Contracts

Limited Notice to Proceed (LNTP)

Definition

An owner's written authorization for a contractor to start only named early work, often up to a dollar cap, before the full notice to proceed.

Topic: Project delivery & contracts

Updated

Notice to proceed timeline: award, limited NTP, full NTP, contract time, completionA vertical timeline. Contract award and agreement come first, with bonds and insurance delivered. An optional limited notice to proceed authorizes early work such as mobilization, design and long-lead purchases, usually capped. The full notice to proceed is day 0, when contract time starts. Contract time runs, for example 540 calendar days, until substantial completion, when liquidated damages stop. Final completion follows with punch list, closeout and final payment.Award + agreementcontract signed; bonds, insurance inLimited NTP (optional)mobilize, design, long-lead buysFull NTP · day 0contract time startsSubstantial completionend of contract time; LDs stopFinal completionpunch list, closeout, final paymentcontract timee.g. 540 calendar daysThe contract says when the clock starts:NTP date, a later date, or X days after receipt.
The full NTP usually starts the contract clock. A limited NTP releases named early work without starting it, unless the contract says otherwise.

A limited notice to proceed (LNTP) is the owner’s written authorization for the contractor to start only named early work, such as design, permitting, mobilization or long-lead procurement, usually up to a dollar cap, before the full notice to proceed. It lets critical early activities start while financing, permits or contract terms are still being finalized.

How it works

  1. The parties agree early work is needed. Common triggers: switchgear or transformers with long lead times, design that must start to hold the schedule, or site work before a weather window closes.
  2. The owner issues the LNTP. It should name the authorized scope, the not-to-exceed amount, how the work is priced (contract rates, cost-plus or a lump sum), and what happens if the project doesn’t go ahead.
  3. The contractor performs only that scope. Purchase orders placed under the LNTP should carry cancellation terms that match it.
  4. The full NTP follows, releasing the rest of the work and usually starting contract time. LNTP costs are typically credited against the contract sum.

Why it matters

LNTPs are common on design-build, energy and financed projects, where waiting for a full NTP would push long-lead items past their need dates. The risk is scope creep: crews and buyers treat the LNTP as a green light for everything. Track cost against the cap the same way you would track a commitment.

Common mistakes

  • Doing work outside the named scope and expecting to be paid if the project stalls.
  • Exceeding the dollar cap without a written increase.
  • Placing non-cancellable orders when the LNTP only covers cancellation costs.
  • Starting the schedule’s contract time at the LNTP when the contract starts it at the full NTP, or the reverse.

This is general information, not legal advice. LNTP terms are negotiated project by project.

How os.construction handles it

In Scheduling, LNTP work can be its own activities and milestones ahead of the full NTP, with the baseline named for the commencement date the contract uses.

The notice to proceed template includes a limited NTP option with an early-work scope table and a not-to-exceed cap.

Watch the explainer · 2:50

Notice to proceed (NTP) explained

  1. 0:00What NTP means
  2. 0:21Paperwork first, then the NTP
  3. 0:41What the notice says
  4. 0:59When the clock starts
  5. 1:23An illustrative contract
  6. 1:43NTP on time, site not ready
  7. 2:04Limited notice to proceed
  8. 2:26Before you mobilize
Read the transcript

NTP stands for notice to proceed. It's the owner's written authorization for the contractor to start work under a signed contract. On most jobs, the NTP date starts contract time, the countdown to substantial completion. That one date anchors the schedule, liquidated damages and any time extension claims.

The NTP usually isn't the day the contract is signed. First comes award and the agreement. Then the contractor delivers its performance and payment bonds and certificates of insurance, while the owner lines up financing, land and key permits. Only then does the owner issue the notice to proceed, often weeks after signing.

The notice can be a one-page letter or an agency form. It should name the project and the contract, the date work may begin, the contract time, and the completion dates that result. It must be in writing and signed by someone with authority under the contract.

When does the clock actually start? The contract decides. The standard AIA owner-contractor agreement lets the parties pick the agreement date, a date set in a notice to proceed, or another method. Federal contracts using the FAR commencement clause require work to begin within a stated number of calendar days after the contractor receives the notice.

Here's an illustrative contract: five hundred forty calendar days from NTP to substantial completion. The NTP is issued March third, so completion lands in late August of the following year. If the owner issues the NTP three weeks late, the completion date moves three weeks with it.

Now flip it. The NTP goes out on time, but the site isn't available for those three weeks. The clock is running, but the crews can't work. Give written notice right away and request a time extension, which may be compensable depending on the contract. Terms vary by contract; this is general information, not legal advice.

A limited notice to proceed authorizes only named early work, such as design, permitting, mobilization or ordering long-lead equipment, usually with a dollar cap. It usually doesn't start contract time; the full NTP releases everything else. Track spending against the cap, and don't treat a limited NTP as a green light for the whole job.

Before you mobilize, check that the NTP is written and signed, that the commencement date and contract time match the agreement, and that the site and permits are really available. In os.construction Scheduling, the notice to proceed is the planned start of a new schedule, and every date is calculated from it.

FAQ

What is a limited notice to proceed?

A limited notice to proceed (LNTP) is the owner's written authorization for a contractor to start a defined part of the work before the full notice to proceed. It usually names the permitted scope, such as design, permitting, mobilization or ordering long-lead equipment, and caps what the owner will pay under it. Everything else waits for the full NTP.

Does a limited notice to proceed start the contract time?

Usually not, but the contract decides. Most LNTPs authorize early activities without starting the clock to substantial completion, which then begins at the full NTP. Some contracts start contract time at the LNTP, or start a separate milestone clock for the limited scope. Read the notice and the agreement together, and record the right date in the schedule baseline.

What happens if the full NTP is never issued?

That depends on the LNTP and the contract. A well-written LNTP says what the owner pays if the project doesn't proceed: typically costs incurred for the authorized scope up to the cap, plus cancellation charges on authorized orders and a stated markup. Costs beyond the authorized scope or cap are usually at the contractor's risk.