 import options, DCMA health, three-point risk, a reviewed update cycle, portfolio programs, reports, baselines, versions, resources, costs and period performance.

On this page

Scheduling in os.construction is a critical path method (CPM) workspace built into the project, not a file passed around beside it. You build the network: activities, a WBS outline, calendars, all four relationship types with lags and leads, and P6-style constraints. You record progress against a data date. A calculation engine cross-validated against Primavera P6 then works out every early and late date, total and free float, and the longest path. Each saved calculation is kept as an immutable version you can baseline, compare, analyse and explain.

Who
Schedulers, project controls, PMs and owners’ reviewers
Where
Project Tools › Schedule: Overview, Plan, Update, Analyze, Resources & cost, Import & export
Access
Schedule admin for full-network planning and analysis

The engine

The calculation engine runs in an isolated worker with no access to application data. Each request gets an authorized snapshot of the saved plan. The engine is the original scheduling code, adopted byte for byte with checksums, not a simplified rewrite. Its development suite compares its dates with P6’s own stored answers. On the P6 23.12 cross-validation fixture, 156 of 160 date comparisons match, and each known difference is documented in the engine source with the reason it remains.

The engine understands what P6 schedulers rely on:

  • Four relationship types: finish-to-start, start-to-start, finish-to-finish and start-to-finish, with positive lags and negative leads.
  • Ten constraint types, primary and secondary: start on, start on or after, start on or before, finish on, finish on or after, finish on or before, as late as possible, mandatory start, mandatory finish, and none. Plus a project must finish by date.
  • Progress modes: retained logic (the default), progress override and actual dates, read from P6 project settings on import.
  • Scheduling options: lag calendar, data date convention, total float method, expected finish dates and make open-ended activities critical, measured against P6 23.12, plus suspend and resume of started work.
  • Resource-dependent activities, each driving assignment on its own resource calendar with its assignment lag and P6’s Drive Activity Dates flag, and units % complete carried through import and export.
  • Calendars with working weekdays, hours per day and named exceptions.
  • Activity kinds: tasks, start and finish milestones, level of effort and WBS summaries, with level-of-effort and summary dates derived from the work they span.
  • Time precision: whole days or exact working minutes, detected automatically from the file. Agreement with P6 on 39 real projects rises from 81.5% to 87.6% of compared values with it on.
  • P6 cost, units and earned value fields: roll-ups by resource type with expenses included, cost and units % complete, baseline variances and P6’s earned value indices. On 34 projects, 98.7% of the costs and units P6 stored agree. See P6 compatibility.
  • Scale: up to 30,000 activities per schedule. A 19,000-activity programme imports in about 10 seconds or less, at about half the peak memory of the previous release, and calculates in about 5. Above 2,000 activities the Planner loads a lean plan, about 10 MiB at 25,000 activities, and saves only what changed.

What you can do

Get started
Create a plan, add activities and logic, save and calculate your first version.
Read →
Create a schedule
Start from a shipped or company template, a blank plan, a copy, a P6 file or field tasks, with durations adjusted by lessons learned.
Read →
Planning and CPM
Activities, WBS, calendars, relationships, constraints, progress and the data date.
Read →
Activity grid and Gantt
Quick filters, longest-path focus, bar dragging and why-this-date traces.
Read →
Views and layouts
Classic Schedule, layout files, filters, Group & Sort, timescales, bars, baselines, the progress line, Network, Trace Logic and Assignments and the WBS window.
Read →
Editing and progress tools
Fill down, Excel paste and round-trip, Global Change, Progress Spotlight and the schedule log.
Read →
Location-based planning
Line of Balance flowlines with conflicts, buffers and crossings, and takt plans with adherence.
Read →
Activity details and P6 fields
Codes, UDFs, steps, notebooks, feedback, linked documents, expenses and assignments with duration-type rules.
Read →
WBS and hierarchy
Build the WBS outline, place activities under it, roll it up in the WBS window and publish the hierarchy to field tasks.
Read →
Touch view
Cards, a pinch-and-pan Gantt that follows your layout, and quick progress on a phone or tablet.
Read →
Field mode (offline)
Keep a project’s schedule and lookahead on a phone, record progress without signal and sync it as one version.
Read →
Schedule analysis
DCMA 14-point health, Monte Carlo risk, earned schedule SPI(t) and compare.
Read →
Risk analysis
Three-point estimates, a risk register, correlation, mitigation and weather.
Read →
Last Planner
Weekly work plans from the lookahead, make-ready commitments, PPC and reasons for variance.
Read →
The update cycle
Checks, narrative, multi-step review, updates of record, forensic windows, prospective TIA and submittals.
Read →
Working together
Activity discussion with @mentions, presence, the change feed and rebasing edits after a conflict.
Read →
Baselines and versions
Name baselines, overlay them, diff any two versions and check conformance.
Read →
P6 and Project import
Bring in XER, P6 XML and Microsoft Project XML, adopt it, or update the current plan with P6 import options.
Read →
P6 compatibility
Settings, export, what round-trips, how we verify and the limits that remain.
Read →
Large schedules
30,000 activities, lean loading and patch saves, Auto/Days/Minutes precision and background jobs.
Read →
Security and accessibility
What the Schedule security review found and fixed, the tests that guard every route, and the WCAG 2.2 AA audit.
Read →
Resources and costs
Assignments, Resource Usage, cost loading, cost accounts to cost codes, Budget reconciliation, P6 leveling options and workforce capacity.
Read →
Period performance and earned value
Financial periods, Store Period Performance, earned value columns and P6’s EV and ETC techniques.
Read →
Reports and printing
Twelve reports, a tiled print Gantt, scheduled emails and the opt-in assistant.
Read →
CPM analytics in Insights
Critical, near-critical, float bands, finish variance and DCMA grade across projects.
Read →
Portfolio and programs
Every schedule, several projects open at once, inter-project links, a program calculation with per-project options and cross-project leveling.
Read →
Schedule API
Every planning, calculation and analysis operation over REST.
Read →

How the pieces fit

Every view and report points at one saved version

Everything downstream reads a saved version, never an unsaved draft. When a report, trace or analysis says “version 12”, it means one exact, digest-verified definition and the calculation saved with it. That’s what makes the evidence hold up later: you can show what the schedule said on the day you said it.

Status

Scheduling is live. Everything in this section runs in the app today, and each guide states its own limits. Most capabilities have local release evidence, including browser journeys and contract tests. Authenticated production acceptance is still being recorded for several of them. Line of Balance, takt planning, Last Planner, discussion, presence, the change feed, rebasing, the new Activity Details tabs, the WBS window and Open projects are covered by unit and service tests; browser acceptance journeys for them haven’t been written yet. The P6 view features still to come, such as exporting layouts to P6 .plf files, are listed under Views and layouts.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file