Esc

↑↓ move↵ openIndex · Pagefind

How to run a pull planning session: from milestone back to Monday

Pull planning has the trades plan a phase backwards from a milestone, one handoff at a time, so the sequence comes from the people doing the work. Here is how to prepare, who to invite, how to run the wall, how to turn it into a look-ahead, and a worked example for a floor of interior build-out.

Charley Forey6 min readSchedulingFieldProject coordination
On this page
  1. Step 1: Pick the milestone and the scope
  2. Step 2: Prepare
  3. Step 3: Invite the last planners
  4. Step 4: Build the wall backwards
  5. Step 5: Check the result against the milestone
  6. Step 6: Turn it into the look-ahead and track constraints
  7. Worked example: one floor of interior build-out
  8. Common mistakes
  9. How os.construction handles it
  10. FAQ

A pull planning session has the foremen of each trade plan a phase backwards from a milestone, one handoff at a time: each trade says what it needs finished before it can start, how long its work takes, and what could stop it. The GC facilitates, the trades own the cards, and the result becomes the sequence for the look-ahead and the constraints to clear before the work starts.

A master schedule written by one scheduler often has the right activities and the wrong handoffs. Drywall can’t start until the inspection is passed; the inspection can’t be called until the sprinkler mains are tested; the test needs the fire alarm interface. The foremen know those dependencies better than anyone. Pull planning gets them into the plan before the crews are standing around waiting.

Pull planning is the phase planning step of the Last Planner System, developed by Glenn Ballard and Greg Howell and promoted by the Lean Construction Institute. You don’t need the whole system to get value from the session, but it fits best when the output feeds a weekly work plan.

Step 1: Pick the milestone and the scope

Choose a milestone with a clear, physical definition: “Level 3 ready for ceiling close-in inspection”, “Building dried in”, “Level 1 turned over for owner furniture”. Agree what “done” means before the session, because the whole wall is built back from it.

Keep the scope to a phase people can see in their heads. A single floor, a single system or a few weeks to a few months of work is typical. Planning the whole job on one wall produces cards too vague to act on.

Step 2: Prepare

  • The milestone date from the master schedule, and the date the phase can start.
  • The drawings for the area, and the current master schedule activities for it.
  • A wall or a large board with a timeline across it, by week or by day, and a column for constraints. Some teams use a digital whiteboard instead of sticky notes; the method is the same.
  • Card colours by trade, so the sequence is easy to read from across the room.
  • A list of known constraints: open RFIs, submittals not yet approved, long-lead deliveries, inspections.

Step 3: Invite the last planners

The people who decide what their crew does each day: foremen and crew leads. Not the sub’s estimator, and not the PM alone. Add the superintendent and project engineer, and anyone who controls a constraint the phase depends on, such as the inspector’s scheduling contact or the design team for open questions, if they can attend.

Step 4: Build the wall backwards

  1. Put the milestone on the far right.
  2. Ask “what has to be finished right before this?” The trade that does that work writes a card: the task, its location, its duration in days, crew size, and what it needs before it can start.
  3. Keep pulling. For each card, ask what has to be done before it, and who does that. Each answer is a new card to its left, linked by a handoff.
  4. Make the handoffs explicit. A handoff is a promise from one trade to the next: “Area B ready for you on day 12”. The receiving trade says what “ready” means to it.
  5. Write constraints on the card, and also on the constraint list: the RFI, submittal, delivery, inspection or decision that has to happen first, and who owns it.

Work in conversation. When the drywall foreman says he can’t start until the mechanical inspection is signed off, the mechanical foreman hears it directly, not through the schedule.

Step 5: Check the result against the milestone

Once the wall reaches the start date, look at the result honestly:

  • If it finishes early, the team decides where to keep the spare days, usually as a buffer before the milestone, not spread into everyone’s durations.
  • If it doesn’t fit, look for overlap by area, crew changes, or constraints that can be cleared sooner. If it still doesn’t fit, take it to the project manager. Squeezing durations on the wall until they fit just moves the problem to the field.
  • Check the critical path. Make sure the phase still ties to the master schedule logic around it.

Step 6: Turn it into the look-ahead and track constraints

Photograph the wall and transcribe it the same day. Update the master schedule activities for the phase, or add detail under them, and put the next few weeks into the look-ahead. Each constraint gets an owner and a need-by date that comes before the card it blocks. Review those constraints every week. How to build a three-week look-ahead covers that step.

