Topic · 46 terms

Construction scheduling: CPM, look-aheads and delay analysis

A construction schedule is a network of activities and logic. The critical path method finds the longest chain through it, and float says how far everything else can slip before the finish moves.

The terms here cover building the network (WBS, activity codes, calendars, logic), updating it (data date, progress, retained logic, out-of-sequence work), planning the near term in the field (look-aheads, weekly work plans, PPC, takt) and analysing delay (time impact analysis, windows analysis, pacing).

Read the guide: How the critical path works

Scheduling: terms defined

Project management

Critical Path

The driving sequence of activities that determines a selected completion milestone under the schedule's logic, calendars, and settings.

Project management

Float

Calculated timing flexibility: total float relates to the schedule's late-date limit; free float relates to a successor's early start.

Project management

Longest Path

The chain of driving relationships from the data date to the project finish; it can differ from the set of activities with zero total float.

Project management

Work Breakdown Structure

A hierarchy that breaks the whole scope of a project into smaller, manageable pieces of work, used to organize the schedule, the budget and progress reporting.

Project management

Activity Code

A user-defined classification, such as area, trade, phase or responsibility, assigned to schedule activities so they can be filtered, grouped and reported.

Project management

Schedule Calendar

The working-time rules a scheduling calculation uses to place activity durations on actual dates.

Project management

Duration Type

A P6 activity setting that decides which of duration, units and units per time is recalculated when one of the others is edited.

Project management

Schedule Baseline

A preserved reference plan used to compare later progress and forecast dates against the agreed planning basis.

Project management

Data Date

The status cutoff separating recorded progress from the remaining work forecast in a schedule update.

Project management

Update Period (Schedule Update)

The interval between two schedule data dates, usually a month, for which progress is recorded, checked, explained in a narrative and submitted for review.

Project management

Retained Logic

A progress setting where an out-of-sequence activity's remaining work still waits for its unfinished predecessors.

Project management

Progress Override

A progress setting that releases the logic into an out-of-sequence activity, so its remaining work continues from the data date.

Project management

Out-of-Sequence Progress

Recorded work that started or progressed before the schedule relationships would normally allow it.

Project management

Trace Logic

A small network diagram of one activity's predecessors and successors, a chosen number of levels deep, used to follow logic through a schedule.

Project management

Open-Ended Activity

An activity missing a predecessor or a successor, so the schedule logic leaves its start or finish free.

Project management

Expected Finish

A date the scheduler enters for when an activity is expected to finish; with the project's Use expected finish dates option on, the calculation fits the activity's remaining work to end on it.

Project management

Suspend and Resume

Dates that record a pause in started work: the suspend date when it stopped and the resume date when its remaining work restarts.

Project management

Weather Allowance

Working days a schedule sets aside for normal bad weather, usually by month and applied only to weather-sensitive work.

Project management

Look-Ahead Schedule

A short-range schedule, usually two to six weeks, that breaks the master schedule into the specific tasks crews will perform next.

Project management

Weekly Work Plan

The set of commitments each trade makes for the coming week in the Last Planner System, drawn from make-ready work in the lookahead and assessed at the end of the week.

Project management

Percent Plan Complete (PPC)

The share of a week's commitments that were finished as promised, used in the Last Planner System to measure how reliable short-term planning is.

Project management

Takt Time

The fixed time each trade gets in each zone in takt planning, so trades move through the building in a steady rhythm, like the carriages of a train.

Project management

Line of Balance

A location-based schedule chart that plots locations against time, with one sloped line per trade, so you can see each crew moving through the building and where two trades collide.

Project management

Program (Schedule)

A group of related projects whose schedules are linked and managed together, so a delay on one project can be traced into the others.

Project management

Three-Point Estimate

An activity duration given as optimistic, most likely and pessimistic values, used to describe uncertainty for schedule risk analysis.

Project management

Monte Carlo P80

The finish date that 80% of simulated schedule outcomes meet or beat in a Monte Carlo schedule risk analysis.

Project management

DCMA 14-Point Assessment

Fourteen schedule-quality screening metrics (logic, leads, lags, constraints, float, durations, dates, resources, missed tasks, CPT, CPLI and BEI) from DCMA guidance.

Project management

Earned Value Technique

The rule that decides how much of an activity's budget counts as earned at a given point of progress, such as percent complete, 0/100 or 50/50.

Project management

SPI(t)

Earned Schedule's time-based Schedule Performance Index: earned schedule divided by actual time. Below 1.00 means the work is behind the baseline.

Project management

Performance Factor

A multiplier applied to the budget of remaining work to estimate what it will actually cost: 1, a custom value, 1/CPI or 1/(CPI × SPI).

Project management

Units Percent Complete

Progress measured as actual resource units over the units expected at completion, across an activity's labor and nonlabor assignments.

Project management

Financial Period

A named date range, usually a month, that a schedule's actual units and costs are stored into, so cost performance can be reported per period rather than only to date.

Project management

Store Period Performance

A P6 action that records a schedule's actual units and costs, and earned and planned value, into a financial period, so per-period figures survive later updates.

Project management

Progress Line

A line drawn down a Gantt chart through the data date that bends out to each activity's progress point, showing at a glance which work is ahead of plan and which is behind.

Project management

Resource Usage Profile

A time-phased chart of a resource's planned and remaining units or cost per day, week or month, often with cumulative curves and the resource's limit, used to spot over-allocation.

Project management

Time Impact Analysis

A schedule modeling method that inserts an event into a selected schedule and compares the calculated milestone dates.

Project management

Prospective Time Impact Analysis

A forward-looking time impact analysis, done near the time of a delay event, that inserts an agreed fragnet into the current schedule update to estimate its effect on completion.

Project management

Windows Analysis

A retrospective delay analysis that measures how the forecast completion moved in each period between consecutive schedule updates, and why.

Project management

Pacing

A deliberate slowing of non-critical work in response to a delay on another path, so it isn't counted as concurrent delay.

Project management

Acceleration

Speeding up work to finish earlier than the current schedule allows, either because the owner directs it or because the owner denies a time extension the contractor was owed.

Contracts

Delay Claim

A documented request for contractual relief associated with delay, supported by records, schedule analysis, and the applicable contract.

Project management

Layout (Schedule View)

A saved arrangement of a schedule view: its columns, filters, grouping, sort, Gantt settings and panes, reusable by one person, a project team or the whole company.

Project management

Group & Sort

A schedule view setting that bands activities by WBS, activity code or any field, up to several levels, with totals per band and a sort order within each band.

Project management

Assignments View

A schedule view with one row per resource assignment across all activities, showing units, costs, rates, dates and curves, for reviewing and editing resource loading in bulk.

Project management

Progress Spotlight

A P6 view feature that highlights the activities that should have progressed between the current data date and a new one, as a guide for statusing.

Project management

User-Defined Field (UDF)

A custom field added to schedule activities, such as text, a number, a cost, a date or an indicator, for information the standard fields don't hold.