- Step 1: Build the register at mobilization
- Step 2: Turn every condition into an owned item
- Step 3: Tie inspections to conditions and the schedule
- Step 4: Know which expiration rule applies
- Step 5: Record what the authority did, with evidence
- Step 6: Review weekly, then close out
- Worked example
- Common mistakes
- How os.construction handles it
- FAQ
To track construction permits, keep one register per job with every permit’s authority, number, holder and dates; turn each permit condition into its own item with an owner and a due date; link inspections to the conditions and schedule activities that depend on them; watch the expiration rule that actually applies to each permit; and review the register weekly with the schedule. The permit number is the easy part. The conditions and the expiration rules are what catch teams out.
Permit rules are set locally. This post describes a tracking routine, not the law in any jurisdiction; the building permit entry covers the basics.
Step 1: Build the register at mobilization
List every permit the job needs, not just the building permit:
- Building permit, and any phased permits (foundation-only, shell, tenant improvement)
- Trade permits: electrical, plumbing, mechanical, fire sprinkler, fire alarm, elevator
- Demolition, grading, right-of-way, street use, crane and hoisting, tree removal
- Utility and agency approvals that act like permits: fire department, health department, stormwater
For each, record the authority, permit number, type, scope, who holds it (owner, GC or sub), who on your team is responsible, and the application, issue and expiration dates. A trade permit pulled by a sub still belongs on your register, because its inspections are on your schedule.
Step 2: Turn every condition into an owned item
Read each permit and its approved plans for conditions, and give each one its own line: what is required, before which stage (before framing inspection, before cover, before occupancy), who owns it and the due date. Common conditions:
| Condition | Typical owner | Due before |
|---|---|---|
| Special inspections (structural steel, anchors, concrete) | GC with the special inspector | The work is covered |
| Deferred submittals (fire alarm, sprinkler, truss drawings) | Trade sub through the design team | Installation or the related inspection |
| Fire department acceptance tests | Fire protection sub | Final inspection |
| Agency sign-offs (health, utility, public works) | Owner or GC, by contract | Certificate of occupancy |
| Recorded documents (easements, covenants) | Owner | Permit issuance or occupancy |
An unmet condition rarely stops work on the day. It stops an inspection, and the inspection stops the next trade.
Step 3: Tie inspections to conditions and the schedule
Required inspections go into the schedule as activities with realistic lead times for booking them. Link each inspection to the conditions that must be cleared first, and to the work it releases. When an inspection fails, the correction becomes a tracked item too, with a reinspection date. The three-week look-ahead is the right place to check that nothing due in the next three weeks is waiting on a condition nobody owns.
Step 4: Know which expiration rule applies
Don’t assume a permit lasts for the whole job. Two published examples show how different the rules are:
- Model IBC, as adopted in Massachusetts (780 CMR 105.5): a permit becomes invalid if work doesn’t start within 180 days of issuance, or if work is suspended or abandoned for 180 days. The building official can grant written extensions of up to 180 days each, requested in writing before expiry.
- New York City (DOB NOW: Build): permits expire at the earliest of the permit holder’s general liability, disability or workers’ compensation insurance expiration, its license expiration, or one year from issuance. Renewing the insurance or license before it expires extends the permit.
The New York rule links permits to certificates of insurance and licenses: a lapsed policy can quietly end a permit. Record the expiration the authority reports, note the rule behind it, and diary renewals well ahead.
Step 5: Record what the authority did, with evidence
Your register should reflect the authority’s status, not your hopes. Record each event (submitted, corrections required, approved, issued, inspection passed or failed, renewed, closed) with its date and the evidence: the authority’s letter, the portal screenshot, the inspection report. When status matters for a decision, confirm it with the authority. A note saying “issued” is not a permit.
Step 6: Review weekly, then close out
Each week, with the superintendent:
- Sort open conditions by due date. Anything due in the next three weeks without an owner gets one.
- Check inspections booked against the look-ahead.
- Check expiration dates, including linked insurance and license dates, for the next 60 days.
- Update statuses from the authority’s records.
