Prequalification decides who gets invited to bid. Owners prequalify general contractors, and GCs prequalify their subcontractors, usually once a year and again before large awards. A typical subcontractor prequal looks at:
- Safety: EMR (experience modification rate), OSHA logs, recordable incident rates, written safety program.
- Financial: financial statements, working capital, revenue, banking and bonding references, bonding capacity.
- Capacity: current backlog, largest project completed, crew size, single project limit.
- Experience: similar project types, references, licenses.
- Insurance: coverages and limits, often confirmed with a certificate of insurance.
- Legal: litigation history, defaults, liens filed against them.
The result is usually an approval status and a recommended single-project and aggregate limit, meaning the largest contract the GC is comfortable awarding to that sub.
Why it matters
Sub default is one of the biggest risks a GC carries. A subcontractor that’s overextended or undercapitalized can fail mid-job, leaving the GC to finish the work, fix defects and pay their suppliers. Prequalification is the first defense, and if the GC carries subcontractor default insurance, the insurer usually requires a documented prequal process.
Common mistakes
- Prequalifying once and never updating as the sub’s backlog grows.
- Awarding above a sub’s approved limit because they were low bidder.
- Collecting financials but nobody actually reviewing them.
- No check of how much open work the sub already has with you.