# Notice to proceed template

**Project:** ______________________  
**Contract no.:** ______________________  
**Owner:** ______________________  
**Contractor:** ______________________  
**Date of this notice:** ______________________  
**Issued by (name, title):** ______________________  

## Notice details

| Item | Entry | Where it comes from |
| --- | --- | --- |
| Type of notice | Full NTP / Limited NTP (SAMPLE · delete this row) | Tick one |
| Date of commencement | Date of this notice, a later stated date, or __ days after receipt | Agreement (e.g. AIA A101 date of commencement) |
| Contract time | 540 calendar days | Agreement |
| Substantial completion date | Commencement + contract time | Agreement, adjusted by change orders |
| Final completion date |   | Agreement or general conditions |
| Liquidated damages | $ ____ per calendar day, as stated in the contract | Agreement |
| Pre-start submittals due | Schedule of values, baseline schedule, safety plan | Specifications, Division 01 |
|   |   |   |
|   |   |   |
|   |   |   |

## Limited NTP: authorized early work

| # | Scope authorized | Cost code | Not-to-exceed ($) | Expires / superseded by |
| --- | --- | --- | --- | --- |
| 1 | Mobilization and site fencing (SAMPLE · delete this row) | 01 50 00 |   | Full NTP |
| 2 | Deposit and shop drawings for long-lead switchgear | 26 24 00 |   | Full NTP |
| 3 | Building permit application and fees | 01 41 00 |   | Full NTP |
|   |   |   |   |   |
|   |   |   |   |   |
|   |   |   |   |   |
|   |   |   |   |   |

## Before the notice goes out

- [ ] Agreement signed by both parties
- [ ] Performance and payment bonds received, if required
- [ ] Certificates of insurance received and checked against the contract
- [ ] Permits the owner must obtain are issued, or the notice says which are pending
- [ ] Site access, laydown and any owner-furnished items are available on the commencement date
- [ ] Financing closed, or a limited NTP used instead of a full one
- [ ] Commencement date, contract time and LD rate match the agreement; calendar vs working days stated
- [ ] Limited NTP only: scope, not-to-exceed amount and what happens if no full NTP follows are written down

## Contractor acknowledgment

- [ ] Received by (name, title, company)
- [ ] Date and time received
- [ ] Commencement date and contract time confirmed, or exceptions noted in writing

## How to use it

1. Read the agreement before you fill anything in. It decides whether contract time starts on the notice date, a later date in the notice, or a number of days after receipt.
2. Tick full or limited. A limited NTP releases only the scope in its table, usually under a not-to-exceed amount, and usually does not start contract time unless it says so.
3. For a limited NTP, list each early activity with a cost code and a cap, and say what happens if the full NTP never comes: how the contractor is paid for the authorized work and how it demobilizes.
4. State the dates the notice produces: commencement, substantial completion and final completion. If the contractor disagrees, it should say so in writing right away.
5. Send it by a method that proves receipt, and get the acknowledgment signed. The receipt date can be the date contract time starts.
6. Contractors: put the commencement date into the baseline schedule the day the notice arrives.