At the end of the job, close every permit: final inspections passed, conditions signed off, permit closed or the certificate of occupancy issued. Keep the evidence with the closeout package. An open trade permit can resurface when the owner sells or refinances the building.
Worked example
Illustrative: a three-story medical office building, register snapshot at week 22.
| Permit | Holder | Status (authority) | Expires | Open conditions |
|---|---|---|---|---|
| Building B-24-1187 | Owner | Issued | Activity-based, 180 days | Fire alarm deferred submittal, due June 14 (owner: electrical sub) |
| Electrical E-24-3302 | Electrical sub | Issued | Activity-based | Rough-in inspection level 3, booked June 18 |
| Fire sprinkler F-24-0951 | Fire protection sub | Corrections required | n/a | Revised hydraulic calcs, due June 10 (owner: fire protection sub) |
| Right-of-way R-24-0420 | GC | Issued | August 31 | Traffic control plan renewal, due August 15 (owner: GC PM) |
Two items need action this week. The sprinkler permit isn’t issued, and its corrections are due in four days; without it, the level 3 ceiling close-in in the look-ahead can’t be inspected. And the fire alarm deferred submittal is still with the engineer of record, ten days before it’s due. Both have owners and dates, so the meeting is about clearing them, not discovering them.
Common mistakes
- Tracking permit numbers but not conditions. The conditions are what fail inspections.
- Leaving trade permits to subs without seeing their status and inspection results.
- Assuming one expiration rule for every permit and every authority.
- Treating your own note as the authority’s status. Confirm before you rely on it.
- Not linking insurance and licenses where the authority ties permits to them.
- Forgetting to close permits at the end of the job.
General information, not legal advice. Permit requirements, expiration rules, extensions and fees vary by jurisdiction and change over time. Sources: 780 CMR 105.5, Expiration (Massachusetts State Building Code); NYC Department of Buildings, Permit renewal. Reviewed November 21, 2026.
How os.construction handles it
The Permits tool keeps the project permit register: authority, jurisdiction, permit type, scope, responsible person, and submitted, issued and expiration dates. Status changes are recorded as reports of what the authority did, each backed by an exact document version, a link or a stated reason why evidence is missing; the app doesn’t file applications or grant permission to work, and an issued permit past its recorded expiration shows as expired. Each condition has an owner and a due date, can link to an inspection for follow-up, and is completed through a receipt: a field user submits the document version, and a different permit administrator accepts it. A company permit work queue lists open conditions and expirations across projects, filtered by owner and due date. Inspections, the punch list and the schedule live on the same project, so the path to the certificate of occupancy is visible in one place. If your permits live in a spreadsheet and the inspector’s inbox, start a free trial.
FAQ
How do you track building permits on a construction project?
Keep one permit register per job with a line for every permit: building, trade, demolition, right-of-way and any others. Record the authority, permit number, type, scope, who holds it, and the application, issue and expiration dates. Then list each permit's conditions as separate items with an owner and a due date, link the inspections they depend on, and review the register weekly with the schedule.
What should a permit log include?
For each permit: the authority and jurisdiction, permit number and type, scope, permit holder and the person responsible on your team, status as last reported by the authority, application, issue and expiration dates, the conditions with owners and due dates, required inspections and their results, and the evidence for each (approved plans, receipts, inspection reports).
How long does a building permit stay valid?
It depends on the adopted code and local amendments. Under the model International Building Code, as adopted in Massachusetts for example, a permit becomes invalid if work doesn't start within 180 days of issuance or is suspended or abandoned for 180 days. New York City's DOB NOW permits expire at the earliest of the holder's insurance expiration, license expiration or one year from issuance. Check the rule for each authority.
Who is responsible for permits, the GC or the owner?
The contract decides. Many contracts make the contractor responsible for obtaining and paying for the permits needed for its work, with the owner obtaining the general building permit, and trade permits often pulled by licensed subcontractors. Whoever holds a permit, the GC usually still needs to know its conditions and inspection status, because they control the schedule.
What is a permit condition?
A requirement attached to the permit by the authority: a special inspection, a deferred submittal, an agency sign-off, a document to file before a stage of work. Conditions are easy to lose because they sit inside the permit document. Track each one as its own item with an owner and a due date.
Share this article