Mechanics lien deadlines by state

Preliminary notice, lien recording and enforcement deadlines for private commercial work in all 50 states and DC, with the public-project bond rule and the statute behind every row. Look up a state, see its timeline, estimate your dates, or download the whole table.

  • 51 jurisdictions
  • Official statute links
  • Last verified November 18, 2026
  • Free CSV

Download CSVMarkdownDeadline calculator

General information, not legal advice. Rules vary by state and change.

Lien deadlines are strict and a missed one usually cannot be cured. Each row is a short summary of the statute on the official site linked, read on the date shown; summaries leave out exceptions such as residential projects, notices that shorten a deadline, and tier rules. Read the statute and talk to a construction attorney in the project's state before relying on any date. Where a field could not be confirmed in official text it says not verified here: verify with counsel.

Watch the explainer · 2:04

Mechanics lien deadlines: first vs last furnishing

  1. 0:00Three deadlines, two start dates
  2. 0:18First furnishing starts the notice clock
  3. 0:38Why the notice comes so early
  4. 0:59Last furnishing starts the lien clock
  5. 1:17Then enforce it
  6. 1:39Waivers and holds in os.construction
Read the transcript

A mechanics lien lets an unpaid contractor, sub or supplier make a claim against the improved property. Keeping that right can mean three deadlines: a preliminary notice, the lien itself, and a lawsuit to enforce it. And they don't all start on the same day.

In many states, the notice clock starts at first furnishing: the first day you supply labor or materials to the job. California and Arizona give subs and suppliers twenty days from first furnishing to send a preliminary notice. In Florida, the notice to owner is due within forty-five days after starting to furnish.

Why so early? The notice tells the owner, and often the general contractor and lender, that you're on the job. Miss a required notice and the lien right can be lost or limited, even if you meet every later deadline. In California and Arizona, a late notice covers only work from twenty days before it was served.

The lien deadline is usually counted from your last furnishing, or from completion of the whole project. In Florida, you record within ninety days after your final furnishing. Most states give between about sixty days and six months. Warranty and punch list work often doesn't restart the clock.

Recording isn't the end. The lien expires unless you file suit to enforce it within the state's window. In Florida, that's one year after recording. On public projects you generally can't lien the property; you claim against the payment bond instead. Rules vary by state, and this is general information, not legal advice.

In os.construction, Accounts Payable can hold a bill until the lien waiver it needs is on file, and records conditional and unconditional, progress and final waivers, including from lower tiers. It doesn't calculate or file statutory lien notices, so use the state table and the statute for deadlines.

Timeline and calculator

Estimate your lien deadlines

Pick a state and your role, enter your dates, and see the deadlines on a timeline. Estimates only: dates are plain calendar arithmetic with no weekend or holiday adjustment, and the rules leave out exceptions. Record and serve well before any date shown.

Your role
First day you supplied labor or materials. Used for preliminary notice deadlines.
Last day of substantial work or delivery. Warranty and punch work often does not count.
Only used in states whose clock runs from completion. Blank uses your last furnishing date.

Default dates are an illustrative example.

Texas · Sub or supplierEstimate

Texas mechanics lien timeline (estimate) Texas: First furnishing Mar 2, 2026; Last furnishing Sep 15, 2026; Preliminary notice by Dec 15, 2026; Record the lien by Jan 15, 2027; File suit to enforce by Jan 15, 2028. Estimates only. Furnishing labor or materials Window to record the lien Window to file suit First furnishing Mar 2, 2026 · Monday Last furnishing Sep 15, 2026 · Tuesday · +197 days Preliminary notice by Dec 15, 2026 · Tuesday · +91 days Record the lien by Jan 15, 2027 · Friday · +31 days File suit to enforce by Jan 15, 2028 · Saturday · +365 days
  • Preliminary notice byDec 15, 202615th day of the 3rd month after the month of last furnishingCounted from your last furnishing. Where notice is due for each month or delivery, earlier work has earlier deadlines: read the summary.
  • Record the lien byJan 15, 202715th day of the 4th month after the month of last furnishing
  • File suit to enforce byJan 15, 20281 year after the last day to record the lienCounted from the last day the lien could have been recorded.

Read the Texas rules and statute

All states

Mechanics lien and preliminary notice deadlines, state by state

Private commercial projects. Click a column heading to sort, or filter by state or notice requirement. Each state name jumps to its full entry with sources.

