A punch list is the written list of work that is incomplete, damaged or not built to the contract documents near the end of a job. Each item records where it is, what is wrong and which trade owns it. Closing every item is usually a condition of final completion, final payment and the release of retained money.
Typical items are small: a scratched door, a missing cover plate, a ceiling tile out of grid, a fire damper access panel without its label, a failed test that needs a retest. The list exists because hundreds of small items are easy to lose, and because the owner should only pay the last dollars once the building matches what was bought. In the UK the same list is called a snag list (the work is “snagging”), and in Canada it is often called a deficiency list.
How it works
- Internal punch. As areas finish, the superintendent and trades walk them and fix what they find before the owner sees it. Many teams run this room by room or floor by floor.
- Contractor’s list at substantial completion. Under AIA A201 and the G704 certificate, when the contractor believes the work is substantially complete it prepares a list of items still to be completed or corrected.
- Architect and owner walk. The architect inspects, adds items it finds and decides whether the work really is substantially complete. If the list is too long to call the building usable, the date moves.
- Assign and fix. Each item goes to a responsible trade with a due date. Items in dispute (“not my scope”) are settled against the subcontract, not argued on site.
- Verify and close. Someone other than the trade checks each fix. The trade says it is done; the manager or architect accepts it.
- Final walk. The remaining items are confirmed closed, which supports final completion, the final pay application and the release of retainage.
Punch list vs other end-of-job lists
| List | What it holds | When | Who signs off |
|---|---|---|---|
| Punch list (snag list, deficiency list) | Incomplete or defective contract work | Around substantial completion | Architect or owner |
| Inspection checklist | Pass/fail checks against a standard or code | During construction | Inspector or QC lead |
| Closeout list | Documents: O&M manuals, warranties, as-builts, lien waivers | Substantial to final completion | Owner or architect |
| Warranty claim | Defects that appear after acceptance | During the warranty period | Contractor, under the warranty terms |
The punch list is about the physical work. Closeout documents are a separate list, and on most contracts both have to be finished before final payment.
Why it matters
Punch is the last thing between the contractor and its retainage. On a job holding 10% retainage, that money is often far larger than the cost of the remaining items, so a slow punch ties up cash out of all proportion to the work. A long list can also push back the substantial completion date, which on many contracts is when liquidated damages stop running.
It matters to trades too. A subcontractor that never finishes its items can be back-charged for the cost of someone else doing them, and its own retainage stays held. And because punch items are contract work, they are rarely billable. Every week a crew spends going back to a finished floor is cost with no revenue against it.
Worked example
Illustrative: on Riverside Medical Center, the architect’s walk at Level 3 produces 214 items. One reads: “L3 corridor, grid C-4: fire damper access panel missing label.” It is assigned to the mechanical subcontractor with a seven-day due date and a photo pinned to the floor plan.
The mechanical foreman installs the label and marks the item resolved with a new photo. The project engineer checks it on the next walk and moves it to ready to close. The architect accepts it at the final walk. If the contract lets the owner hold back a multiple of the value of open punch work, every closed item like this one lowers the amount held and moves the job toward the final completion payment.
To estimate how long a list will take to close at your team’s current rate, try the punch list closeout calculator. For a blank list to start from, use the free punch list template.
For how to prepare, run and follow up the walk itself, see how to run a punch walk.
Common mistakes
- Waiting until the end. One big list at substantial completion is slower than rolling area-by-area punch from the first turnover.
- Vague items. “Fix wall” with no room, grid line or photo can’t be assigned or verified.
- Letting the trade close its own items. Resolved by the trade and accepted by the reviewer are two steps; merging them leads to items reopened at the final walk.
- Mixing changes into punch. A new request at the walk is a change order. Logging it as punch gives the work away.
- No owner for disputes. Items nobody claims sit open for weeks. Settle scope against the subcontract and move on.
How os.construction handles it
The Punch List tool records each item with a location, linked drawings and photos, the trades assigned to fix it, a punch item manager and a final approver. Each assignee resolves only their own line, the manager reviews the work, and only the final approver closes the item, so “done” and “accepted” stay separate. Ball in court follows the status, and an item can go In Dispute when a trade says it isn’t theirs. The walkthrough in punch list to closeout shows how the list feeds closeout and retainage release.
FAQ
What is a punch list in construction?
A punch list is a written list of work that is incomplete or doesn't meet the contract documents, made near the end of a project. Each item names the location, the problem and the trade responsible. The contractor fixes the items, the architect or owner verifies them, and the closed list supports final completion and the release of retainage.
Who creates the punch list?
Under AIA A201 and the G704 certificate, the contractor prepares the list of items to be completed or corrected when it believes the work is substantially complete, and the architect inspects and may add to it. In practice the superintendent often runs an internal punch first, then the architect and owner walk the building and add their own items.
What is the difference between a punch list and a snag list?
They are the same idea in different markets. Snagging, or a snag list, is the UK term for defects recorded around practical completion. In Canada the same list is often called a deficiency list. The contract form decides when the list is made and what money is tied to it.
Is punch list work included in the contract price?
Usually yes. Punch items are work the contractor already agreed to deliver, so fixing them is not extra. A request that goes beyond the contract documents, such as a finish upgrade added at the walk, is a change rather than a punch item, and should go through a change order.
How long does a punch list take to close?
The contract sets the deadline, often a fixed number of days after substantial completion. The real driver is the length and quality of the list. Rolling area-by-area punch during construction leaves fewer items for the final walk and closes faster than one big list at the end.