A pull plan built backwards from a milestoneThe milestone, Level 3 ready for ceiling close-in inspection, sits on the right. Working backwards from it: insulation and in-wall inspections, then in-wall electrical and plumbing rough-in, then top track and studs. Each arrow is a handoff between trades. Two constraints are noted below the cards: a door frame submittal needed before framing, and the in-wall inspection booking.MILESTONEceilingclose-inINSPECTin-wall, 1 dayinsulation afterIN-WALL MEPelec + plumbing6 daysFRAMINGtrack, studs5 daysPLANNED RIGHT TO LEFT: WHAT DO YOU NEED BEFORE YOU START?DOOR FRAME SUBMITTALBOOK INSPECTIONEACH ARROW IS A HANDOFF ONE TRADE PROMISES TO THE NEXT
The plan is built from the milestone backwards; the work then runs left to right. Illustrative.

Worked example: one floor of interior build-out

Illustrative exampleA made-up project, trades and durations.

Milestone: Level 3 ready for the above-ceiling inspection, in 30 working days. Attendees: superintendent, project engineer, and foremen for framing, mechanical, electrical, plumbing, fire sprinkler and drywall.

Working back from the milestone, the trades build this sequence for the floor, split into areas A and B:

Order Work Trade Days Needs before starting
1 Overhead duct mains, area A then B Mechanical 8 Duct submittal approved
2 Sprinkler mains and branch lines Fire sprinkler 7 Duct mains in the area
3 Overhead conduit and cable tray Electrical 6 Duct and sprinkler mains in the area
4 Top track and studs Framing 5 Overhead mains in the area; door frame submittal approved
5 In-wall rough-in Electrical, plumbing 6 Studs in the area
6 In-wall inspection Inspector 1 Rough-in complete; booked ahead
7 Insulation and one side of board Drywall 4 In-wall inspection passed
8 Above-ceiling inspection Inspector 1 All overhead work complete; booked ahead

Done end to end, the durations add to 38 days, which misses the 30-day milestone. The team overlaps by area: framing starts area A as soon as overhead mains there are done, while mechanical and sprinkler move to area B. On the wall, that brings the plan to 28 days. The team keeps the 2 spare days as a buffer before the milestone rather than spreading them across trades.

Three constraints go on the list: the duct submittal (project engineer, needed in 4 days), the door frame submittal (framing sub, needed in 10 days), and booking both inspections (superintendent). The first two weeks go straight into the look-ahead, and the foremen commit to their first week of cards at the next weekly work plan meeting.

Common mistakes

  • Planning forwards. Starting at the start date produces the same schedule you already had. Start at the milestone.
  • The wrong people at the wall. Estimators and PMs plan what should happen; foremen know what can.
  • A vague milestone. If “done” isn’t defined, every trade plans to a different finish.
  • Squeezing durations to fit. A plan that only works if everyone is optimistic won’t survive the first week.
  • Leaving the wall on the wall. If nobody transcribes it and tracks its constraints, it was a meeting, not a plan.
  • Spreading the buffer. Padding every card hides the spare time. Keep it together before the milestone.

The three-week look-ahead template is a simple place to carry the pull plan forward, and percent plan complete is how you measure whether the weekly commitments that follow are being kept. The critical path calculator is handy for checking a small sequence before you put it in the master schedule.

How os.construction handles it

The pull planning session itself happens at the wall. Afterwards, the Schedule’s Lookahead page lists upcoming activities with the submittals, deliveries, RFIs and inspections linked to them as constraints, and holds the weekly work plan where each trade commits to make-ready work and percent plan complete is tracked by week and by trade.

FAQ

What is pull planning in construction?

Pull planning is a collaborative planning session where the trades plan a phase of work backwards from a milestone. Starting at the milestone, each trade says what it needs to have finished before it can start, so the work is 'pulled' by the next trade's needs. It is part of the Last Planner System, where it is often called phase planning.

Who should attend a pull planning session?

The foremen or crew leads who will direct the work for each trade in the phase, plus the GC's superintendent and project engineer. The scheduler and project manager are useful to connect the result to the master schedule. Representatives for design answers, inspections or owner decisions should attend if the phase depends on them.

How long does a pull planning session take?

It depends on the size of the phase. A single floor or system is often planned in a couple of hours. A larger phase may take a half-day session plus a follow-up to check durations and constraints. Planning a few weeks to a few months of work in one session is common; much more than that gets too detailed to be useful.

What is the difference between pull planning and a look-ahead schedule?

Pull planning sets the sequence and handoffs for a phase, working back from a milestone. The look-ahead covers the next several weeks of work and is where constraints are tracked and cleared so work is ready. The pull plan feeds the look-ahead, and the look-ahead feeds the weekly work plan.

What happens if the pull plan finishes later than the milestone?

The team has found a real problem early. Look at the durations and handoffs together: can work overlap by area, can crews be added, can a constraint be cleared sooner? If not, the milestone or the master schedule needs to be addressed with the project manager and, where the contract requires, the owner. Don't squeeze durations on the wall just to make it fit.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Open file