51 jurisdictionsDownload CSV
Mechanics lien deadlines by state. Sortable columns.
Public projectsStatute · verified
AlabamaALVerifyNot verified here: verify with counselAn original contractor (one contracting with the owner, including a supplier selling directly to the owner) must file a verified statement of lien in the county probate office within 6 months after the last item of work or material is furnished.Subcontractors, suppliers and other claimants must file within 4 months after the last item of work or material. Journeymen and day laborers must file within 30 days.An action to enforce the lien must be filed within 6 months after the entire debt the lien secures matures. Courts note this is usually the date of the last labor or materials.Not verified here: verify with counselAla. Code §35-11-210 et seq.(official source, opens in a new tab)Verified 2026-11-18
AlaskaAKSometimesA notice of right to lien is optional. Giving it to the owner before furnishing shifts the burden of proving owner knowledge and consent onto the owner. If the owner records a notice of completion, claimants who never gave one must record within 15 days after it is recorded. Claimants who gave one keep the 120-day window, unless they received the owner's 5-day advance notice of the recording.If no notice of completion is recorded, record a claim of lien within 120 days after completing the contract or ceasing to furnish. If the owner records a notice of completion, claimants who have not given a notice of right to lien (or who got advance notice of the recording) must record within 15 days after it is recorded.Same rules as prime contractors: 120 days after completing the contract or ceasing to furnish, or 15 days after a recorded notice of completion for claimants without a notice of right to lien.Bring an action in superior court within 6 months after the claim of lien is recorded. One extension is available: record an extension notice within that 6 months and sue within 6 months after the extension is recorded.No liens on public property. State and local public contracts over $100,000 require a payment bond. A sub-sub or supplier with no contract with the prime must give the prime written notice within 90 days after its last labor or material. Suit must be filed within 1 year after final settlement of the contract.AS 34.35.050-.120(official source, opens in a new tab)Verified 2026-11-18
ArizonaAZYesEveryone who furnishes labor, professional services, materials, machinery, fixtures or tools, except wage laborers, serves a preliminary 20-day notice on the owner, original contractor, construction lender and their hiring party within 20 days after first furnishing to the jobsite. A late notice covers only items furnished within 20 days before it and afterward.Record the notice and claim of lien within 120 days after completion of the improvement, or within 60 days after a notice of completion is recorded. Completion means the earlier of 30 days after final inspection and written final acceptance by the government body or 60 consecutive days with no work.Same deadline for subcontractors and suppliers: 120 days after completion, or 60 days after a recorded notice of completion. The preliminary 20-day notice must also have been served.Bring a foreclosure action and record a notice of pendency of action with the county recorder within 6 months after the lien is recorded.Contractors on public buildings and works furnish a payment bond for the full contract amount, with no dollar threshold in the statute. A claimant hired by a subcontractor must give the contractor a preliminary 20-day notice and a written notice within 90 days after last furnishing. Suit within 1 year after last furnishing.A.R.S. § 33-981 et seq.(official source, opens in a new tab)Verified 2026-11-18
ArkansasARSometimesCommercial: subs, suppliers, laborers and service providers must notify the owner and the contractor in writing that they are owed and unpaid within 75 days after supplying the labor or materials. Residential (4 or fewer units): the owner must receive the statutory 'Important Notice to Owner' before work starts, normally from the residential contractor. Every claimant must also give the owner 10 days' notice before filing the lien.File a verified lien account with the circuit clerk within 120 days after the work, labor or materials were last furnished. Attach an affidavit of notice proving compliance with the notice rules, including the 10-day pre-filing notice to the owner.Same 120-day filing deadline, with the affidavit of notice attached. On commercial projects the 75-day notice of nonpayment must have been sent first.The lien expires unless an enforcement action is filed and a lis pendens is recorded within 15 months after the lien account is filed.No liens on public property. Public construction contracts over the §22-9-203 threshold require a payment bond equal to the contract amount. A claimant with no contract with the bonded contractor must give the contractor and surety written notice within 90 days after its last labor or materials. Suit on the payment bond is due within 1 year after final payment or after the prime stops work, whichever comes first.Ark. Code §18-44-101 et seq.(official source, opens in a new tab)Verified 2026-11-18
CaliforniaCAYesSubs and suppliers send a preliminary notice to the owner, the direct contractor and any construction lender within 20 days of first furnishing work. A late notice still works, but only for work furnished within 20 days before it was served and afterward. Laborers are exempt; a direct contractor only has to notify the construction lender.A direct contractor records the claim of lien after finishing its contract and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 60 days after that recording, whichever comes first.Subs and suppliers record after they stop providing work and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 30 days after that recording, whichever comes first.Suit to foreclose must be filed within 90 days after the lien is recorded, or the lien expires. A recorded credit extension can push this out, but never past 1 year after completion.Public property can't be liened. Subs and suppliers use a stop payment notice to the public entity or a claim on the payment bond. Anyone without a direct contract with the prime must first give preliminary notice to the public entity and the prime. A stop payment notice is due within 30 days after a notice of completion, acceptance or cessation is recorded, otherwise within 90 days after completion or cessation. Suit on the bond is due within 6 months after the stop payment notice period ends. Payment bond required on contracts over $25,000 (contracts with state entities fall under the Public Contract Code instead).Civ. Code §§8000-9566 (private works liens: §§8400-8494)(official source, opens in a new tab)Verified 2026-11-18
ColoradoCONoNo preliminary notice at the start of work. Before recording, every claimant must serve a notice of intent to file a lien statement on the owner and the prime contractor at least 10 days before filing, by personal service or registered/certified mail.Record the lien statement with the county clerk and recorder within 4 months after the claimant's last labor or materials. Serve the notice of intent at least 10 days before recording.Same 4 months after the claimant's own last labor or materials for subs and suppliers. Laborers paid by the day or piece have until 2 months after completion of the structure. Recording a notice under 38-22-109(10) can extend the deadline to the earlier of 4 months after completion or 6 months after that notice.File suit to enforce the lien and record a notice of the action (lis pendens) within 6 months after the last work or materials or after completion of the improvement. Otherwise the lien stops holding the property.Claimants on public works file a verified statement of claim with the public body that awarded the contract, any time up to final settlement. Suit on the bond is due within 90 days after the published final settlement date. Bond of at least half the contract is required on local contracts over $50,000 and state contracts over $150,000.C.R.S. 38-22-101 et seq.(official source, opens in a new tab)Verified 2026-11-18
ConnecticutCTSometimesClaimants other than the original contractor (and subs whose written subcontract the owner assented to in writing) must serve the owner and the original contractor with a written notice of intent to claim a lien. Service can be any time after starting work but no later than 90 days after they stop furnishing. The original contractor is entitled to this notice only if it recorded an affidavit with the town clerk within 15 days after starting work.Record a sworn certificate of lien with the town clerk within 90 days after ceasing to perform services or furnish materials. Serve a true and attested copy on the owner within 30 days after recording.Subcontractors and suppliers also record the certificate within 90 days after ceasing work and serve the owner within 30 days after recording. Most must also serve the 90-day notice of intent. Sub liens are capped by what the owner agreed to pay the party they claim through.Start a foreclosure action and record a lis pendens within 1 year after the lien was recorded. If an owner's application to discharge or reduce the lien is pending, the deadline is 60 days after that application is finally decided, if later. Otherwise the lien is discharged by law.No liens on public property. State and municipal public contracts over $100,000 require a payment bond. An unpaid claimant serves a notice of claim on the surety and the principal within 180 days after its last work or materials, and sues within 1 year after that date. Retainage claims run from the date the retainage was due.CGS ch. 847, §§49-33 to 49-39(official source, opens in a new tab)Verified 2026-11-18
DelawareDENoNo preliminary notice is required before filing a statement of claim.A contractor in direct contract with the owner files its statement of claim within 180 days after completion of the structure. The statute also lists alternative triggers, such as receipt of 90% of the contract price, the final invoice, or the certificate of occupancy.Subcontractors and suppliers file within 120 days after completing their labor or making their last delivery of materials. A filing is also timely within 120 days of when their final payment (including retainage) is due, or of final payment to the prime contractor.In Delaware the statement of claim is filed in Superior Court and may serve as the complaint. The claim is pursued by writ of scire facias, and the statute sets no separate foreclosure deadline.No liens on public property. On large state public works contracts, the contractor posts a 100% bond that also secures payment to firms furnishing labor or material. Suit on the bond is due within 1 year after the contractor stops work if the bond says so, otherwise within 3 years after the last work.25 Del. C. ch. 27(official source, opens in a new tab)Verified 2026-11-18
District of ColumbiaDCNoNo preliminary notice is required to preserve lien rights. A subcontractor's written notice of unpaid amounts to the owner, sent while the owner still owes the prime contractor, makes later owner payments to the prime presumptively not in good faith.The contractor records a notice of intent to hold a lien during construction or within 90 days after the earlier of completion or termination of the project. It must mail a copy to the owner by certified mail within 5 business days after recording.Subcontractors, suppliers and laborers hired by the original contractor have the same rights and obligations as the original contractor, so they record within the same 90-day window and serve the notice on the owner. Their lien is limited to the amount unpaid to the original contractor.Suit to enforce must be filed within 180 days after the notice of intent is recorded. A notice of pendency of action must be recorded within 10 days after the suit is filed, or the lien terminates.No liens on public property. Contracts over $25,000 for District public work require performance and payment bonds. A claimant without a direct contract with the prime contractor must give the prime written notice within 90 days after its last labor or material. Suit on the bond is due within 1 year after the last labor or material.D.C. Code tit. 40, ch. 3(official source, opens in a new tab)Verified 2026-11-18
FloridaFLYesLienors not in privity with the owner (subs, sub-subs and suppliers, but not laborers) serve a Notice to Owner before starting or within 45 days after starting to furnish, and in any event before the owner's final payment to the contractor. Sub-subs and suppliers to subs must also serve a copy on the contractor. Contractors in direct contract with the owner don't send one.Record the claim of lien within 90 days after the lienor's final furnishing of labor, services or materials. If the contract is terminated, the deadline is 90 days after termination or 90 days after final furnishing, whichever is first.Same as contractors: record within 90 days after the claimant's final furnishing. A timely Notice to Owner is a prerequisite.Suit to enforce must be filed within 1 year after the claim of lien is recorded, or after an amended claim showing a later final-furnishing date. An owner's notice of contest cuts this to 60 days after service.Claimants use the contractor's payment bond. Claimants not in privity with the contractor serve a notice to the contractor before or within 45 days after starting work, then a sworn notice of nonpayment on the contractor and the surety no earlier than 45 days after first furnishing and no later than 90 days after final furnishing. Suit within 1 year after last furnishing. Bond required on state contracts over $100,000; local governments may exempt contracts of $200,000 or less.Fla. Stat. ch. 713, part I(official source, opens in a new tab)Verified 2026-11-18
GeorgiaGASometimesNot verified here: verify with counselRecord the claim of lien with the superior court clerk in the county where the property is located within 90 days after completing the work or furnishing the materials. Send a copy to the owner within 2 business days after filing (and to the contractor if a notice of commencement was filed).Same rule for subcontractors and suppliers: record within 90 days after the last work or materials, and send a copy to the owner within 2 business days (and to the contractor if a notice of commencement was filed).File a lien action within 365 days after the lien is recorded, then file a notice of commencement of lien action with the clerk within 30 days after filing suit. If the owner or contractor records a Notice of Contest of Lien, the deadline drops to 60 days from receiving that notice.Not verified here: verify with counselO.C.G.A. § 44-14-360 et seq.(official source, opens in a new tab)Verified 2026-11-18
HawaiiHINoNo preliminary notice is required on commercial projects. On residential (home) projects the contractor must explain lien rights and bonding options to the homeowner before or at contract signing, and put that information in the written contract.Anyone claiming a lien files an Application and Notice in circuit court within 45 days after the 'date of completion'. That date is when the owner or GC finishes publishing a notice of completion. If no valid notice is published and filed within 1 year after actual completion, completion is deemed to be 1 year after actual completion. The lien attaches only after the court finds probable cause at a hearing.Subcontractors and suppliers follow the same rule as contractors: file within 45 days after the date of completion (publication of the notice of completion). The Application and Notice must be served on the owner, the party that contracted for the work, and the general contractor.The lien expires 3 months after the court enters the Order Directing Lien to Attach, unless an enforcement action is started within that time. This clock runs from the court order, not from the filing of the application.No liens on public property. State construction contracts over $25,000 require a payment bond. Claimants give the contractor and surety written notice within 90 days after their last labor or material, and must sue within 1 year after that date.HRS ch. 507, pt. II(official source, opens in a new tab)Verified 2026-11-18
IdahoIDSometimesNo preliminary notice is required on commercial projects. On residential contracts over $2,000, the general contractor must give the homeowner the §45-525 disclosure statement before contracting, and the lien claim must include proof of that disclosure.File the claim of lien within 90 days after completing labor or services or furnishing materials. Serve a copy on the owner within 5 business days after filing.Subcontractors and suppliers have the same 90 days after their last labor or materials to file. Serve a copy on the owner within 5 business days after filing.Start proceedings to enforce the lien within 6 months after the claim is filed. If a payment or credit extension is endorsed on the lien record, the 6 months run from that payment or from the expiration of the extension.No liens on public works. Public works contracts of $50,000 or more require a payment bond of at least 85% of the contract amount. A claimant with no direct contract with the contractor must notify the contractor within 90 days after its last labor or materials. Suit is due within 1 year.Idaho Code tit. 45, ch. 5(official source, opens in a new tab)Verified 2026-11-18
