Closeout and TCO checklist, from final inspections to retainage.
Every step between the last inspections and the last retainage check, in the order they usually run: the TCO application, substantial completion, commissioning, the final certificate of occupancy, turnover documents and final payment. Each line gets an owner and a date.
Closeout and TCO checklist
os.construction · free template- Project
- Permit #
- Owner
- Architect
- Building department / AHJ
- Target substantial completion
- TCO expiry date
- Final completion target
1 · Plan the TCO and CO (60 to 90 days out)
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| Pre-final meeting held with the building department; final inspection list and outside agencies confirmed in writing | |||
| Contract checked: is a TCO or a final CO a condition of substantial completion? | |||
| Each final inspection added to the schedule as an activity, with lead time for re-inspection | |||
| Fire alarm acceptance and sprinkler final booked with the fire marshal | |||
| Elevator inspection and certificate booked with the elevator authority, if applicable | |||
| Special inspection final reports and structural observation letters requested from the engineers | |||
| Owner told who applies for the TCO and CO, and which fees, deposits or bonds the jurisdiction requires |
2 · TCO application
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| Areas to be occupied defined on a plan: floors, tenant spaces or phases | |||
| Life safety complete in those areas: fire alarm, sprinklers, exits, exit signs, emergency lighting | |||
| Fire-rated separation and secure barriers between occupied areas and active work | |||
| Fire department access, hydrants, addressing and key box in place | |||
| Required sign-offs for the occupied areas passed (building, fire, electrical, plumbing, mechanical, elevator) | |||
| Design professional letters or certifications submitted, where the jurisdiction asks for them | |||
| Open-items list with completion dates attached to the application | |||
| TCO received; its conditions and expiry date logged and put on the schedule as a milestone | |||
| Renewal lead time noted: the date to apply for an extension if the final CO will not be ready | |||
| Owner’s insurance, utilities and security in place for the occupied areas |
3 · Substantial completion
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| Contractor’s own punch walk completed and list submitted | |||
| Architect / owner punch list received and every item assigned to one trade with a due date | |||
| Certificate of Substantial Completion signed (often AIA G704), with the time to finish the listed items | |||
| Date confirmed for liquidated damages, warranty start and retainage reduction | |||
| Responsibility for security, maintenance, utilities and insurance transferred in writing |
4 · Commissioning (Cx)
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| Test, adjust and balance (TAB) report submitted | |||
| Functional performance tests complete and witnessed by the commissioning authority | |||
| Controls sequences verified and trend data provided where the specification requires it | |||
| Cx issues log closed, or deferred and seasonal tests listed with dates | |||
| Owner training sessions held, with attendance and recordings filed | |||
| Commissioning report or systems manual delivered |
5 · Final inspections and certificate of occupancy
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| All final inspections passed and sign-off cards or reports collected | |||
| Outside agency approvals received (health, public works, utilities, zoning), where required | |||
| Final certificate of occupancy issued before the TCO expired | |||
| Copy of the CO given to the owner and posted where the jurisdiction requires | |||
| Final punch items verified closed by the architect or owner |
6 · Turnover documents
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| As-built drawings submitted, with every field change and RFI answer shown | |||
| Operation and maintenance manuals submitted, organized by spec section | |||
| Warranties and guarantees collected from every trade and manufacturer, with start dates | |||
| Attic stock and spare parts delivered against a signed receipt | |||
| Keys, access cards and combinations turned over against a signed receipt | |||
| Test reports and certificates filed: fire alarm, sprinkler, backflow, elevator |
7 · Final payment and retainage release
| Item | Done | N/A | Comment / follow-up |
|---|---|---|---|
| All pending change orders approved, rejected or withdrawn; sub change orders match owner change orders | |||
| Final subcontractor pay apps received and back charges settled | |||
| Conditional final lien waivers collected from every sub and supplier | |||
| Affidavit of payment of debts and claims (often AIA G706) and lien releases (G706A or state forms) | |||
| Consent of surety to final payment (often AIA G707), on bonded jobs | |||
| Final owner pay app with retainage release submitted and certified | |||
| Unconditional final waivers exchanged once funds clear | |||
| Notice of completion recorded, in states that use one | |||
| Retainage paid to subs under the subcontract terms; warranty-period reminders set |
Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/closeout-checklist
Using the closeout and TCO checklist
- Start section 1 two to three months before substantial completion. Final inspections and the TCO depend on outside schedules you don’t control.
- Read the contract’s definition of substantial completion first. If it requires a TCO or CO, the inspection and TCO sections are on your critical path.
- Give every line an owner and a date. N/A is an answer; a blank is not.
- Put the TCO expiry on the schedule as a milestone with a renewal date ahead of it. An expired TCO can leave an occupied building out of compliance.
- Collect turnover documents from the first pay app, not the last. Section 6 is where closeout usually stalls.
- Don’t submit the final pay app until section 7’s waivers and consent of surety are in hand. Owners and lenders will send it back.
