Notice to proceed template, with a limited NTP option.

A one-page notice that starts the contract clock on the date you mean, or a limited notice that releases named early work under a dollar cap without starting it. Fill the details, tick full or limited, sign and get the contractor’s acknowledgment.

  • Free
  • No signup
  • Print · CSV · Markdown
Download CSVDownload Markdown

Notice to proceed template

os.construction · free template
Project
Contract no.
Owner
Contractor
Date of this notice
Issued by (name, title)

Notice details

ItemEntryWhere it comes from
Type of noticeFull NTP / Limited NTP (SAMPLE · delete this row)Tick one
Date of commencementDate of this notice, a later stated date, or __ days after receiptAgreement (e.g. AIA A101 date of commencement)
Contract time540 calendar daysAgreement
Substantial completion dateCommencement + contract timeAgreement, adjusted by change orders
Final completion dateAgreement or general conditions
Liquidated damages$ ____ per calendar day, as stated in the contractAgreement
Pre-start submittals dueSchedule of values, baseline schedule, safety planSpecifications, Division 01

Limited NTP: authorized early work

#Scope authorizedCost codeNot-to-exceed ($)Expires / superseded by
1Mobilization and site fencing (SAMPLE · delete this row)01 50 00Full NTP
2Deposit and shop drawings for long-lead switchgear26 24 00Full NTP
3Building permit application and fees01 41 00Full NTP

Before the notice goes out

ItemDoneComment / follow-up
Agreement signed by both parties
Performance and payment bonds received, if required
Certificates of insurance received and checked against the contract
Permits the owner must obtain are issued, or the notice says which are pending
Site access, laydown and any owner-furnished items are available on the commencement date
Financing closed, or a limited NTP used instead of a full one
Commencement date, contract time and LD rate match the agreement; calendar vs working days stated
Limited NTP only: scope, not-to-exceed amount and what happens if no full NTP follows are written down

Contractor acknowledgment

ItemDoneComment / follow-up
Received by (name, title, company)
Date and time received
Commencement date and contract time confirmed, or exceptions noted in writing

Sample rows are illustrative and marked for deletion. Your contract, drawings and specifications govern. Template from os.construction/resources/templates/notice-to-proceed

How to use it

Using the notice to proceed template

  1. Read the agreement before you fill anything in. It decides whether contract time starts on the notice date, a later date in the notice, or a number of days after receipt.
  2. Tick full or limited. A limited NTP releases only the scope in its table, usually under a not-to-exceed amount, and usually does not start contract time unless it says so.
  3. For a limited NTP, list each early activity with a cost code and a cap, and say what happens if the full NTP never comes: how the contractor is paid for the authorized work and how it demobilizes.
  4. State the dates the notice produces: commencement, substantial completion and final completion. If the contractor disagrees, it should say so in writing right away.
  5. Send it by a method that proves receipt, and get the acknowledgment signed. The receipt date can be the date contract time starts.
  6. Contractors: put the commencement date into the baseline schedule the day the notice arrives.
From award to contract timeContract signed, then Bonds and insurance in, then Limited NTP (optional), then Full NTP issued, then Contract time starts.Contract signedOwner and contractorBonds and insurance inContractor deliversLimited NTP (optional)Named early work, cappedFull NTP issuedOwner or architectContract time startsBaseline set from commencement
  1. Contract signedOwner and contractor
  2. Bonds and insurance inContractor delivers
  3. Limited NTP (optional)Named early work, capped
  4. Full NTP issuedOwner or architect
  5. Contract time startsBaseline set from commencement
From award to contract time
Text version
  1. Contract signed: Owner and contractor
  2. Bonds and insurance in: Contractor delivers
  3. Limited NTP (optional): Named early work, capped
  4. Full NTP issued: Owner or architect
  5. Contract time starts: Baseline set from commencement
In os.construction

Do this in os.construction instead of a spreadsheet

In os.construction, the prime contract records its dates, and the Schedule can hold the notice to proceed, commencement, substantial completion and final completion as milestones with contract-date constraints, so the baseline starts from the date the notice sets. The signed notice itself goes into Documents, where it is versioned and permissioned with the rest of the contract file.

Try it on the sample project

Every trial workspace includes a sample project to run this workflow on. 14-day free trial. Pricing for paid plans isn't set yet.

FAQ

Questions about the notice to proceed template

What should a notice to proceed include?

The project and contract, the parties, the date of commencement or how it is set, the contract time, the resulting substantial and final completion dates, any liquidated damages reference, items due before work starts, the issuer’s signature and a line for the contractor’s acknowledgment of receipt.

What is a limited notice to proceed?

A limited NTP authorizes only named early work, such as mobilization, design, permitting or long-lead purchases, usually under a not-to-exceed amount. It lets early activities start while financing, permits or the final contract are being finished. It usually does not start contract time unless it says so.

Does the NTP date start contract time?

Usually, but your agreement decides. AIA A101-2017 lets the parties set the date of commencement as the agreement date, a date in a notice to proceed, or another way. Federal contracts using FAR 52.211-10 require work to start within a stated number of calendar days after the contractor receives the notice, and to finish within the stated period.

Who issues the notice to proceed?

The owner, or the architect or engineer on the owner’s behalf where the contract allows. It should be signed by someone with authority to bind the owner.

Can a contractor start work before the NTP?

It can, but work done without a written notice or limited NTP may not be paid if the project stalls and can blur when contract time began. If early work is needed, ask for a limited NTP with a scope and a cap.