IllinoisILSometimesSubcontractors and suppliers must serve written notice of their claim on the owner (and lender, if known) within 90 days after completing their work, unless the contractor's sworn statement already disclosed the amount. On an existing owner-occupied single-family home, subs must also notify the occupant within 60 days of first furnishing; late notice protects the lien only to the extent the owner has not yet paid the contractor.Record a claim for lien with the county recorder within 4 months after completion to keep the lien good against third parties (lenders, buyers). As against the owner, the claim may be filed up to 2 years after completion.Serve the 90-day notice on the owner, then record the claim within the same time limits as contractors (4 months after completion as to third parties; 2 years as to the owner).Suit to enforce must be filed within 2 years after completion of the contract or extra work. If the owner or another interested party serves a written demand, suit must be filed within 30 days or the lien is forfeited.No lien on public property; claimants can lien the contract funds by sworn notice to the public body's clerk (or State official) before payment, then sue within 90 days of the notice (770 ILCS 60/23). Payment bond required on public contracts over $150,000 (over $50,000 from 1/1/2029; IDOT and Tollway over $500,000). Bond claimants must file a verified notice within 180 days after last furnishing (copy to the contractor within 10 days) and sue within 1 year after last furnishing.770 ILCS 60(official source, opens in a new tab)Verified 2026-11-18
IndianaINSometimesNot required on commercial projects. A supplier or sub who furnishes on credit for alteration or repair of an owner-occupied 1-2 family dwelling must give the occupying owner notice within 30 days after first delivery or labor. For new construction of an owner's intended 1-2 family home, the notice goes to the owner and is filed with the county recorder within 60 days after first delivery or labor. In either case the notice is a condition of the lien.Record a sworn statement and notice of intention to hold a lien with the county recorder within 90 days after performing labor or furnishing materials. For Class 2 structures (residential, as defined in IC 22-12-1-5) and improvements auxiliary to them, the deadline is 60 days. The recorder mails a copy to the owner.Subcontractors and suppliers have the same deadline: 90 days after their last labor or materials, or 60 days for Class 2 structures.File a complaint to enforce the lien within 1 year after the notice of intention is recorded (or after a recorded written credit expires), or the lien is void. If the owner sends written notice demanding suit, the lienholder must file within 30 days of receiving it.State public works projects estimated at more than $200,000 require a 100% payment bond that directly benefits subcontractors, laborers and suppliers. Sureties are not released until 1 year after final settlement. Local-government projects follow separate rules in IC 36-1-12, which this entry does not cover.IC 32-28-3(official source, opens in a new tab)Verified 2026-11-18
IowaIASometimesCommercial: anyone furnishing to a subcontractor (2nd tier) must send the GC a one-time written notice within 30 days of first furnishing. Residential: subcontractors post a preliminary notice on the state Mechanics' Notice and Lien Registry (MNLR); the GC must first post a notice of commencement within 10 days of starting work.Post the lien on the MNLR within 90 days after last furnishing for full rights. A lien can still be posted up to 2 years and 90 days after last furnishing, but late liens are limited to what the owner still owes at the time of notice.Same 90-day deadline from last furnishing on the MNLR. Liens posted after 90 days (up to 2 years and 90 days) reach only the balance the owner still owes the GC when served.Suit must be brought within 2 years after the 90-day period following last furnishing ends (about 2 years and 90 days). If the owner serves a written demand, suit is due within 30 days of the demand.No mechanic's lien on public improvements; claimants file a sworn claim with the public body against the retained funds and bond. Claims are due within 30 days after completion and final acceptance (later only if funds remain unpaid and no action is pending); suit may be brought 30 to 60 days after final acceptance. Bond required on contracts of $25,000 or more.Iowa Code ch. 572(official source, opens in a new tab)Verified 2026-11-18
KansasKSSometimesNo general preliminary notice on commercial jobs. On owner-occupied residential improvements and new homes for an individual owner, subs and suppliers must mail the owner a statutory warning statement (not needed for claims of $250 or less). For new residential property sold to a buyer, a notice of intent to perform must be filed before the deed is recorded.File a verified lien statement with the district court clerk within 4 months after last furnishing. On non-residential property, filing a notice of extension within those 4 months extends the deadline to 5 months.Subs and suppliers file within 3 months after last furnishing and must serve a copy on an owner. On non-residential property, a notice of extension filed within 3 months (and mailed to the GC) extends the deadline to 5 months.Suit to foreclose must be brought within 1 year after the lien statement is filed (or 1 year from maturity of a promissory note attached instead of an itemized statement).Public contracts over $100,000 require a bond for at least the contract amount, filed with the district court clerk, and no lien attaches once it is filed. Unpaid claimants sue on the bond within 6 months after completion of the improvement.K.S.A. 60-1101 et seq.(official source, opens in a new tab)Verified 2026-11-18
KentuckyKYSometimesClaimants without a direct contract with the owner must send the owner a written notice of intent to lien, with the amount, within 120 days after last furnishing for claims over $1,000, or within 75 days for claims under $1,000. On owner-occupied 1-2 family homes the notice is due within 75 days regardless of amount.File a sworn lien statement with the county clerk within 6 months after last furnishing, and mail a copy to the owner within 7 days of filing or the lien is dissolved.Same 6 months from last furnishing and 7-day mailing to the owner, plus the earlier notice of intent (75 or 120 days after last furnishing) for anyone without a direct owner contract.Suit to enforce must be brought within 12 months after the lien statement is filed (plus 6 months after a personal representative qualifies if the owner dies first).Public property itself cannot be liened; claimants get a lien on the funds the public owner owes the contractor. File a verified statement with the county clerk (county of the owner's seat of government) by the later of 60 days after the end of the month of furnishing or substantial completion, and deliver an attested copy to the public owner. If the contractor protests, suit must be filed and served within 30 days after notice of the protest is mailed.KRS 376.010-376.110(official source, opens in a new tab)Verified 2026-11-18
LouisianaLANoNo general preliminary notice under the Private Works Act since the 2019 rewrite (Act 325). On residential work with no notice of contract, a notice of nonpayment sent to the owner at least 10 days before filing extends the filing window to 70 days. Suppliers can trigger a direct surety payment by sending a notice of nonpayment 45+ days after delivery on bonded jobs.File a statement of privilege within 60 days after the owner files a notice of termination, or 60 days after substantial completion or abandonment if none is filed. If the GC's notice of contract was timely filed, the deadline is 60 days after notice of termination or 7 months after substantial completion. A GC on a contract over $100,000 has no privilege unless a notice of contract was filed before work began.Subs, suppliers, laborers and equipment lessors file within 60 days after notice of termination, or after substantial completion or abandonment if none is filed. If a notice of contract was timely filed, the deadline is 30 days after notice of termination (or 6 months after substantial completion if none), and a copy goes to the owner.Suit against the owner must be instituted within 1 year after filing the statement of claim or privilege.The Private Works Act does not cover public works. Claimants file a sworn statement with the public entity and record it in the parish mortgage records within 45 days after recordation of acceptance (or notice of default). Claimants without a contract with the prime also give the contractor written notice within those 45 days, and unpaid suppliers to a sub send a notice of nonpayment to the GC and owner by the 75th day after the end of the month of delivery; suit on the bond within 1 year from recorded acceptance. Payment bond of at least 50% of the price required on contracts over $25,000.La. R.S. 9:4801 et seq. (Private Works Act)(official source, opens in a new tab)Verified 2026-11-18
MaineMENoNo preliminary notice is required. Claimants without a direct owner contract may send the owner an optional written notice (with the statutory 'paying twice' warning) to cap the owner's payment defense; this matters mainly on residential work, since that defense does not apply to business, commercial or industrial premises unless the owner lives there.A contractor with a direct contract with the owner does not need to record a lien statement; the lien is preserved by filing suit within 120 days after last furnishing.Subs and suppliers without a contract with the owner must record a sworn lien statement with the county register of deeds within 90 days after last furnishing and mail a copy to the owner.All claimants must file suit in Superior or District Court within 120 days after last furnishing. Non-privity claimants may not serve the owner until 30 days after filing.Contracts over $125,000 for public works require a payment bond for the full contract amount. Claimants with no contract with the prime must give the prime written notice within 90 days after last furnishing; suit may be brought after 90 days unpaid and no later than 1 year after last furnishing.10 M.R.S. §§3251-3269(official source, opens in a new tab)Verified 2026-11-18
MarylandMDSometimesSubcontractors and suppliers (not the GC) must give the owner a written notice of intention to claim a lien within 120 days after doing the work or furnishing the materials, by certified or registered mail or personal delivery (posting allowed if the owner can't be reached).File a petition to establish the mechanic's lien in the county circuit court within 180 days after the work is finished or materials furnished. The court then decides whether the lien attaches after a show-cause process.Same 180-day petition deadline, and the petition must show that the 120-day notice to the owner was properly given.The right to enforce expires 1 year after the petition to establish the lien was first filed; a petition to enforce (or to execute on a release bond) must be filed in the lien case within that year.No liens on public property; claimants sue on the payment security, which is required (at least 50% of the contract) on construction contracts above the small procurement amount. Suppliers to a sub with no contract with the prime must give the prime written notice within 90 days after last supplying; suit is due within 1 year after the public body finally accepts the work.Md. Code, Real Prop. §§9-101 to 9-114(official source, opens in a new tab)Verified 2026-11-18
MassachusettsMASometimesOptional but important for lower tiers: a claimant with no contract with the GC should send the GC a notice of identification by certified mail within 30 days of starting work, or its lien is capped at what the GC still owes the claimant's upstream subcontractor. Subs must also give the owner actual notice of their recorded notice of contract.Two recordings at the registry of deeds. First a notice of contract, by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after the last work on the job. Then a statement of account, by the earliest of 90 days after a notice of substantial completion, 120 days after a notice of termination, or 120 days after the last work on the job.Same two steps and deadlines as the GC (written contract required). Both deadlines are measured from the last day the GC or anyone under it worked on the job, not the sub's own last day. The sub's lien is capped at what the owner owes the GC when the owner gets notice.File suit within 90 days after recording the statement of account, and record an attested copy of the complaint at the registry of deeds within 30 days after filing suit, or the lien dissolves.No liens on public property; payment bond of at least half the contract price required on public contracts over $25,000. Second-tier claimants (contract with a sub, none with the prime) must give the prime written notice within 65 days after last furnishing; suit is due within 1 year after last furnishing.M.G.L. c. 254(official source, opens in a new tab)Verified 2026-11-18
MichiganMIYesSubs and suppliers must serve a notice of furnishing within 20 days after first furnishing. It goes to the designee and GC named in the notice of commencement, personally or by certified mail. Late notice still preserves the lien, except for amounts the owner already paid under sworn statements or waivers. GCs in direct contract with the owner don't send one.Record the claim of lien with the county register of deeds within 90 days after the claimant's last labor or materials. Serve it on the designee (or owner) within 15 days after recording.Subs, suppliers and laborers have the same 90 days after their own last furnishing, then service within 15 days. Subs and suppliers must attach proof of service of their notice of furnishing.File suit to foreclose within 1 year after the claim of lien was recorded, and record a lis pendens when the action starts.Public contracts over $50,000 require payment and performance bonds. Claimants without a direct contract with the prime must send notice to the prime within 30 days of first furnishing. They must also notify the prime and the government unit within 90 days of last furnishing, both by certified mail. Suit is due within 1 year after final payment to the prime.MCL 570.1101 et seq. (Construction Lien Act)(official source, opens in a new tab)Verified 2026-11-18
MinnesotaMNSometimesWhere pre-lien notice applies, anyone without a direct owner contract must deliver a written notice to the owner (personally or by certified mail) within 45 days of first furnishing, and the GC must put the statutory notice in its owner contract (or deliver it within 10 days of agreeing on the work). Not required on most larger commercial jobs: nonresidential projects adding or involving more than 5,000 usable sq ft, or wholly residential projects with more than four units.Record a verified lien statement with the county recorder (or registrar of titles) and serve a copy on the owner within 120 days after last furnishing.Same 120 days after last furnishing to record and serve, plus the 45-day pre-lien notice where it applies.File a complaint (or answer in another lien action) within 1 year after the last item of work shown in the recorded lien statement, and record a notice of lis pendens.No liens on public property; public contracts at or above the small-contract threshold in Minn. Stat. 471.345, subd. 3 need payment and performance bonds of at least the contract price. All claimants serve written notice of claim on the surety and contractor within 120 days after last furnishing; suit within 1 year after last furnishing.Minn. Stat. ch. 514 (§§514.01-514.17)(official source, opens in a new tab)Verified 2026-11-18
MississippiMSSometimesOnly on single-family residential work: subs, suppliers and design professionals without a contract with the owner must give the owner a written pre-lien notice at least 10 days before filing a claim of lien. Not required on commercial projects.File the claim of lien with the chancery clerk in the county where the property sits within 90 days after the claimant's last work or materials. Within 2 business days of filing, send a copy to the owner by registered or certified mail or overnight delivery.Same 90 days from the claimant's own last furnishing. Within 2 business days, copies go to both the owner and the GC. Lien rights reach subs and suppliers hired by the GC or by a first-tier sub; lower tiers have no lien.File a payment action (with a lis pendens) within 180 days after the claim of lien is filed, or the lien expires. The owner or GC can shorten this by recording a notice of contest of lien.Contractors on public building and public works contracts must furnish performance and payment bonds equal to the contract amount; small contracts paid lump-sum on completion are exempt. Claimants may sue on the bond if unpaid 90 days after last furnishing; those with no contract with the prime must first give it written notice within 90 days after last furnishing.Miss. Code Ann. §§85-7-401 to 85-7-433(official source, opens in a new tab)Verified 2026-11-18
