Notice to proceed template, with a limited NTP option.
A one-page notice that starts the contract clock on the date you mean, or a limited notice that releases named early work under a dollar cap without starting it. Fill the details, tick full or limited, sign and get the contractor’s acknowledgment.
Notice to proceed template
os.construction · free template- Project
- Contract no.
- Owner
- Contractor
- Date of this notice
- Issued by (name, title)
Notice details
| Item | Entry | Where it comes from |
|---|---|---|
| Type of notice | Full NTP / Limited NTP (SAMPLE · delete this row) | Tick one |
| Date of commencement | Date of this notice, a later stated date, or __ days after receipt | Agreement (e.g. AIA A101 date of commencement) |
| Contract time | 540 calendar days | Agreement |
| Substantial completion date | Commencement + contract time | Agreement, adjusted by change orders |
| Final completion date | Agreement or general conditions | |
| Liquidated damages | $ ____ per calendar day, as stated in the contract | Agreement |
| Pre-start submittals due | Schedule of values, baseline schedule, safety plan | Specifications, Division 01 |
Limited NTP: authorized early work
| # | Scope authorized | Cost code | Not-to-exceed ($) | Expires / superseded by |
|---|---|---|---|---|
| 1 | Mobilization and site fencing (SAMPLE · delete this row) | 01 50 00 | Full NTP | |
| 2 | Deposit and shop drawings for long-lead switchgear | 26 24 00 | Full NTP | |
| 3 | Building permit application and fees | 01 41 00 | Full NTP | |
Before the notice goes out
| Item | Done | Comment / follow-up |
|---|---|---|
| Agreement signed by both parties | ||
| Performance and payment bonds received, if required | ||
| Certificates of insurance received and checked against the contract | ||
| Permits the owner must obtain are issued, or the notice says which are pending | ||
| Site access, laydown and any owner-furnished items are available on the commencement date | ||
| Financing closed, or a limited NTP used instead of a full one | ||
| Commencement date, contract time and LD rate match the agreement; calendar vs working days stated | ||
| Limited NTP only: scope, not-to-exceed amount and what happens if no full NTP follows are written down |
Contractor acknowledgment
| Item | Done | Comment / follow-up |
|---|---|---|
| Received by (name, title, company) | ||
| Date and time received | ||
| Commencement date and contract time confirmed, or exceptions noted in writing |
Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/notice-to-proceed
Using the notice to proceed template
- Read the agreement before you fill anything in. It decides whether contract time starts on the notice date, a later date in the notice, or a number of days after receipt.
- Tick full or limited. A limited NTP releases only the scope in its table, usually under a not-to-exceed amount, and usually does not start contract time unless it says so.
- For a limited NTP, list each early activity with a cost code and a cap, and say what happens if the full NTP never comes: how the contractor is paid for the authorized work and how it demobilizes.
- State the dates the notice produces: commencement, substantial completion and final completion. If the contractor disagrees, it should say so in writing right away.
- Send it by a method that proves receipt, and get the acknowledgment signed. The receipt date can be the date contract time starts.
- Contractors: put the commencement date into the baseline schedule the day the notice arrives.
- Contract signedOwner and contractor
- Bonds and insurance inContractor delivers
- Limited NTP (optional)Named early work, capped
- Full NTP issuedOwner or architect
- Contract time startsBaseline set from commencement
Text version
- Contract signed: Owner and contractor
- Bonds and insurance in: Contractor delivers
- Limited NTP (optional): Named early work, capped
- Full NTP issued: Owner or architect
- Contract time starts: Baseline set from commencement
Do this in os.construction instead of a spreadsheet
In os.construction, the prime contract records its dates, and the Schedule can hold the notice to proceed, commencement, substantial completion and final completion as milestones with contract-date constraints, so the baseline starts from the date the notice sets. The signed notice itself goes into Documents, where it is versioned and permissioned with the rest of the contract file.
Try it on the sample project
Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.
Questions about the notice to proceed template
What should a notice to proceed include?
The project and contract, the parties, the date of commencement or how it is set, the contract time, the resulting substantial and final completion dates, any liquidated damages reference, items due before work starts, the issuer’s signature and a line for the contractor’s acknowledgment of receipt.
What is a limited notice to proceed?
A limited NTP authorizes only named early work, such as mobilization, design, permitting or long-lead purchases, usually under a not-to-exceed amount. It lets early activities start while financing, permits or the final contract are being finished. It usually does not start contract time unless it says so.
Does the NTP date start contract time?
Usually, but your agreement decides. AIA A101-2017 lets the parties set the date of commencement as the agreement date, a date in a notice to proceed, or another way. Federal contracts using FAR 52.211-10 require work to start within a stated number of calendar days after the contractor receives the notice, and to finish within the stated period.
Who issues the notice to proceed?
The owner, or the architect or engineer on the owner’s behalf where the contract allows. It should be signed by someone with authority to bind the owner.
Can a contractor start work before the NTP?
It can, but work done without a written notice or limited NTP may not be paid if the project stalls and can blur when contract time began. If early work is needed, ask for a limited NTP with a scope and a cap.
Keep going
- GlossaryLimited Notice to Proceed (LNTP)
- GlossaryLiquidated Damages (LDs)
- GlossaryNotice to Proceed (NTP)
- GlossarySchedule Baseline
- GlossarySubstantial Completion
- Free resourceNotice to proceed generator (full or limited)
- Free resourceNotice to proceed letter (printable)
- Free resourceNTP meaning in construction
- TemplatePunch list template
- TemplateMeeting minutes template
- TemplateInspection checklist starter pack
- TemplateT&M ticket template
- TemplateRFI writing checklist
- TemplateDaily log checklist
- TemplateChange event log
- TemplateBack charge notice and log
- TemplateThree-week look-ahead template
- TemplateSafety observation log
- TemplateAction item tracker
- TemplateCloseout and TCO checklist
- TemplateJob cost report template
- TemplateConstruction schedule (Gantt) template
- TemplateChange order log template
- TemplateBid tabulation and leveling template
- TemplateCash flow projection template
- TemplateBuyout log template
- TemplateASI log template
Keep exploring
Related across os.construction
- Free toolNotice to proceed generatorFull or limited NTP letter with completion dates in calendar or working days.
- BlogHow to calculate liquidated damages exposure and carry it in your forecastLiquidated damages exposure is the days between your forecast finish and the adjusted contract date, times the daily rate, for each milestone that carries LDs, limited by any cap. The hard part is using honest inputs: approved extensions only, a forecast from the current schedule, pending requests and risk shown as separate scenarios. Here is the method and a worked example with two milestones.
- BlogSnagging, variations, retention: a US-UK construction term mapA snagging list is a punch list, a variation order is a change order and retention is retainage. A full US-UK crosswalk of construction terms, with the contract differences that matter: JCT and NEC vs AIA, practical vs substantial completion, and Canadian holdback.
- Free toolGeneral conditions calculatorLine-by-line general conditions: weekly burn, share of contract and cost per week of delay.
- ExplainerEarned value, step by stepPV, EV and AC S-curves on one control account: move the status date and read CV, SV, CPI, SPI and EAC.
- ExplainerCloseout to Occupancy: Punch, Cx, As-Builts, TCO, COConstruction closeout from substantial completion to final payment: punch list, commissioning (Cx), inspections, TCO vs CO, as-builts and retainage.