Esc

↑↓ move↵ openIndex · Pagefind
Billing

Preliminary Notice

Definition

A notice a sub or supplier sends early in a job to preserve its lien rights, telling the owner and GC it is furnishing labor or materials.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

Updated

A preliminary notice (called a prelim, notice to owner, or notice of furnishing depending on the state) is sent by a subcontractor or supplier to the owner, GC and sometimes the lender, stating that it is providing labor or materials to the project. In many states it is required to preserve lien rights, and must be sent within a set number of days of first furnishing (California’s well-known version is the 20-day preliminary notice). Not every state uses one. Rules vary widely; this is not legal advice.

How it works

  1. First furnishing. The sub or supplier starts work or makes its first delivery. In most states that require notice, the clock starts here.
  2. Gather project details. The sender needs the owner’s name and address, the GC, the lender if there is one, its own customer and a description of what it’s furnishing. A recorded notice of commencement, where the state uses one, is a common source for these.
  3. Serve the notice. It is delivered by the method the statute requires, often certified mail or personal service, and the sender keeps proof of service.
  4. GC and owner log it. The GC adds the sender to its waiver list for the customer named in the notice.
  5. Waivers before payment. When the GC pays the sub, it collects lien waivers from that sub and from the lower tiers that sent prelims, often conditional with the pay app and unconditional once funds clear.
  6. Later notices. If payment stops, the claimant may move on to a notice of nonpayment, a stop payment notice or a mechanics lien, depending on the state and project type.

Worked example

Illustrative: on Riverside Medical Center, the GC receives a prelim from a drywall supplier to CoreDry. That supplier is now added to the waiver list for CoreDry’s billings. Since CoreDry’s waivers are already missing (sample data), the GC might consider a joint check to make sure the supplier is paid.

A second illustration, using California’s 20-day rule: a door supplier first delivers on 3 March but doesn’t serve its prelim until 10 April. Twenty days before 10 April is 21 March. Deliveries before 21 March are generally outside the notice’s protection.

Delivery period Value Covered by the 10 April notice?
3 March to 20 March $18,000 Generally no
21 March onward $27,000 Yes, if other requirements are met
Total furnished $45,000 $27,000 protected

Serving on time, by 23 March, would have protected the full $45,000.

Document Sent by When Purpose
Notice of commencement Owner Before work starts Records project and owner details
Preliminary notice Sub or supplier Early, after first furnishing Preserves lien rights; identifies who’s on the job
Notice of nonpayment Unpaid claimant After a missed payment Warns of nonpayment before a lien
Lien waiver Party being paid With or after each payment Gives up lien rights for amounts paid
Notice of completion Owner At completion Can shorten lien filing deadlines
Mechanics lien Unpaid claimant Within the statutory deadline Secures the claim against the property

Why it matters

Prelims tell the GC who is actually on the job, including sub-tier suppliers it never contracted with directly. Every prelim is someone you may need a lien waiver from. Ignoring them is how a GC ends up paying twice.

For the sub or supplier, a missed prelim can mean losing the lien right altogether, leaving only a claim against its customer, or a payment bond claim on bonded work.

For owners and lenders, prelims are an early warning list. When a construction loan draw comes in, a lender can compare the parties that sent prelims with the waivers supplied, and ask about any gap before releasing funds.

Common mistakes

  • Filing prelims in a drawer instead of adding the sender to the waiver list.
  • Subs and suppliers missing the state deadline and losing lien rights. See preliminary notice requirements by state.
  • Treating a prelim as a sign of a dispute; in many states it’s routine.
  • Sending the notice to the wrong owner, such as a tenant instead of the property owner, or leaving out the lender.
  • Relying on the project address without the correct legal owner name from public records.
  • Assuming the rules for private jobs apply to public ones, which usually use bond claims instead of liens.

How os.construction handles it

In Accounting, Accounts Payable records lien waivers from lower-tier parties as well as from the vendor, and a final retainage release needs every lower tier’s unconditional final waiver. See Accounts payable. Received prelims are not tracked, and notice deadlines are not calculated.

Watch the explainer · 2:04

Mechanics lien deadlines: first vs last furnishing

  1. 0:00Three deadlines, two start dates
  2. 0:18First furnishing starts the notice clock
  3. 0:38Why the notice comes so early
  4. 0:59Last furnishing starts the lien clock
  5. 1:17Then enforce it
  6. 1:39Waivers and holds in os.construction
Read the transcript

A mechanics lien lets an unpaid contractor, sub or supplier make a claim against the improved property. Keeping that right can mean three deadlines: a preliminary notice, the lien itself, and a lawsuit to enforce it. And they don't all start on the same day.

In many states, the notice clock starts at first furnishing: the first day you supply labor or materials to the job. California and Arizona give subs and suppliers twenty days from first furnishing to send a preliminary notice. In Florida, the notice to owner is due within forty-five days after starting to furnish.

Why so early? The notice tells the owner, and often the general contractor and lender, that you're on the job. Miss a required notice and the lien right can be lost or limited, even if you meet every later deadline. In California and Arizona, a late notice covers only work from twenty days before it was served.

The lien deadline is usually counted from your last furnishing, or from completion of the whole project. In Florida, you record within ninety days after your final furnishing. Most states give between about sixty days and six months. Warranty and punch list work often doesn't restart the clock.

Recording isn't the end. The lien expires unless you file suit to enforce it within the state's window. In Florida, that's one year after recording. On public projects you generally can't lien the property; you claim against the payment bond instead. Rules vary by state, and this is general information, not legal advice.

In os.construction, Accounts Payable can hold a bill until the lien waiver it needs is on file, and records conditional and unconditional, progress and final waivers, including from lower tiers. It doesn't calculate or file statutory lien notices, so use the state table and the statute for deadlines.

FAQ

What is a preliminary notice?

It's a written notice that a subcontractor or supplier sends near the start of its work, telling the owner, the general contractor and sometimes the lender that it is furnishing labor or materials to the project. In states that require one, sending it on time is a condition of keeping the right to file a mechanics lien later.

Who has to send a preliminary notice?

It depends on the state. Where they're required, they usually apply to parties without a direct contract with the owner, such as subcontractors, sub-subcontractors and suppliers. Direct contractors and laborers are often treated differently. Check the statute for the state where the project is located.

When is a California 20-day preliminary notice due?

Within 20 days after the claimant first furnishes work or materials to the job. A notice served later is still useful, but in California it generally protects only work furnished within the 20 days before it was served and afterwards.

Does receiving a preliminary notice mean someone is about to file a lien?

No. In states that require them, prelims are routine and many suppliers send one on every job. A prelim tells you who may have lien rights, so you can collect lien waivers from them before paying their customer.

Is a notice to owner the same as a preliminary notice?

Largely, yes. Florida calls its version a notice to owner, and other states use names such as notice of furnishing. The purpose is the same, but deadlines, recipients, content and delivery rules differ by state.

Sources

Open file