MissouriMOSometimesOriginal contractors must give the owner a statutory written lien-rights disclosure (at contract signing, first delivery, start of work or with the first invoice) before receiving any payment; it is a condition of the lien. Subs and suppliers must give the owner 10 days' notice of the claim before filing a lien.File the lien statement with the circuit court clerk in the county within 6 months after the debt accrues (generally the last furnishing).Same 6 months after the debt accrues, after serving the owner a 10-day notice of intent. Rented equipment claims: 60 days after the equipment is last removed.Suit to enforce must be started within 6 months after the lien is filed, or the lien expires.No liens on public property; contractors on public works estimated over $50,000 must furnish a payment bond. Remote suppliers must give the contractor written notice of nonpayment within 90 days of last delivery to claim on the bond.RSMo ch. 429(official source, opens in a new tab)Verified 2026-11-18
MontanaMTSometimesSubs and suppliers send a notice of right to claim a lien to the contracting owner within 20 days of first furnishing (45 days in some lender-funded projects) and file a copy with the county clerk and recorder within 5 business days. Not required for original contractors, wage earners, 5+ family dwellings, or partly or wholly commercial improvements.File the lien with the county clerk and recorder no later than 90 days after final furnishing, or 90 days after the owner files a notice of completion, and certify that a copy was served on the owner of record.Same 90-day deadline. On non-commercial work, an unexpired notice of right to claim a lien must be on file; late notice limits the lien to work furnished in the 20 days before the notice.All actions under the lien law must be started within 2 years from the date the lien was filed.No liens on public property; public bodies require a payment bond or deposit (may be waived for building projects under $150,000, or under $7,500 for school districts). Claimants file written notice with the public body within 90 days after the contract is completed and accepted.MCA Title 71, ch. 3, part 5(official source, opens in a new tab)Verified 2026-11-18
NebraskaNENoNo preliminary notice is required. Any claimant may send the contracting owner a notice of right to assert a lien after contracting; on residential (protected-party) jobs it limits the owner's later payments and caps non-prime liens, so it is worth sending there.Record the lien with the register of deeds no later than 120 days after final furnishing, and send the owner a copy within 10 days after recording.Same: record within 120 days after the claimant's final furnishing. Against a residential protected-party owner, the lien is capped by what remains unpaid on the prime contract when the owner gets notice.The lien stays enforceable for 2 years after recording. An owner's written demand can shorten this to 30 days after the claimant receives it.No liens on public property; a payment bond equal to the contract price is required (state jobs over $15,000; local jobs over $10,000). Claimants without a contract with the prime give the contractor written notice within 4 months after last labor or materials; suit within 1 year after final settlement of the prime contract.Neb. Rev. Stat. §§52-125 to 52-159 (Construction Lien Act)(official source, opens in a new tab)Verified 2026-11-18
NevadaNVYesSubs and suppliers deliver a notice of right to lien to the owner in person or by certified mail (copy to the prime contractor). It covers work furnished in the 31 days before the notice and everything after, so send it within 31 days of first furnishing. Prime contractors and labor-only claimants are exempt.Record the notice of lien within 90 days after the latest of completion of the work of improvement, the claimant's last delivery, or last work performed. A recorded and served notice of completion shortens this to 40 days after it is recorded.Same 90-day rule (40 days after a notice of completion), and a notice of right to lien must have been given. On residential jobs, non-laborers must also serve a 15-day notice of intent to lien on the owner and prime contractor, which extends the deadline by 15 days.Suit must be filed within 6 months after the notice of lien is recorded, unless a written extension (up to 1 year from recording) is recorded within that period.No liens on public property; contracts over $100,000 need a payment bond of at least 50% of the contract amount. Claimants without a contract with the prime notify the contractor within 30 days of first furnishing and again within 90 days of last furnishing; suit within 1 year after last furnishing.NRS 108.221-108.246(official source, opens in a new tab)Verified 2026-11-18
New HampshireNHSometimesSubs and suppliers without a contract with the owner must give the owner written notice before starting work or furnishing materials. Later notice is allowed but only reaches amounts then due or becoming due to the contractor above them. They should also give the owner an account at least every 30 days.No lien is recorded. The lien arises automatically and lasts 120 days after the services or materials are furnished; it must be secured by a court attachment of the property within that 120 days.Same 120-day lien period, secured by attachment, but only if the prior notice to the owner was given; the lien is limited to what the owner still owes up the chain.Secure the lien by a writ of attachment (stating that purpose) while the lien continues, i.e. within 120 days after the services or materials are furnished.Bond of at least 100% of the price required on contracts of $75,000 (state) or $125,000 (political subdivisions). File a statement of claim within 90 days after completion and acceptance of the project, with copies to principal and surety; petition in superior court within 1 year after filing the claim.RSA ch. 447(official source, opens in a new tab)Verified 2026-11-18
New JerseyNJSometimesNo preliminary notice is required on commercial jobs. Filing an optional Notice of Unpaid Balance and Right to File Lien gives the lien priority over later-recorded conveyances and mortgages. On residential contracts, the claimant must record that notice within 60 days of last furnishing, followed by arbitration.Lodge the lien claim for record with the county clerk within 90 days after the last work, services, materials or equipment. Serve a copy on the owner and any contractor or sub involved within 10 days after lodging. Warranty or service calls don't extend the date.Subs and suppliers face the same deadline: 90 days after their last furnishing, then service within 10 days. Residential claims follow the notice-and-arbitration process and must be lodged within 120 days of last furnishing.Sue in Superior Court within 1 year after the last furnishing. If the owner, contractor or sub serves a written demand to sue, the deadline becomes 30 days after the claimant receives it.Public works carry a payment bond. Beneficiaries without a direct contract with the prime should give the prime written notice before starting work; rights run only from the date of notice. Send the sureties a statement of the amount due within 1 year after last furnishing. Suit can be filed 90 days after the statement and no later than 1 year after last furnishing. The bond may be waived on local contracts up to $100,000 and State contracts up to $200,000.N.J.S.A. 2A:44A-1 et seq. (Construction Lien Law)(official source, opens in a new tab)Verified 2026-11-18
New MexicoNMSometimesClaimants who do not contract with the owner or the original contractor, on liens over $5,000, give written notice of right to claim a lien to the owner or original contractor within 60 days of first furnishing. Late notice limits the lien to work from 30 days before the notice. Not required on residential property of 4 or fewer units.The original contractor files the lien claim with the county clerk within 120 days after completing its contract, and sends the owner a copy within 15 days of filing.Everyone else files within 90 days after completion of the building or improvement (not their own last work), and sends the owner a copy within 15 days of filing.The lien lapses 2 years after the claim is filed unless court or binding arbitration proceedings to enforce it are started within that time.Not verified here: verify with counselNMSA 1978 §§48-2-1 to 48-2-17(official source, opens in a new tab)Verified 2026-11-18
New YorkNYNoNo preliminary notice is required before filing a notice of lien on a private project. A copy of the filed lien must be served on the owner (see lien summary).File the notice of lien with the county clerk during the work or within 8 months after the last work or materials (4 months for a single-family dwelling). Serve a copy on the owner from 5 days before to 30 days after filing, and file proof of service within 35 days of filing or the lien terminates.Same deadline as contractors: 8 months after the claimant's last work or materials (4 months for a single-family dwelling), with the same owner service and 35-day proof-of-service rule.The lien lapses 1 year after filing unless a foreclosure action is started and a notice of pendency filed. It can be extended by filing an extension with the county clerk (up to 1 year each); liens on single-family dwellings can only be extended by court order.Public improvement liens attach to contract funds: file a notice of lien with the head of the department and the comptroller/financial officer before, or within 30 days after, completion and acceptance; the lien lasts 1 year unless foreclosure is started or it is extended (Lien Law §§12, 18). On state contracts a payment bond is required (may be waived under $100,000); claimants with no direct contract with the prime must give written notice to the prime within 120 days of last furnishing, and suit must be filed within 1 year after the improvement is completed and accepted (State Finance Law §137).Lien Law art. 2 (§§10, 11, 17)(official source, opens in a new tab)Verified 2026-11-18
North CarolinaNCSometimesOn projects that need a lien agent (improvements costing $40,000 or more, except work on an existing owner-occupied single-family home), every potential lien claimant sends a Notice to Lien Agent within 15 days after first furnishing. A later notice still works if sent before the property is sold to a bona fide purchaser, but the lien may then rank behind mortgages recorded first.File the claim of lien on real property with the clerk of superior court within 120 days after the last furnishing of labor or materials at the site.Subcontractors file a claim of lien on real property (through the contractor above them) within 120 days after their own last furnishing. They can also serve a notice of claim of lien upon funds on the owner or other obligor at any time, which makes the obligor hold back unpaid funds. Second- and third-tier claimants can lose lien rights if the owner posts a notice of contract and they do not serve a notice of subcontract.Sue to enforce the lien in the county where the property is located no later than 180 days after the last furnishing of labor or materials.Claimants use the payment bond, which equals 100% of the contract and is required for each contract over $50,000 when the project's contracts total more than $300,000 ($500,000 for State agencies and UNC). A claimant with no contract with the prime gives the prime written notice within 120 days after last furnishing. Suit no earlier than 90 days after last furnishing, and within 1 year after last furnishing or final settlement with the contractor, whichever is later.G.S. ch. 44A, art. 2(official source, opens in a new tab)Verified 2026-11-18
North DakotaNDNoNo notice at the start of work. Before recording, the claimant must send the legal or equitable owner written notice by certified mail that a lien will be claimed, at least 10 days before recording.Record the lien with the county recorder within 90 days after all of the claimant's contribution is done, after the 10-day pre-recording notice to the owner.Same 90 days after the claimant's last contribution. A late lien still binds the owner, except for amounts already paid to the contractor before recording, but not good-faith purchasers or lenders; no lien may be filed more than 3 years after first furnishing.Start a suit and record a lis pendens within 3 years after recording the lien, or within 30 days after an owner's written demand. Give the owner notice of intent to enforce at least 10 days (personal service) or 20 days (registered mail) before suing.No liens on public property; public improvements over $250,000 require a payment bond equal to the contract price. Claimants not paid within 90 days of completing their work may sue on the bond; those without a contract with the prime must give the contractor written notice by registered mail within 90 days after completing their contribution.NDCC ch. 35-27(official source, opens in a new tab)Verified 2026-11-18
OhioOHSometimesIf a notice of commencement was recorded, subs and suppliers not in direct contract with the owner serve a notice of furnishing on the owner's designee and the GC within 21 days of first furnishing. Late notice preserves only work from 21 days before service onward. Not required of GCs, laborers, or on home construction contracts.Record the lien affidavit with the county recorder within 75 days after your last labor or materials (60 days for a 1-2 family dwelling or residential condo unit). Serve a copy on the owner within 30 days after filing.Same as contractors: 75 days after the claimant's last labor or materials (60 days residential), copy to the owner within 30 days of filing; a notice of furnishing is needed first if a notice of commencement was recorded.The lien stays in force 6 years after the affidavit is filed (longer if suit is pending). If the owner or another interested party serves a notice to commence suit, suit must be filed within 60 days or the lien is void.No lien on public property; subs and suppliers can serve a lien affidavit on the public authority within 120 days of last furnishing to reach contract funds (R.C. 1311.26). On the contract bond, claimants send the surety a statement of amount due no later than 90 days after completion and acceptance, wait 60 days, and sue within 1 year of acceptance; subs/suppliers not in privity with the prime whose work costs more than $30,000 must also serve a notice of furnishing (recovery limited to work from 21 days before service onward).R.C. ch. 1311(official source, opens in a new tab)Verified 2026-11-18
OklahomaOKSometimesClaimants other than the original contractor send a pre-lien notice to the original contractor and an owner no later than 75 days after their last supply, and before filing the lien. Not required for claims under $10,000 aggregate or on non-owner-occupied residential projects of 4 or fewer units; it is required on owner-occupied dwellings.The original contractor files a verified lien statement with the county clerk within 4 months after the date materials or equipment were last furnished or labor was last performed.Subs and suppliers file within 90 days after last furnishing or last labor under the subcontract, with an affidavit of pre-lien notice compliance. The clerk mails notice of the lien to the owner within 5 business days after filing.Suit to enforce must be brought within 1 year after the lien is filed with the county clerk.No liens on public property; public construction contracts over $100,000 require a payment bond for the full contract price. Claimants without a contract with the prime give written notice to the contractor and surety within 90 days after last furnishing; suit on the bond within 1 year after last furnishing.42 O.S. §§141-153, 172(official source, opens in a new tab)Verified 2026-11-18
OregonORSometimesClaimants not hired by the owner deliver a notice of right to lien to the owner (in person or by registered or certified mail); it only protects work furnished from 8 business days before delivery, so send it within 8 business days of first furnishing. Not needed for labor on commercial improvements. On residential contracts over $2,000 the original contractor must give the owner the statutory Information Notice to Owner.File the claim of lien with the county recording officer no later than 75 days after the claimant stopped furnishing labor, equipment or materials, or 75 days after completion of construction, whichever is earlier. Mail notice of the filing to the owner and mortgagee within 20 days.Same 75-day rule (earlier of last furnishing or completion of construction), limited to work covered by a timely notice of right to lien.Suit to foreclose must be filed within 120 days after the claim of lien is filed (longer only if extended credit terms are stated in the claim, never past 2 years). Give the owner and mortgagee written notice of intent to foreclose at least 10 days before suing.No liens on public improvements; contracts estimated over $100,000 ($50,000 for transportation work) need a payment bond for the full contract price. Claimants give written notice of claim to the contractor and the contracting agency within 180 days after last furnishing; suit within 2 years after last furnishing.ORS 87.001-87.093(official source, opens in a new tab)Verified 2026-11-18
