Project delivery methods and construction contracts
How a job is bought decides almost everything that follows: who designs it, who carries the price risk, how changes are paid for and when the contractor gets its money.
Start with the delivery method (design-bid-build, design-build, CM at risk, IPD), then the pricing structure (lump sum, GMP, cost-plus, unit price, time and materials), then the clauses that move risk around: notice to proceed, liquidated damages, contingency, allowances, escalation and force majeure.
Read the guide: Project delivery methods: design-build, CMAR, GMP and more
Project delivery & contracts: terms defined
Design-Build
A delivery method where one entity holds a single contract with the owner for both design and construction.
ContractsDesign-Bid-Build
The traditional delivery method: the owner hires a designer to complete the drawings, bids them to contractors, then signs a separate construction contract.
ContractsConstruction Manager at Risk (CMAR)
A delivery method where the CM gives preconstruction advice, then commits to building the project for a guaranteed maximum price.
ContractsIntegrated Project Delivery (IPD)
A delivery method where owner, designer and builder sign one multi-party agreement and share project risk and reward.
ContractsGeneral Contractor
The company that holds the prime construction contract with the owner and is responsible for building the whole project, usually by managing subcontractors, suppliers and its own crews.
ContractsGuaranteed Maximum Price (GMP)
A cost-plus contract with a ceiling: the owner pays actual cost plus fee up to a cap, and the contractor absorbs overruns.
ContractsLump Sum Contract
A contract where the contractor agrees to deliver a defined scope for one fixed price, keeping savings and absorbing overruns.
ContractsCost-Plus Contract
A contract where the owner reimburses the contractor's actual costs plus a fee, either a percentage or a fixed amount.
ContractsTime and Materials Contract
A contract where the owner pays for labor at agreed hourly rates plus materials at cost with a markup, usually capped by a not-to-exceed amount.
ContractsUnit Price Contract
A contract where the owner pays a fixed price per unit of work (per cubic yard, linear foot, ton) times the actual quantity installed.
ContractsShared Savings (GMP Savings Split)
A cost-plus-fee with GMP provision that splits any amount by which final cost comes in under the guaranteed maximum price between owner and contractor.
ContractsAllowance
A placeholder amount in the contract for a specific item not fully defined at bid time, reconciled against actual cost later.
ContractsContingency
Money set aside in a budget or contract to cover unknown costs and risks that are expected but can't be pinned down yet.
ContractsScope of Work
The written description of the work a contractor or subcontractor must perform, including what is included, what is excluded and the standards it must meet.
ContractsSubcontract
A contract between the prime contractor and a trade contractor to perform a defined part of the prime contract's scope.
ContractsFlow-Down Clause
A subcontract provision that binds the subcontractor to the GC's obligations under the prime contract, as they apply to the sub's work.
ContractsNotice to Proceed (NTP)
NTP stands for notice to proceed: the owner's written authorization for the contractor to start work. The NTP date usually starts contract time, the clock that runs to substantial completion.
ContractsLimited Notice to Proceed (LNTP)
An owner's written authorization for a contractor to start only named early work, often up to a dollar cap, before the full notice to proceed.
ContractsLiquidated Damages (LDs)
A fixed amount per day, set in the contract, that the contractor owes the owner for finishing late.
ContractsNo-Damages-for-Delay Clause
A contract clause that limits a contractor's remedy for owner-caused delay to a time extension, with no extra money.
ContractsForce Majeure
A contract clause that excuses delay (and sometimes performance) caused by events beyond either party's control, like severe weather, war or epidemics.
ContractsEscalation Clause
A contract provision that adjusts the price when the cost of specified materials or labor rises (or falls) beyond a set threshold after bid.
ContractsIndemnity Agreement
A promise by one party to cover another's losses. In surety, the general indemnity agreement makes the contractor and its owners repay the surety for any bond loss.
ContractsSubstantial Completion
The point when the work is complete enough for the owner to occupy or use it for its intended purpose.
ContractsFinal Completion
The point when all contract work, punch list and closeout requirements are done and final payment becomes due.
ContractsMaintenance Bond
A surety bond that guarantees the contractor will correct defects in materials and workmanship that appear during a set period after the work is completed.
Tools, templates and guides
Lessons and videos
Articles
- How to track subcontractor certificates of insurance: collect, review, renew, hold Nov 21, 2026
- AIA A201 vs ConsensusDocs 200: how the two standard contract families differ Nov 18, 2026
- Builder's risk vs general liability: which policy pays when something goes wrong on site Nov 18, 2026
- Hard costs vs soft costs in construction: what goes where, and why it matters Nov 18, 2026
- How to build a construction estimate from scratch: from takeoff to bid price Nov 18, 2026
- How to calculate general conditions costs: build them from the schedule, not a percentage Nov 18, 2026
- How to calculate liquidated damages exposure and carry it in your forecast Nov 18, 2026
- How to create a work breakdown structure for a construction project Nov 18, 2026
- How to handle a differing site condition: the first 48 hours Nov 18, 2026