- Life safety testedFire marshal, inspectors
- TCO issuedBuilding official
- Substantial completionArchitect signs the G704
- Cx and punch closedCxA, trades, architect
- Certificate of occupancyBuilding officialFailed final: back to “Cx and punch closed”
- Final paymentWaivers, surety consent, retainage
Text version
- Life safety tested: Fire marshal, inspectors
- TCO issued: Building official
- Substantial completion: Architect signs the G704
- Cx and punch closed: CxA, trades, architect
- Certificate of occupancy: Building official
- Final payment: Waivers, surety consent, retainage
Failed final: from “Certificate of occupancy” back to “Cx and punch closed”.
Do this in os.construction instead of a spreadsheet
In os.construction, the Punch List tool takes each item from Initiated to Closed with a punch item manager and a final approver, Inspections record pass, fail or N/A with signatures and link failed items to observations, and Documents holds as-builts, O&M manuals and warranties in versioned folders. In the Schedule, final inspections, the TCO expiry and the CO can be milestones in the CPM network. Retainage released is entered on a pay app, and in AR a final retainage release is refused until the contract’s required closeout documents are on file. A closeout requirements list per subcontract and turnover package export are planned, not live.
Try it on the sample project
Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.
Questions about the closeout and TCO checklist
What do you need for a TCO?
It depends on the building department, but typically: an approved building permit, life safety complete in the areas to be occupied (fire alarm, sprinklers, egress, emergency lighting), the required inspections passed for those areas, fire department access, and sometimes a design professional’s letter, a list of open items, a fee or a bond. Ask your building department for its list early.
How long does a TCO last?
The building official sets the period. The International Building Code (Section 111.3) leaves it to the official, and local practice varies. In New York City, for example, the Department of Buildings says TCOs typically expire 90 days after issuance and can be renewed while final CO items are open.
Is a TCO the same as substantial completion?
No. A TCO is the building department’s permission to occupy; substantial completion is a contract milestone the architect certifies. Many contracts require a TCO or CO before substantial completion can be certified, so they often happen close together, but your contract’s definition decides.
Who applies for the certificate of occupancy?
Usually the permit holder, which in many jurisdictions is the owner, often with the contractor or an expediter doing the legwork. The contractor schedules inspections, fixes deficiencies and collects sign-offs. Check your contract for who is responsible.
When is retainage released at closeout?
Under AIA A201-2017, most retainage is released at substantial completion except amounts held for incomplete work and unsettled claims, and the balance with final payment once closeout documents, waivers and consent of surety are in. Your contract and some state laws set different rules.
Keep going
- GlossaryAs-Built Drawings
- GlossaryCertificate of Occupancy (CO)
- GlossaryCommissioning (Cx)
- GlossaryFinal Completion
- GlossaryO&M Manuals
- GlossaryRetainage Release
- GlossarySubstantial Completion
- GlossaryTemporary Certificate of Occupancy (TCO)
- Free resourceCloseout package checklist generator
- Free resourceCloseout to occupancy guide
- Free resourceCloseout and TCO checklist (one-page printable)
- Free resourceRetainage calculator
- TemplatePunch list template
- TemplateMeeting minutes template
- TemplateInspection checklist starter pack
- TemplateT&M ticket template
- TemplateRFI writing checklist
- TemplateDaily log checklist
- TemplateChange event log
- TemplateBack charge notice and log
- TemplateThree-week look-ahead template
- TemplateSafety observation log
- TemplateAction item tracker
- TemplateNotice to proceed template
- TemplateJob cost report template
- TemplateConstruction schedule (Gantt) template
- TemplateChange order log template
- TemplateBid tabulation and leveling template
- TemplateCash flow projection template
- TemplateBuyout log template
- TemplateASI log template
Keep exploring
Related across os.construction
- ExplainerCloseout to Occupancy: Punch, Cx, As-Builts, TCO, COConstruction closeout from substantial completion to final payment: punch list, commissioning (Cx), inspections, TCO vs CO, as-builts and retainage.
- Free toolCloseout package checklist generatorTCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with dates.
- BlogTCO vs certificate of occupancy: what you need before turnoverA TCO lets an owner occupy safe parts of a building before everything is finished; a certificate of occupancy is the final, permanent approval. What the IBC says, how NYC and Philadelphia handle TCO permits, and what a GC needs in hand before turnover.
- BlogSubstantial completion vs final completion: what each one triggersSubstantial completion is when the owner can use the building; final completion is when every last item, document and payment obligation is done. Here is what each milestone triggers, how they differ, a worked retainage example and the mistakes that keep jobs open for months.
- Free toolPunch list closeout calculatorWeeks to clear the punch list at your close and add rates, and the rate a target needs.
- DocsCloseout and retainage releaseHow AR retainage release and contract closeout checklists work today, what remains unautomated, and why contract and jurisdiction terms must be configured per project.