PennsylvaniaPASometimesOn searchable projects ($1.5M or more) where the owner filed a Notice of Commencement in the State Construction Notices Directory, subcontractors must file a Notice of Furnishing in the directory within 45 days of first furnishing or lose lien rights. Separately, every subcontractor must give the owner a formal notice of intent at least 30 days before filing a lien.File the claim with the prothonotary within 6 months after completing your work (last labor or materials), and serve notice of filing on the owner within 1 month after filing; file the affidavit of service within 20 days after service.Same 6-month filing and 1-month service rules, plus a formal notice of intent to the owner at least 30 days before filing. Only subs contracting with the GC or with a first-tier sub can lien.An action to obtain judgment must be commenced within 2 years from filing the claim (unless the owner extends in writing), and a verdict or judgment must be obtained within 5 years of filing.No lien for work done for a purely public purpose. Prime contractors post a 100% payment bond on public contracts over $5,000. Claimants with no contract with the prime must give written notice to the prime within 90 days of last furnishing. Suit may be brought once 90 days pass after last furnishing unpaid, and must be filed within 1 year (42 Pa.C.S. §5523(3)).Mechanics' Lien Law of 1963, 49 P.S. §1101 et seq.(official source, opens in a new tab)Verified 2026-11-18
Rhode IslandRISometimesA contractor in direct contract with the owner (not a material supplier) must give a Notice of Possible Mechanic's Lien before starting work or delivering materials, either conspicuously in the written contract or by certified mail; without it that contractor has no lien. Subs and suppliers have no preliminary notice requirement.Mail a notice of intention to claim a lien to the owner of record by registered or certified mail and record a copy in the land evidence records of the city or town, before or within 200 days after the work or materials were furnished.Same as the general contractor: mail the notice of intention to the owner and record it within 200 days after the work or materials were furnished. If the mailed notice comes back undelivered, it can be filed with the returned envelope within 30 days of its return (no later than 200 days after mailing).File the complaint to enforce and a notice of lis pendens within 40 days after recording the notice of intention (the complaint on the same day as the lis pendens or within 7 days after).No mechanics' liens on improvements built for, or land owned by, the state or a city or town. State contracts over $150,000 need a payment bond. Claimants without a direct contract with the prime must give the prime written notice by certified mail within 90 days of last furnishing; suit within 2 years of last furnishing (or the bond's longer limit).R.I. Gen. Laws ch. 34-28(official source, opens in a new tab)Verified 2026-11-18
South CarolinaSCSometimesNo general preliminary notice. If a Notice of Project Commencement is filed, a sub-subcontractor or supplier who does not send the contractor a notice of furnishing by certified or registered mail has its lien capped at what the contractor owes the subcontractor. Claimants hired by someone other than the owner must notify the owner in writing of what they furnished for the lien to attach against the owner.Serve the owner and file a sworn statement of account with the register of deeds or clerk of court within 90 days after you last furnish labor or materials.Same 90-day rule for subcontractors and suppliers: serve the owner and file the sworn statement within 90 days after last furnishing. Total liens cannot exceed what the owner still owes on the contract.Start a suit to enforce the lien and file a notice of pendency of action within 6 months after you stop furnishing labor or materials.State construction contracts require a 100% payment bond (may be waived at $50,000 or less). Claimants without a direct contract with the prime must give the prime written notice within 90 days of last furnishing; suit on the bond within 1 year of last furnishing.S.C. Code tit. 29, ch. 5(official source, opens in a new tab)Verified 2026-11-18
South DakotaSDSometimesOnly when a Notice of Project Commencement has been filed: sub-subcontractors and suppliers to subcontractors must send a notice of furnishing by certified or registered mail to the contractor named in that notice, with a copy to the owner, no later than 60 days after their last work. Individual laborers with liens under $2,000 are exempt.File a verified lien statement with the county register of deeds within 120 days after the last work or furnishing. A copy must first be mailed to the owner by registered or certified mail, with the receipt attached to the statement.Same 120-day filing deadline for subcontractors and suppliers. Where a Notice of Project Commencement was filed, lower-tier claimants must also have sent the 60-day notice of furnishing.Assert the lien by complaint or answer within 6 years of the last item in the lien statement. If the owner, owner's agent or contractor serves a written demand, suit must be started within 30 days of service or the lien is forfeited.Public contractors must give a surety bond for prompt payment of laborers and suppliers (waivable on small contracts under the § 5-18A-14 limit). Unpaid claimants may sue on the bond if the public body hasn't within 6 months of completion and final settlement; suit no earlier than 6 months after completion and within 1 year after that.SDCL ch. 44-9(official source, opens in a new tab)Verified 2026-11-18
TennesseeTNVerifyNot verified here: verify with counselNot verified here: verify with counselNot verified here: verify with counselNot verified here: verify with counselNot verified here: verify with counselTenn. Code Ann. tit. 66, ch. 11(official source, opens in a new tab)Not verified
TexasTXYesSubs and suppliers (anyone other than the original contractor) send a notice of claim for unpaid labor or materials to the owner and the original contractor by the 15th day of the 3rd month after each month work was done (2nd month for residential). The calculator date covers only the final month of work. Unpaid retainage not already noticed needs its own notice within 30 days after the claimant's contract ends, or after the original contract is terminated or abandoned if that comes first.The original contractor files the lien affidavit by the 15th day of the 4th month after the month its work was completed, terminated or abandoned (3rd month for residential). A copy goes to the owner within 5 days after filing.Subs and suppliers file the lien affidavit by the 15th day of the 4th month after the month they last provided labor or materials (3rd month for residential). Retainage claims are due by the 15th day of the 3rd month after the original contract is completed, terminated or abandoned. A copy goes to the owner and original contractor within 5 days after filing.Suit to foreclose must be filed within 1 year after the last day the claimant could have filed the lien affidavit. A recorded written agreement with the owner can extend this to 2 years after the affidavit was filed.No liens on public property; claimants use the payment bond. Payment bond required on contracts over $25,000 ($50,000 for municipalities); performance bond over $100,000. Claimants mail a notice of claim with a sworn statement of account to the prime and the surety by the 15th day of the 3rd month after each month of work. Claimants without a direct contract with the prime must also notify the prime by the 15th day of the 2nd month. Suit may be filed if the claim is still unpaid 60 days after notice, and no later than 1 year after the notice was mailed.Prop. Code ch. 53(official source, opens in a new tab)Verified 2026-11-18
UtahUTYesEveryone who wants lien rights, including the prime contractor, must file a preliminary notice with the State Construction Registry within 20 days after first providing work. A late notice only covers work provided from 5 days after it is filed, and has no effect if filed more than 10 days after a notice of completion.Record a notice of construction lien with the county recorder within 180 days after final completion of the original contract, or within 90 days after a notice of completion is filed (never later than 180 days after final completion). Mail a copy to the owner by certified mail within 30 days after filing.Same deadline as the prime: 180 days after final completion of the original contract, or 90 days after a notice of completion. A subcontractor doing substantial work after the certificate of occupancy or final inspection has until 180 days after finishing its own work.File an action to enforce and record a notice of pendency of action within 180 days after recording the notice of construction lien, or the lien is void (extended to 90 days after the stay lifts if the owner files bankruptcy).Public construction contracts awarded under the Procurement Code require a 100% payment bond (waivable by rule; since a 2026 amendment, contracts administered by the state facilities division (DFCM) need a bond only when the division requires one). Claimants unpaid 90 days after last furnishing may sue on the bond within 1 year after last furnishing.Utah Code tit. 38, ch. 1a(official source, opens in a new tab)Verified 2026-11-18
VermontVTSometimesNo preliminary notice for contractors hired by the owner. Subcontractors and suppliers get a lien only by giving the owner (or owner's agent) written notice, stating the payment due date if known; the lien covers only the contract price still unpaid when the owner receives it, so send it early.File a signed lien memorandum with the town clerk where the property is located within 180 days after payment became due for the last labor or materials.Same 180-day filing deadline (from when payment became due for the last labor or materials), after the written notice to the owner. Recovery is limited to what the owner still owed on the contract when notice was received.Start suit and attach the property within 180 days after filing the lien memorandum, or within 180 days after payment becomes due if it was not yet due when you filed.For state transportation contracts, the contractor files a payment bond with the Secretary of Transportation (waivable at $250,000 or less). Claimants file a sworn statement within 90 days after the state's final acceptance of the project and petition Superior Court within 1 year after filing. No general statewide public-works bond statute was confirmed.9 V.S.A. ch. 51 (§§ 1921-1928)(official source, opens in a new tab)Verified 2026-11-18
VirginiaVASometimesNo preliminary notice on commercial projects. On one- or two-family homes where the building permit names a mechanics' lien agent, claimants must notify that agent within 30 days of first furnishing (or of permit issuance). If they're late, the lien covers only work done after the notice.Record a memorandum of lien no later than 90 days after the last day of the month of last work or materials, and no later than 90 days after the structure is completed. The memorandum can't cover work more than 150 days before the last furnishing, except retainage up to 10% of the contract.Subs, sub-subs and suppliers follow the same 90-day recording rule. They must also give written notice of the amount and character of the claim to the owner, and second-tier claimants to the GC as well. A sub's lien is capped at what the owner owes the GC.File suit within 6 months after recording the memorandum, or within 60 days after the structure is completed or work otherwise ends, whichever is later.Claimants on public projects use the payment bond. Claimants without a direct contract with the prime must send notice to the prime by registered or certified mail within 90 days after their last furnishing. Suit is due within 1 year after the claimant's last labor or materials. Bonds are required on non-transportation contracts over $500,000 and Commonwealth-funded transportation contracts over $350,000.Va. Code Title 43, Ch. 1 (43-1 et seq.)(official source, opens in a new tab)Verified 2026-11-18
WashingtonWASometimesSuppliers and others who furnish professional services, materials or equipment without a direct contract with the owner or the prime send the owner a notice of right to claim a lien (and the prime, in some cases). It can be sent any time but only protects items supplied within 60 days before it was sent (10 days for a new single-family home). Laborers, first-tier subcontractors and anyone contracting directly with the owner are exempt.Record the claim of lien within 90 days after you stop furnishing labor, professional services, materials or equipment. Give the owner a copy within 14 days of recording, or lose any claim to attorneys' fees and costs against the owner.Same deadline for subcontractors and suppliers: record within 90 days after their last furnishing, and copy the owner within 14 days of recording.File suit in superior court in the property's county within 8 calendar months after the lien is recorded, and serve the owner within 90 days after filing.Claimants use the contractor's bond, which equals the full contract price for state work (cities and towns can set as little as 25%). File a written claim notice with the public body within 30 days after completion and acceptance of the work. Suppliers to a subcontractor must notify the prime within 10 days of first delivery. On contracts of $150,000 or less the agency can hold 10% retainage instead of a bond.RCW 60.04(official source, opens in a new tab)Verified 2026-11-18
West VirginiaWVNoNo required preliminary notice. Anyone working for the owner's contractor may optionally notify the owner, before starting work, that they will look to the owner if unpaid.Record a sworn notice of lien with the county clerk where the property is located within 100 days after completing the work under your contract with the owner.Subcontractors, and suppliers to a contractor or subcontractor, must record the notice of lien with the county clerk and serve it on the owner (as a legal notice or summons is served) within 100 days after completing the subcontract or ceasing to furnish materials.Start a circuit court action to enforce the lien within 6 months after recording the notice of lien, or the lien is discharged.No lien on public buildings or the land under them. The public body must require a recorded payment bond covering the reasonable cost of labor and materials, and unpaid suppliers and laborers recover from the bond. The statute sets no bond claim notice or suit deadline.W. Va. Code ch. 38, art. 2(official source, opens in a new tab)Verified 2026-11-18
WisconsinWINoNo preliminary notice on nonresidential projects or residential projects adding more than 4 living units. Everyone must still serve the owner a 30-day notice of intent to file a lien before filing (see lien deadlines).Serve the owner a written notice of intent to file a lien at least 30 days before filing, then file the claim for lien with the clerk of circuit court within 6 months after your last labor or materials. Serve a copy of the filed claim on the owner within 30 days after filing.Same as the prime: 30-day notice of intent to the owner, then file the claim for lien within 6 months after your last labor or materials and serve a copy on the owner within 30 days after filing.Bring an action, with summons and complaint filed, within 2 years after filing the claim for lien.Payment and performance bonds are required on state contracts over $369,000 and local contracts over $148,000 (over $74,000 locally, a bond or substitute payment assurance). Subs and suppliers must serve the prime written notice within 60 days of first furnishing (not needed for contracts of $5,000 or less or for subs listed in the prime's contract) and sue on the bond within 1 year after completion of the work. Claimants can also claim against public funds owed to the prime before the prime is paid (§ 779.15).Wis. Stat. ch. 779, subch. I(official source, opens in a new tab)Verified 2026-11-18
WyomingWYYesEveryone must send the record owner a written notice of lien rights (form in W.S. 29-10-101): the prime contractor before receiving any payment, including advances, and subs and suppliers within 30 days after first furnishing, with a copy to the contractor they work for. Missing it bars the lien.Send the owner a notice of intent to lien at least 20 days before filing, then file the lien statement within 150 days after the earlier of your last work or materials or substantial completion of the project. An owner's recorded notice of substantial completion is presumed to set that date.Subcontractors and suppliers file within 120 days after the earlier of their last work or materials or substantial completion of the project (for a subcontractor, after the last day it worked at the contractor's direction), after a 20-day notice of intent to the owner.Start an action to foreclose within 180 days after filing the lien statement, or the lien ends.Public works contracts over $150,000 require a 100% payment and performance bond (smaller contracts may use another guarantee). Claimants sue on the bond, notifying the obligee, within 1 year after the public entity's date of final completion. No pre-suit notice deadline is set in the statute.W.S. 29-2-101 to 29-2-113(official source, opens in a new tab)Verified 2026-11-18

