Esc

↑↓ move↵ openIndex · Pagefind
Topic · 26 terms

Project delivery methods and construction contracts

How a job is bought decides almost everything that follows: who designs it, who carries the price risk, how changes are paid for and when the contractor gets its money.

Start with the delivery method (design-bid-build, design-build, CM at risk, IPD), then the pricing structure (lump sum, GMP, cost-plus, unit price, time and materials), then the clauses that move risk around: notice to proceed, liquidated damages, contingency, allowances, escalation and force majeure.

Read the guide: Project delivery methods: design-build, CMAR, GMP and more

Project delivery & contracts: terms defined

Contracts

Design-Build

A delivery method where one entity holds a single contract with the owner for both design and construction.

Contracts

Design-Bid-Build

The traditional delivery method: the owner hires a designer to complete the drawings, bids them to contractors, then signs a separate construction contract.

Contracts

Construction Manager at Risk (CMAR)

A delivery method where the CM gives preconstruction advice, then commits to building the project for a guaranteed maximum price.

Contracts

Integrated Project Delivery (IPD)

A delivery method where owner, designer and builder sign one multi-party agreement and share project risk and reward.

Contracts

General Contractor

The company that holds the prime construction contract with the owner and is responsible for building the whole project, usually by managing subcontractors, suppliers and its own crews.

Contracts

Guaranteed Maximum Price (GMP)

A cost-plus contract with a ceiling: the owner pays actual cost plus fee up to a cap, and the contractor absorbs overruns.

Contracts

Lump Sum Contract

A contract where the contractor agrees to deliver a defined scope for one fixed price, keeping savings and absorbing overruns.

Contracts

Cost-Plus Contract

A contract where the owner reimburses the contractor's actual costs plus a fee, either a percentage or a fixed amount.

Contracts

Time and Materials Contract

A contract where the owner pays for labor at agreed hourly rates plus materials at cost with a markup, usually capped by a not-to-exceed amount.

Contracts

Unit Price Contract

A contract where the owner pays a fixed price per unit of work (per cubic yard, linear foot, ton) times the actual quantity installed.

Contracts

Shared Savings (GMP Savings Split)

A cost-plus-fee with GMP provision that splits any amount by which final cost comes in under the guaranteed maximum price between owner and contractor.

Contracts

Allowance

A placeholder amount in the contract for a specific item not fully defined at bid time, reconciled against actual cost later.

Contracts

Contingency

Money set aside in a budget or contract to cover unknown costs and risks that are expected but can't be pinned down yet.

Contracts

Scope of Work

The written description of the work a contractor or subcontractor must perform, including what is included, what is excluded and the standards it must meet.

Contracts

Subcontract

A contract between the prime contractor and a trade contractor to perform a defined part of the prime contract's scope.

Contracts

Flow-Down Clause

A subcontract provision that binds the subcontractor to the GC's obligations under the prime contract, as they apply to the sub's work.

Contracts

Notice to Proceed (NTP)

NTP stands for notice to proceed: the owner's written authorization for the contractor to start work. The NTP date usually starts contract time, the clock that runs to substantial completion.

Contracts

Limited Notice to Proceed (LNTP)

An owner's written authorization for a contractor to start only named early work, often up to a dollar cap, before the full notice to proceed.

Contracts

Liquidated Damages (LDs)

A fixed amount per day, set in the contract, that the contractor owes the owner for finishing late.

Contracts

No-Damages-for-Delay Clause

A contract clause that limits a contractor's remedy for owner-caused delay to a time extension, with no extra money.

Contracts

Force Majeure

A contract clause that excuses delay (and sometimes performance) caused by events beyond either party's control, like severe weather, war or epidemics.

Contracts

Escalation Clause

A contract provision that adjusts the price when the cost of specified materials or labor rises (or falls) beyond a set threshold after bid.

Contracts

Indemnity Agreement

A promise by one party to cover another's losses. In surety, the general indemnity agreement makes the contractor and its owners repay the surety for any bond loss.

Contracts

Substantial Completion

The point when the work is complete enough for the owner to occupy or use it for its intended purpose.

Contracts

Final Completion

The point when all contract work, punch list and closeout requirements are done and final payment becomes due.

Contracts

Maintenance Bond

A surety bond that guarantees the contractor will correct defects in materials and workmanship that appear during a set period after the work is completed.

Open file