A subcontract is the agreement where a general contractor (GC) hands a slice of its scope to a trade partner: the electrician, the steel erector, the drywall crew. It defines scope, price, schedule, insurance, retainage, payment terms and how changes get priced. Most subcontracts “flow down” the prime contract terms, so the sub is bound to the owner’s requirements through the GC.
How it works
A subcontract comes out of buyout, after the GC has won the prime contract:
- Prequalify and bid. The GC invites prequalified subs to price a defined scope package, then levels the bids so they compare like for like.
- Write the scope. The scope of work lists inclusions, exclusions and interfaces with other trades. Most later disputes trace back to this exhibit.
- Set commercial terms. Price, schedule of values, retainage, payment timing, change pricing and markup, insurance and bonding.
- Flow down the prime contract. A flow-down clause binds the sub to the owner’s requirements as they apply to its work: specifications, schedule, notice periods, prevailing wage and similar.
- Execute and record the commitment. The signed value becomes a commitment in job cost.
- Administer it. Monthly pay applications, subcontract change orders, lien waivers, back-charges and, at the end, closeout and final retainage.
Standard forms include AIA A401 and ConsensusDocs 750 in the US and CCDC 17 in Canada. In the UK, “domestic subcontractor” means one the main contractor chose itself, as opposed to one named by the employer.
Worked example
On Riverside Medical Center (Job #24-118), Volt Electric holds the 26 Electrical subcontract. When CO #14 adds fire damper wiring, the GC issues a subcontract change order to Volt and the commitment goes up by Volt’s share. Volt’s next pay app bills against the revised value, minus 10% retainage, and the GC collects a conditional waiver before releasing payment.
Illustrative numbers for that pay app:
| Item | Amount |
|---|---|
| Original subcontract | $2,400,000 |
| Approved subcontract change orders | $46,000 |
| Revised subcontract value | $2,446,000 |
| Work completed to date (55%) | $1,345,300 |
| Less 10% retainage | $134,530 |
| Less previous payments | $1,008,000 |
| Due this period | $202,770 |
If CO #14 had been approved by the owner but no subcontract change order issued, committed cost would still show $2,400,000 and the cost-to-complete would be $46,000 too low.
Subcontract vs related agreements
| Agreement | Parties | Typical use |
|---|---|---|
| Prime contract | Owner and GC | Whole project scope |
| Subcontract | GC and trade contractor | On-site work with labour |
| Sub-subcontract | Sub and lower-tier sub | Part of the sub’s scope |
| Purchase order | GC or sub and supplier | Materials or equipment, no site work |
Why it matters
Most of the dollars on a commercial job run through subcontracts. Each one becomes a commitment in job cost, and every sub pay app, change order and lien waiver hangs off it. If the subcontract value in accounting is wrong, your cost-to-complete is wrong. Payment clauses also decide cash flow: a pay-when-paid clause ties the sub’s payment timing to the owner’s payment, and its enforceability varies by jurisdiction.
What to check before signing
For the GC: the scope exhibit matches what was leveled at bid, insurance and bonding requirements match the prime contract, and notice periods are shorter than the prime’s so claims can be passed up in time. For the sub: the payment clause (pay-when-paid or pay-if-paid), retainage rate and release terms, the change pricing method, back-charge procedure, the schedule the sub is agreeing to meet, and which prime contract documents are incorporated by reference. A sub that signs without reading the incorporated prime contract is bound by terms it hasn’t seen.
Common mistakes
- Issuing owner change orders without matching subcontract change orders, so committed cost lags reality.
- Weak scope exclusions that turn into “that’s not in my contract” fights mid-job.
- Missing flow-down of owner terms like notice periods and liquidated damages.
- Letting subs start work before the subcontract is signed, so the terms are argued after the fact.
- Change notice periods in the subcontract that are longer than the prime contract’s, so the GC can’t pass a sub’s claim on in time.
For checking a subcontractor’s monthly billing against the subcontract, see how to review a subcontractor pay application.
How os.construction handles it
Subcontracts are commitments on the same record as the budget, change orders and pay apps, each with its own schedule of values, and an approved commitment change order updates committed cost. See Commitments.
FAQ
What is a subcontract in construction?
A subcontract is the agreement between a prime contractor, usually the general contractor, and a trade contractor who performs part of the prime contract's work. It sets scope, price, schedule, payment terms, retainage, insurance, change procedures and how the prime contract's requirements apply to the sub.
Does a subcontractor have a contract with the owner?
Normally not. The subcontractor's contract is with the prime contractor, which stays responsible to the owner for the sub's work. Owner requirements reach the sub through flow-down clauses. Lien and payment bond rights can still give a sub remedies against the project or the bond, depending on the jurisdiction.
What is the difference between a subcontract and a purchase order?
A subcontract covers work performed on site, usually labour with materials, and carries site obligations such as insurance, safety, schedule and flow-down terms. A purchase order usually covers materials or equipment delivered by a supplier who doesn't work on site. Some firms use a short-form subcontract for small installers.
What clauses matter most in a subcontract?
Scope and exclusions, price and schedule of values, payment terms including any pay-when-paid or pay-if-paid clause, retainage, change order pricing and notice periods, schedule and delay terms, indemnity and insurance, back-charge rights, default and termination, and dispute resolution. Flow-down of the prime contract ties many of these together.
Are there standard subcontract forms?
Yes. In the US, AIA A401 and ConsensusDocs 750 are widely used. In Canada, CCDC 17 is the stipulated price subcontract. In the UK, JCT publishes subcontract forms for use with its main contracts. Many general contractors use their own form instead, and subs should read it as closely as any standard form.