50 of 51 jurisdictions checked against official statute or state government text on November 18, 2026. 10 fields could not be confirmed there and say "verify with counsel". The CSV has the same rows plus the statute URLs and notes.

Reading the table

What each deadline means

Preliminary notice requirements by state

A preliminary notice tells the owner (and often the GC and lender) that you are on the job. Where it is required, missing it usually kills or limits the lien right, even if every later deadline is met. Requirements differ on who must send it (often only parties without a direct contract with the owner), who receives it, how it is delivered and when. Some states key the notice to a recorded notice of commencement, and some count from each delivery rather than the first.

The lien recording deadline

This is the date by which the mechanics lien must be recorded (or filed) with the county where the property sits, and in many states served on the owner too. It usually runs from your last furnishing of labor or materials, or from completion of the whole project. A recorded notice of completion or cessation shortens it in several states.

The enforcement deadline

A recorded lien is not self-executing. You must file suit to foreclose it within the state's window, counted from recording, from last furnishing or from completion. After that the lien lapses, and in many states the owner can shorten the window by serving a notice to commence suit.

Public projects and Little Miller Acts

Public property generally cannot be liened. Instead, each state's "Little Miller Act" requires the prime contractor on public work above a dollar threshold to post a payment bond, and unpaid subs and suppliers claim against it. Bond claims have their own notice and suit deadlines, which are summarized in the Public projects column. Federal projects follow the Miller Act; see construction bonds explained. Some states add a stop payment notice against the public funds.

Counting days, weekends and holidays

The calculator adds calendar days or months to the date you enter. It does not move dates off weekends or holidays, because states treat that differently for lien filings. Treat every computed date as later than your real deadline, and record and serve before it. Keeping the job's first and last furnishing dates, notices and lien waivers on the same record as the pay apps is what makes these deadlines easy to hit; the getting paid in construction guide walks through the whole cycle.

State by state

Lien rules for each state, with sources

Every entry links the statute we read. "Copy Markdown" puts one state's summary on your clipboard for a job file or a note to counsel.

Alabama mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Verify
Not verified here: verify with counsel
Prime contractor lien deadline
An original contractor (one contracting with the owner, including a supplier selling directly to the owner) must file a verified statement of lien in the county probate office within 6 months after the last item of work or material is furnished.6 months after last furnishing
Subcontractor and supplier lien deadline
Subcontractors, suppliers and other claimants must file within 4 months after the last item of work or material. Journeymen and day laborers must file within 30 days.4 months after last furnishing
Enforcement deadline
An action to enforce the lien must be filed within 6 months after the entire debt the lien secures matures. Courts note this is usually the date of the last labor or materials.
Public projects
Not verified here: verify with counsel
Notes
The Legislature's code site loads only through JavaScript, so the deadlines were taken from §35-11-215 and §35-11-221 as quoted in official appellate opinions (2016, 2017). Not verified: the pre-filing notice to the owner that unpaid-balance (sub/supplier) claimants must give under §35-11-218, and the public-works bond statute. Those fields are left null.

Sources read: Massey Asphalt Paving, Inc. v. Lee Land Dev., Inc., No. 2140680 (Ala. Civ. App. Mar. 4, 2016), quoting §35-11-215 and §35-11-221, McGee v. Dillard, No. 2160581 (Ala. Civ. App. Dec. 1, 2017), quoting §35-11-221

Alaska mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
A notice of right to lien is optional. Giving it to the owner before furnishing shifts the burden of proving owner knowledge and consent onto the owner. If the owner records a notice of completion, claimants who never gave one must record within 15 days after it is recorded. Claimants who gave one keep the 120-day window, unless they received the owner's 5-day advance notice of the recording.
Prime contractor lien deadline
If no notice of completion is recorded, record a claim of lien within 120 days after completing the contract or ceasing to furnish. If the owner records a notice of completion, claimants who have not given a notice of right to lien (or who got advance notice of the recording) must record within 15 days after it is recorded.120 days after last furnishing
Subcontractor and supplier lien deadline
Same rules as prime contractors: 120 days after completing the contract or ceasing to furnish, or 15 days after a recorded notice of completion for claimants without a notice of right to lien.120 days after last furnishing
Enforcement deadline
Bring an action in superior court within 6 months after the claim of lien is recorded. One extension is available: record an extension notice within that 6 months and sue within 6 months after the extension is recorded.6 months after the lien is recorded
Public projects
No liens on public property. State and local public contracts over $100,000 require a payment bond. A sub-sub or supplier with no contract with the prime must give the prime written notice within 90 days after its last labor or material. Suit must be filed within 1 year after final settlement of the contract. AS 36.25.010-.020 (official source, opens in a new tab)
Notes
The owner must give claimants who served a notice of right to lien (or a stop-lending notice) at least 5 days' notice before recording a notice of completion. Claimants owed past-due amounts can also give the construction lender a stop-lending notice.

Sources read: AS 34.35.050-.120 (print view), AS 36.25.010-.025 (print view)

Arizona mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Everyone who furnishes labor, professional services, materials, machinery, fixtures or tools, except wage laborers, serves a preliminary 20-day notice on the owner, original contractor, construction lender and their hiring party within 20 days after first furnishing to the jobsite. A late notice covers only items furnished within 20 days before it and afterward.20 days after first furnishing
Prime contractor lien deadline
Record the notice and claim of lien within 120 days after completion of the improvement, or within 60 days after a notice of completion is recorded. Completion means the earlier of 30 days after final inspection and written final acceptance by the government body or 60 consecutive days with no work.120 days after completion
Subcontractor and supplier lien deadline
Same deadline for subcontractors and suppliers: 120 days after completion, or 60 days after a recorded notice of completion. The preliminary 20-day notice must also have been served.120 days after completion
Enforcement deadline
Bring a foreclosure action and record a notice of pendency of action with the county recorder within 6 months after the lien is recorded.6 months after the lien is recorded
Public projects
Contractors on public buildings and works furnish a payment bond for the full contract amount, with no dollar threshold in the statute. A claimant hired by a subcontractor must give the contractor a preliminary 20-day notice and a written notice within 90 days after last furnishing. Suit within 1 year after last furnishing. A.R.S. §§ 34-222, 34-223 (official source, opens in a new tab)
Notes
Owner-occupied 1-2 family dwellings: no lien unless the claimant has a written contract directly with the owner-occupant (A.R.S. § 33-1002). A recorded notice of completion shortens the lien deadline to 60 days after it is recorded.

