Closeout and TCO checklist, from final inspections to retainage.

Every step between the last inspections and the last retainage check, in the order they usually run: the TCO application, substantial completion, commissioning, the final certificate of occupancy, turnover documents and final payment. Each line gets an owner and a date.

  • Free
  • No signup
  • Print · CSV · Markdown
Download CSVDownload Markdown

Closeout and TCO checklist

os.construction · free template
Project
Permit #
Owner
Architect
Building department / AHJ
Target substantial completion
TCO expiry date
Final completion target

1 · Plan the TCO and CO (60 to 90 days out)

ItemDoneN/AComment / follow-up
Pre-final meeting held with the building department; final inspection list and outside agencies confirmed in writing
Contract checked: is a TCO or a final CO a condition of substantial completion?
Each final inspection added to the schedule as an activity, with lead time for re-inspection
Fire alarm acceptance and sprinkler final booked with the fire marshal
Elevator inspection and certificate booked with the elevator authority, if applicable
Special inspection final reports and structural observation letters requested from the engineers
Owner told who applies for the TCO and CO, and which fees, deposits or bonds the jurisdiction requires

2 · TCO application

ItemDoneN/AComment / follow-up
Areas to be occupied defined on a plan: floors, tenant spaces or phases
Life safety complete in those areas: fire alarm, sprinklers, exits, exit signs, emergency lighting
Fire-rated separation and secure barriers between occupied areas and active work
Fire department access, hydrants, addressing and key box in place
Required sign-offs for the occupied areas passed (building, fire, electrical, plumbing, mechanical, elevator)
Design professional letters or certifications submitted, where the jurisdiction asks for them
Open-items list with completion dates attached to the application
TCO received; its conditions and expiry date logged and put on the schedule as a milestone
Renewal lead time noted: the date to apply for an extension if the final CO will not be ready
Owner’s insurance, utilities and security in place for the occupied areas

3 · Substantial completion

ItemDoneN/AComment / follow-up
Contractor’s own punch walk completed and list submitted
Architect / owner punch list received and every item assigned to one trade with a due date
Certificate of Substantial Completion signed (often AIA G704), with the time to finish the listed items
Date confirmed for liquidated damages, warranty start and retainage reduction
Responsibility for security, maintenance, utilities and insurance transferred in writing

4 · Commissioning (Cx)

ItemDoneN/AComment / follow-up
Test, adjust and balance (TAB) report submitted
Functional performance tests complete and witnessed by the commissioning authority
Controls sequences verified and trend data provided where the specification requires it
Cx issues log closed, or deferred and seasonal tests listed with dates
Owner training sessions held, with attendance and recordings filed
Commissioning report or systems manual delivered

5 · Final inspections and certificate of occupancy

ItemDoneN/AComment / follow-up
All final inspections passed and sign-off cards or reports collected
Outside agency approvals received (health, public works, utilities, zoning), where required
Final certificate of occupancy issued before the TCO expired
Copy of the CO given to the owner and posted where the jurisdiction requires
Final punch items verified closed by the architect or owner

6 · Turnover documents

ItemDoneN/AComment / follow-up
As-built drawings submitted, with every field change and RFI answer shown
Operation and maintenance manuals submitted, organized by spec section
Warranties and guarantees collected from every trade and manufacturer, with start dates
Attic stock and spare parts delivered against a signed receipt
Keys, access cards and combinations turned over against a signed receipt
Test reports and certificates filed: fire alarm, sprinkler, backflow, elevator

7 · Final payment and retainage release

ItemDoneN/AComment / follow-up
All pending change orders approved, rejected or withdrawn; sub change orders match owner change orders
Final subcontractor pay apps received and back charges settled
Conditional final lien waivers collected from every sub and supplier
Affidavit of payment of debts and claims (often AIA G706) and lien releases (G706A or state forms)
Consent of surety to final payment (often AIA G707), on bonded jobs
Final owner pay app with retainage release submitted and certified
Unconditional final waivers exchanged once funds clear
Notice of completion recorded, in states that use one
Retainage paid to subs under the subcontract terms; warranty-period reminders set

Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/closeout-checklist

How to use it

Using the closeout and TCO checklist

  1. Start section 1 two to three months before substantial completion. Final inspections and the TCO depend on outside schedules you don’t control.
  2. Read the contract’s definition of substantial completion first. If it requires a TCO or CO, the inspection and TCO sections are on your critical path.
  3. Give every line an owner and a date. N/A is an answer; a blank is not.
  4. Put the TCO expiry on the schedule as a milestone with a renewal date ahead of it. An expired TCO can leave an occupied building out of compliance.
  5. Collect turnover documents from the first pay app, not the last. Section 6 is where closeout usually stalls.
  6. Don’t submit the final pay app until section 7’s waivers and consent of surety are in hand. Owners and lenders will send it back.
From final inspections to retainageLife safety tested, then TCO issued, then Substantial completion, then Cx and punch closed, then Certificate of occupancy, then Final payment. Failed final: from Certificate of occupancy back to Cx and punch closed.Failed finalLife safety testedFire marshal, inspectorsTCO issuedBuilding officialSubstantial completionArchitect signs the G704Cx and punch closedCxA, trades, architectCertificate of occupancyBuilding officialFinal paymentWaivers, surety consent, retainage
  1. Life safety testedFire marshal, inspectors
  2. TCO issuedBuilding official
  3. Substantial completionArchitect signs the G704
  4. Cx and punch closedCxA, trades, architect
  5. Certificate of occupancyBuilding officialFailed final: back to “Cx and punch closed”
  6. Final paymentWaivers, surety consent, retainage
From final inspections to retainage
Text version
  1. Life safety tested: Fire marshal, inspectors
  2. TCO issued: Building official
  3. Substantial completion: Architect signs the G704
  4. Cx and punch closed: CxA, trades, architect
  5. Certificate of occupancy: Building official
  6. Final payment: Waivers, surety consent, retainage

Failed final: from “Certificate of occupancy” back to “Cx and punch closed”.

In os.construction

Do this in os.construction instead of a spreadsheet

In os.construction, the Punch List tool takes each item from Initiated to Closed with a punch item manager and a final approver, Inspections record pass, fail or N/A with signatures and link failed items to observations, and Documents holds as-builts, O&M manuals and warranties in versioned folders. In the Schedule, final inspections, the TCO expiry and the CO can be milestones in the CPM network. Retainage released is entered on a pay app, and in AR a final retainage release is refused until the contract’s required closeout documents are on file. A closeout requirements list per subcontract and turnover package export are planned, not live.

Try it on the sample project

Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.

FAQ

Questions about the closeout and TCO checklist

What do you need for a TCO?

It depends on the building department, but typically: an approved building permit, life safety complete in the areas to be occupied (fire alarm, sprinklers, egress, emergency lighting), the required inspections passed for those areas, fire department access, and sometimes a design professional’s letter, a list of open items, a fee or a bond. Ask your building department for its list early.

How long does a TCO last?

The building official sets the period. The International Building Code (Section 111.3) leaves it to the official, and local practice varies. In New York City, for example, the Department of Buildings says TCOs typically expire 90 days after issuance and can be renewed while final CO items are open.

Is a TCO the same as substantial completion?

No. A TCO is the building department’s permission to occupy; substantial completion is a contract milestone the architect certifies. Many contracts require a TCO or CO before substantial completion can be certified, so they often happen close together, but your contract’s definition decides.

Who applies for the certificate of occupancy?

Usually the permit holder, which in many jurisdictions is the owner, often with the contractor or an expediter doing the legwork. The contractor schedules inspections, fixes deficiencies and collects sign-offs. Check your contract for who is responsible.

When is retainage released at closeout?

Under AIA A201-2017, most retainage is released at substantial completion except amounts held for incomplete work and unsettled claims, and the balance with final payment once closeout documents, waivers and consent of surety are in. Your contract and some state laws set different rules.