Percent plan complete (PPC) is commitments met divided by commitments made, for one week. It belongs to the Last Planner System, where the people who do the work agree each week what they will finish. PPC measures how reliable those promises are, not how much work was done: a crew can be productive and still have a low PPC if it keeps promising work it can’t do.
The formula is simple: PPC = commitments completed as promised ÷ commitments made × 100.
How it works
- Make ready. In the look-ahead, the team clears constraints so tasks are ready before they’re due.
- Commit. At the weekly planning meeting, each foreman commits to specific tasks from the ready work: what, where, and by when. The list becomes the weekly work plan.
- Freeze. Once the week starts, the commitments don’t change. New work can be added and done, but it isn’t counted in that week’s PPC.
- Assess. At the end of the week, each commitment is marked complete or not complete. There’s no partial credit.
- Record reasons. Every missed commitment gets a reason for variance from an agreed list.
- Calculate and chart. PPC is calculated for the week, often by trade too, and plotted as a trend.
- Learn. The team looks at the most common reasons and acts on the root causes, for example by tracking deliveries earlier or chasing RFIs sooner.
Worked example
Illustrative: the week of 3 March has 20 commitments. 16 are finished, 3 are missed because a delivery slipped, and 1 because an RFI answer came late. PPC is 16 ÷ 20 = 80%. Over eight weeks, materials is the top reason, so the team starts tracking deliveries in the lookahead.
The eight-week tally behind that decision (sample data), 172 commitments with 42 missed:
| Reason for variance | Misses | Share of misses |
|---|---|---|
| Materials | 15 | 36% |
| Prerequisite work | 10 | 24% |
| Information (RFIs, drawings) | 8 | 19% |
| Labor | 6 | 14% |
| Weather | 3 | 7% |
| Total | 42 | 100% |
Pooled PPC across the eight weeks is (172 − 42) ÷ 172 = 75.6%. Materials and prerequisite work together account for about 60% of misses, and both are constraints the look-ahead is meant to catch.
What makes a good commitment
PPC is only as meaningful as the commitments behind it. Ballard’s work on the Last Planner System sets out quality criteria for weekly assignments, which in practice come down to:
- Defined: specific enough that anyone can tell whether it was finished, with location and quantity.
- Sound: all constraints cleared, so the work can actually be done.
- Sequenced: in the right order for the work that depends on it.
- Sized: matched to the crew’s capacity for the week.
- Learning: misses are tracked to a reason so the next plan improves.
PPC vs related measures
| Measure | Question it answers | Basis |
|---|---|---|
| PPC | Did we do what we said this week? | Commitments met ÷ made |
| Percent complete | How much of the work is done? | Quantity, cost or duration |
| Schedule performance (SPI) | Is work done ahead of or behind plan, in value? | Earned value ÷ planned value |
| Tasks made ready | Is the look-ahead clearing constraints in time? | Tasks anticipated that became ready |
| Takt plan adherence | Are trades moving through zones on rhythm? | Zones finished on takt |
Why it matters
Reliable short-term planning is what makes the master schedule believable. A falling PPC is an early sign that work is being released before it is ready. The reasons for variance recorded against missed commitments, such as materials, information or prerequisite work, show which constraints to attack first.
Reliability also helps the next trade. When the crew ahead finishes what it promised, the following crew can plan its start with confidence, and less time is lost waiting for areas to open up.
Common mistakes
- Giving partial credit. A commitment is met or missed; “90% done” is missed.
- Changing the week’s commitments after it starts, which inflates PPC.
- Reporting an unassessed week as 100%, or an unplanned week as 0%. Both are unmeasured.
- Watching a single week instead of the trend.
- Committing to vague tasks, such as “work on level 3”, that can’t clearly be judged done.
- Using PPC to rank or punish crews, which teaches them to commit to less.
- Recording “other” as the reason so often that the reason data stops being useful.
How os.construction handles it
The Schedule Lookahead page holds a weekly work plan per week and reports PPC by week and by trade, with reasons for variance. Committing a week freezes its commitments, a missed commitment needs a reason, and a week with unassessed commitments has no PPC. See Last Planner.
FAQ
How do you calculate percent plan complete?
Divide the number of commitments completed as promised in a week by the number of commitments made for that week, and multiply by 100. A commitment counts only if it was fully finished; partly done work counts as missed.
What is a good PPC?
There's no universal target. Teams new to the Last Planner System often start low and improve as they get better at only committing to ready work. The trend and the reasons for variance matter more than any single week's number.
What is the difference between PPC and percent complete?
Percent complete measures how much of an activity or project is done. PPC measures whether the team did what it said it would do that week. A job can be well ahead on percent complete while PPC is low, if crews keep committing to work they then can't finish.
What are reasons for variance?
They're the recorded causes of missed commitments, grouped into categories such as materials, information, prerequisite work, labor, equipment, weather or a change in priorities. Counting them over several weeks shows which constraint causes the most misses, so the team can fix the system rather than blame a crew.
Who came up with PPC?
PPC is part of the Last Planner System of production control, developed by Glenn Ballard and Greg Howell and promoted by the Lean Construction Institute. Ballard's doctoral thesis at the University of Birmingham describes it in detail.