Sources read: A.R.S. § 33-992.01, A.R.S. § 33-993, A.R.S. § 33-998, A.R.S. § 33-1002, A.R.S. § 34-222, A.R.S. § 34-223

Arkansas mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Commercial: subs, suppliers, laborers and service providers must notify the owner and the contractor in writing that they are owed and unpaid within 75 days after supplying the labor or materials. Residential (4 or fewer units): the owner must receive the statutory 'Important Notice to Owner' before work starts, normally from the residential contractor. Every claimant must also give the owner 10 days' notice before filing the lien.
Prime contractor lien deadline
File a verified lien account with the circuit clerk within 120 days after the work, labor or materials were last furnished. Attach an affidavit of notice proving compliance with the notice rules, including the 10-day pre-filing notice to the owner.120 days after last furnishing
Subcontractor and supplier lien deadline
Same 120-day filing deadline, with the affidavit of notice attached. On commercial projects the 75-day notice of nonpayment must have been sent first.120 days after last furnishing
Enforcement deadline
The lien expires unless an enforcement action is filed and a lis pendens is recorded within 15 months after the lien account is filed.15 months after the lien is recorded
Public projects
No liens on public property. Public construction contracts over the §22-9-203 threshold require a payment bond equal to the contract amount. A claimant with no contract with the bonded contractor must give the contractor and surety written notice within 90 days after its last labor or materials. Suit on the payment bond is due within 1 year after final payment or after the prime stops work, whichever comes first. Ark. Code §§18-44-503, 18-44-508 (as amended by Act 986 of 2021) (official source, opens in a new tab)
Notes
Arkansas's codified statutes are hosted only on a JavaScript-based Lexis site, so these rules were read from enacted session laws and an official court publication. Confirm that no later act changed them. Under Act 984 of 2021, a residential contractor who fails to give the owner notice loses its lien. A payment bond filed before any lien claim can protect private property from liens (§18-44-505).

Sources read: Act 454 of 2009 (text of §§18-44-114 to -118 as amended), Act 984 of 2021 (§18-44-115(a)(4)), Act 986 of 2021 (§§18-44-501 to -508 bonds), Ark. Admin. Office of the Courts, Appellate Update Oct. 2023 (§§18-44-117, -119)

California mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Subs and suppliers send a preliminary notice to the owner, the direct contractor and any construction lender within 20 days of first furnishing work. A late notice still works, but only for work furnished within 20 days before it was served and afterward. Laborers are exempt; a direct contractor only has to notify the construction lender.20 days after first furnishing
Prime contractor lien deadline
A direct contractor records the claim of lien after finishing its contract and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 60 days after that recording, whichever comes first.90 days after completion
Subcontractor and supplier lien deadline
Subs and suppliers record after they stop providing work and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 30 days after that recording, whichever comes first.90 days after completion
Enforcement deadline
Suit to foreclose must be filed within 90 days after the lien is recorded, or the lien expires. A recorded credit extension can push this out, but never past 1 year after completion.90 days after the lien is recorded
Public projects
Public property can't be liened. Subs and suppliers use a stop payment notice to the public entity or a claim on the payment bond. Anyone without a direct contract with the prime must first give preliminary notice to the public entity and the prime. A stop payment notice is due within 30 days after a notice of completion, acceptance or cessation is recorded, otherwise within 90 days after completion or cessation. Suit on the bond is due within 6 months after the stop payment notice period ends. Payment bond required on contracts over $25,000 (contracts with state entities fall under the Public Contract Code instead). Civ. Code §§9100, 9300, 9356, 9550, 9558 (official source, opens in a new tab)
Notes
Completion means actual completion, owner occupation or use plus cessation of labor, 60 days of continuous cessation, or a recorded notice of cessation after 30 days of cessation. A copy of the lien with the statutory Notice of Mechanics Lien must be served on the owner or the lien is unenforceable (§8416). The statute sets the same deadlines for residential work.

Sources read: Civ. Code §8180 (completion), Civ. Code §8200, Civ. Code §8204, Civ. Code §8412, Civ. Code §8414, Civ. Code §8416, Civ. Code §8460, Civ. Code §9100, Civ. Code §9200 (public works completion), Civ. Code §9300, Civ. Code §9356, Civ. Code §9550, Civ. Code §9554, Civ. Code §9558, Civ. Code §9560, Legislative Counsel bulk code data (section text read from here)

Colorado mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice at the start of work. Before recording, every claimant must serve a notice of intent to file a lien statement on the owner and the prime contractor at least 10 days before filing, by personal service or registered/certified mail.
Prime contractor lien deadline
Record the lien statement with the county clerk and recorder within 4 months after the claimant's last labor or materials. Serve the notice of intent at least 10 days before recording.4 months after last furnishing
Subcontractor and supplier lien deadline
Same 4 months after the claimant's own last labor or materials for subs and suppliers. Laborers paid by the day or piece have until 2 months after completion of the structure. Recording a notice under 38-22-109(10) can extend the deadline to the earlier of 4 months after completion or 6 months after that notice.4 months after last furnishing
Enforcement deadline
File suit to enforce the lien and record a notice of the action (lis pendens) within 6 months after the last work or materials or after completion of the improvement. Otherwise the lien stops holding the property.6 months after last furnishing
Public projects
Claimants on public works file a verified statement of claim with the public body that awarded the contract, any time up to final settlement. Suit on the bond is due within 90 days after the published final settlement date. Bond of at least half the contract is required on local contracts over $50,000 and state contracts over $150,000. C.R.S. 38-26-106, 38-26-107 (official source, opens in a new tab)
Notes
Owners of existing single-family homes or owner-occupied new residences have a payment defense under 38-22-102(3.5) if they paid the contractor in full. Liens lapse after 1 year unless suit has started or an annual affidavit is filed (38-22-109(8)). SB 26-074 (effective Aug. 12, 2026) lets lien statements and public verified claims include delay or disruption costs the contract allows and penalizes knowingly excessive public claims. It does not change any deadlines. The enforcement clock uses the earlier trigger (last furnishing); the statute also references completion.

Sources read: C.R.S. Title 38 (2024 official printout): 38-22-102, 38-22-109, 38-22-110, 38-26-106, 38-26-107, SB 26-074 signed act, SB 26-074 bill page

Connecticut mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Claimants other than the original contractor (and subs whose written subcontract the owner assented to in writing) must serve the owner and the original contractor with a written notice of intent to claim a lien. Service can be any time after starting work but no later than 90 days after they stop furnishing. The original contractor is entitled to this notice only if it recorded an affidavit with the town clerk within 15 days after starting work.
Prime contractor lien deadline
Record a sworn certificate of lien with the town clerk within 90 days after ceasing to perform services or furnish materials. Serve a true and attested copy on the owner within 30 days after recording.90 days after last furnishing
Subcontractor and supplier lien deadline
Subcontractors and suppliers also record the certificate within 90 days after ceasing work and serve the owner within 30 days after recording. Most must also serve the 90-day notice of intent. Sub liens are capped by what the owner agreed to pay the party they claim through.90 days after last furnishing
Enforcement deadline
Start a foreclosure action and record a lis pendens within 1 year after the lien was recorded. If an owner's application to discharge or reduce the lien is pending, the deadline is 60 days after that application is finally decided, if later. Otherwise the lien is discharged by law.1 year after the lien is recorded
Public projects
No liens on public property. State and municipal public contracts over $100,000 require a payment bond. An unpaid claimant serves a notice of claim on the surety and the principal within 180 days after its last work or materials, and sues within 1 year after that date. Retainage claims run from the date the retainage was due. CGS §§49-41, 49-42 (official source, opens in a new tab)
Notes
The served notice of intent, with the server's return endorsed, must come back to the claimant within 30 days after the certificate of lien is recorded. §49-39 was last amended by P.A. 16-194. Residential home-improvement rules (CGS ch. 400) were not reviewed.

Sources read: CGS §49-33, CGS §49-34, CGS §49-35, CGS §49-39, CGS §49-41, CGS §49-42

Delaware mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required before filing a statement of claim.
Prime contractor lien deadline
A contractor in direct contract with the owner files its statement of claim within 180 days after completion of the structure. The statute also lists alternative triggers, such as receipt of 90% of the contract price, the final invoice, or the certificate of occupancy.180 days after completion
Subcontractor and supplier lien deadline
Subcontractors and suppliers file within 120 days after completing their labor or making their last delivery of materials. A filing is also timely within 120 days of when their final payment (including retainage) is due, or of final payment to the prime contractor.120 days after last furnishing
Enforcement deadline
In Delaware the statement of claim is filed in Superior Court and may serve as the complaint. The claim is pursued by writ of scire facias, and the statute sets no separate foreclosure deadline.
Public projects
No liens on public property. On large state public works contracts, the contractor posts a 100% bond that also secures payment to firms furnishing labor or material. Suit on the bond is due within 1 year after the contractor stops work if the bond says so, otherwise within 3 years after the last work. 29 Del. C. §6962 (official source, opens in a new tab)
Notes
Under §2707, an owner who uses the property solely as a residence and pays the contractor in full in good faith takes it free of liens. If payment is partial, the lien is limited to the unpaid balance.

Sources read: 25 Del. C. §§2701-2708, 25 Del. C. §§2711-2716, 29 Del. C. §6962

District of Columbia mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required to preserve lien rights. A subcontractor's written notice of unpaid amounts to the owner, sent while the owner still owes the prime contractor, makes later owner payments to the prime presumptively not in good faith.
Prime contractor lien deadline
The contractor records a notice of intent to hold a lien during construction or within 90 days after the earlier of completion or termination of the project. It must mail a copy to the owner by certified mail within 5 business days after recording.90 days after completion
Subcontractor and supplier lien deadline
Subcontractors, suppliers and laborers hired by the original contractor have the same rights and obligations as the original contractor, so they record within the same 90-day window and serve the notice on the owner. Their lien is limited to the amount unpaid to the original contractor.90 days after completion
Enforcement deadline
Suit to enforce must be filed within 180 days after the notice of intent is recorded. A notice of pendency of action must be recorded within 10 days after the suit is filed, or the lien terminates.180 days after the lien is recorded
Public projects
No liens on public property. Contracts over $25,000 for District public work require performance and payment bonds. A claimant without a direct contract with the prime contractor must give the prime written notice within 90 days after its last labor or material. Suit on the bond is due within 1 year after the last labor or material. D.C. Code §§2-201.01, 2-201.02 (official source, opens in a new tab)
Notes
A notice of intent missing any required content is void. Required content includes licensing/good-standing information where applicable and a copy of any home improvement contract. The 90-day clock runs from completion or termination of the project, whichever is earlier.

Sources read: D.C. Code §40-301.01, D.C. Code §40-301.02, D.C. Code §40-303.01, D.C. Code §40-303.02, D.C. Code §40-303.03, D.C. Code §40-303.13, D.C. Code §2-201.01, D.C. Code §2-201.02

Florida mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Lienors not in privity with the owner (subs, sub-subs and suppliers, but not laborers) serve a Notice to Owner before starting or within 45 days after starting to furnish, and in any event before the owner's final payment to the contractor. Sub-subs and suppliers to subs must also serve a copy on the contractor. Contractors in direct contract with the owner don't send one.45 days after first furnishing
Prime contractor lien deadline
Record the claim of lien within 90 days after the lienor's final furnishing of labor, services or materials. If the contract is terminated, the deadline is 90 days after termination or 90 days after final furnishing, whichever is first.90 days after last furnishing
Subcontractor and supplier lien deadline
Same as contractors: record within 90 days after the claimant's final furnishing. A timely Notice to Owner is a prerequisite.90 days after last furnishing
Enforcement deadline
Suit to enforce must be filed within 1 year after the claim of lien is recorded, or after an amended claim showing a later final-furnishing date. An owner's notice of contest cuts this to 60 days after service.1 year after the lien is recorded
Public projects
Claimants use the contractor's payment bond. Claimants not in privity with the contractor serve a notice to the contractor before or within 45 days after starting work, then a sworn notice of nonpayment on the contractor and the surety no earlier than 45 days after first furnishing and no later than 90 days after final furnishing. Suit within 1 year after last furnishing. Bond required on state contracts over $100,000; local governments may exempt contracts of $200,000 or less. Fla. Stat. §255.05 (official source, opens in a new tab)
Notes
A contractor in privity must give the owner a final contractor's affidavit at least 5 days before suing to enforce (§713.06(3)(d)). The statute sets the same lien deadlines for residential work.

Sources read: Fla. Stat. ch. 713 (§§713.06, 713.08, 713.22), 2026 Florida Statutes, Fla. Stat. §255.05, 2026 Florida Statutes

Georgia mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Not verified here: verify with counsel
Prime contractor lien deadline
Record the claim of lien with the superior court clerk in the county where the property is located within 90 days after completing the work or furnishing the materials. Send a copy to the owner within 2 business days after filing (and to the contractor if a notice of commencement was filed).90 days after last furnishing
Subcontractor and supplier lien deadline
Same rule for subcontractors and suppliers: record within 90 days after the last work or materials, and send a copy to the owner within 2 business days (and to the contractor if a notice of commencement was filed).90 days after last furnishing
Enforcement deadline
File a lien action within 365 days after the lien is recorded, then file a notice of commencement of lien action with the clerk within 30 days after filing suit. If the owner or contractor records a Notice of Contest of Lien, the deadline drops to 60 days from receiving that notice.365 days after the lien is recorded
Public projects
Not verified here: verify with counsel
Notes
Verified from Georgia session-law text (signed HB 480 of 2021 and the SB 374 substitute of 2008). The current code on LexisNexis would not load. Liens must state that the lien expires 395 days after filing if no notice of commencement of lien action is filed (§ 44-14-367). A Notice to Contractor applies to claimants without privity when a notice of commencement is filed (§ 44-14-361.5), but its deadline could not be read in official text, so prelim summary is null. Public work (O.C.G.A. 13-10-60 et seq.) is null because no official text of §§ 13-10-63/13-10-65 was reachable.

Sources read: HB 480 (2021), as passed and signed; restates O.C.G.A. § 44-14-361.1 in full, SB 374 (2008) House Judiciary substitute: §§ 44-14-361.1, 44-14-361.5(c), 44-14-367, 44-14-368 (effective 3/31/2009), SB 315 (2020), as passed; amends § 44-14-366 (lien waivers) only

Hawaii mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required on commercial projects. On residential (home) projects the contractor must explain lien rights and bonding options to the homeowner before or at contract signing, and put that information in the written contract.
Prime contractor lien deadline
Anyone claiming a lien files an Application and Notice in circuit court within 45 days after the 'date of completion'. That date is when the owner or GC finishes publishing a notice of completion. If no valid notice is published and filed within 1 year after actual completion, completion is deemed to be 1 year after actual completion. The lien attaches only after the court finds probable cause at a hearing.45 days after a notice of completion is recorded
Subcontractor and supplier lien deadline
Subcontractors and suppliers follow the same rule as contractors: file within 45 days after the date of completion (publication of the notice of completion). The Application and Notice must be served on the owner, the party that contracted for the work, and the general contractor.45 days after a notice of completion is recorded
Enforcement deadline
The lien expires 3 months after the court enters the Order Directing Lien to Attach, unless an enforcement action is started within that time. This clock runs from the court order, not from the filing of the application.
Public projects
No liens on public property. State construction contracts over $25,000 require a payment bond. Claimants give the contractor and surety written notice within 90 days after their last labor or material, and must sue within 1 year after that date. HRS §103D-324 (official source, opens in a new tab)
Notes
If no notice of completion is published, the 45 days effectively run from 1 year after actual completion. The notice of completion is published twice, seven days apart, and must follow substantial completion or abandonment. Residential contractors who skip the HRS §444-25.5 lien disclosures may be barred from liening the home.

Sources read: HRS §507-42, HRS §507-43, HRS §507-47, HRS §444-25.5, HRS §103D-324

Idaho mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No preliminary notice is required on commercial projects. On residential contracts over $2,000, the general contractor must give the homeowner the §45-525 disclosure statement before contracting, and the lien claim must include proof of that disclosure.
Prime contractor lien deadline
File the claim of lien within 90 days after completing labor or services or furnishing materials. Serve a copy on the owner within 5 business days after filing.90 days after last furnishing
Subcontractor and supplier lien deadline
Subcontractors and suppliers have the same 90 days after their last labor or materials to file. Serve a copy on the owner within 5 business days after filing.90 days after last furnishing
Enforcement deadline
Start proceedings to enforce the lien within 6 months after the claim is filed. If a payment or credit extension is endorsed on the lien record, the 6 months run from that payment or from the expiration of the extension.6 months after the lien is recorded
Public projects
No liens on public works. Public works contracts of $50,000 or more require a payment bond of at least 85% of the contract amount. A claimant with no direct contract with the contractor must notify the contractor within 90 days after its last labor or materials. Suit is due within 1 year. Idaho Code §§54-1926, 54-1927 (official source, opens in a new tab)
Notes
§45-507 was last amended in 2022. The §45-525 residential disclosure applies to 1-4 unit residential property and new-home purchasers. On public bond claims, a subcontractor's 1-year suit period runs from when final payment under the subcontract became due.

Sources read: Idaho Code §45-507, Idaho Code §45-510, Idaho Code §45-525, Idaho Code §54-1926, Idaho Code §54-1927

Illinois mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Subcontractors and suppliers must serve written notice of their claim on the owner (and lender, if known) within 90 days after completing their work, unless the contractor's sworn statement already disclosed the amount. On an existing owner-occupied single-family home, subs must also notify the occupant within 60 days of first furnishing; late notice protects the lien only to the extent the owner has not yet paid the contractor.
Prime contractor lien deadline
Record a claim for lien with the county recorder within 4 months after completion to keep the lien good against third parties (lenders, buyers). As against the owner, the claim may be filed up to 2 years after completion.4 months after completion
Subcontractor and supplier lien deadline
Serve the 90-day notice on the owner, then record the claim within the same time limits as contractors (4 months after completion as to third parties; 2 years as to the owner).
Enforcement deadline
Suit to enforce must be filed within 2 years after completion of the contract or extra work. If the owner or another interested party serves a written demand, suit must be filed within 30 days or the lien is forfeited.2 years after completion
Public projects
No lien on public property; claimants can lien the contract funds by sworn notice to the public body's clerk (or State official) before payment, then sue within 90 days of the notice (770 ILCS 60/23). Payment bond required on public contracts over $150,000 (over $50,000 from 1/1/2029; IDOT and Tollway over $500,000). Bond claimants must file a verified notice within 180 days after last furnishing (copy to the contractor within 10 days) and sue within 1 year after last furnishing. 770 ILCS 60/23; 30 ILCS 550/1, 550/2 (official source, opens in a new tab)
Notes
"Completion" is measured from completion of the claimant's contract or later extra work; the statute does not spell out how this applies to subcontractors, so the sub clock is left blank. §24 service methods updated by P.A. 103-827 (eff. 1/1/2025). Bond threshold drops to $50,000 on 1/1/2029.

Sources read: 770 ILCS 60 (Mechanics Lien Act, incl. §§7, 9, 21, 23, 24, 28, 34), 30 ILCS 550 (Public Construction Bond Act, §§1, 2)

Indiana mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Not required on commercial projects. A supplier or sub who furnishes on credit for alteration or repair of an owner-occupied 1-2 family dwelling must give the occupying owner notice within 30 days after first delivery or labor. For new construction of an owner's intended 1-2 family home, the notice goes to the owner and is filed with the county recorder within 60 days after first delivery or labor. In either case the notice is a condition of the lien.
Prime contractor lien deadline
Record a sworn statement and notice of intention to hold a lien with the county recorder within 90 days after performing labor or furnishing materials. For Class 2 structures (residential, as defined in IC 22-12-1-5) and improvements auxiliary to them, the deadline is 60 days. The recorder mails a copy to the owner.90 days after last furnishing
Subcontractor and supplier lien deadline
Subcontractors and suppliers have the same deadline: 90 days after their last labor or materials, or 60 days for Class 2 structures.90 days after last furnishing
Enforcement deadline
File a complaint to enforce the lien within 1 year after the notice of intention is recorded (or after a recorded written credit expires), or the lien is void. If the owner sends written notice demanding suit, the lienholder must file within 30 days of receiving it.1 year after the lien is recorded
Public projects
State public works projects estimated at more than $200,000 require a 100% payment bond that directly benefits subcontractors, laborers and suppliers. Sureties are not released until 1 year after final settlement. Local-government projects follow separate rules in IC 36-1-12, which this entry does not cover. IC 4-13.6-7-6 (official source, opens in a new tab)
Notes
Class 2 structures (IC 22-12-1-5) and improvements auxiliary to them have a 60-day recording deadline. A recorded no-lien contract can bar sub liens on Class 2 and some utility work. A lien in original construction of a 1-2 family home does not attach against an innocent purchaser unless recorded before the deed.

Sources read: IC 32-28-3-1, -3, -6, -10 (Indiana Code 2026, Title 32 Art. 28 PDF), IC 4-13.6-7-2, -6, -7 (Indiana Code 2026, Title 4 Art. 13.6 PDF)

Iowa mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Commercial: anyone furnishing to a subcontractor (2nd tier) must send the GC a one-time written notice within 30 days of first furnishing. Residential: subcontractors post a preliminary notice on the state Mechanics' Notice and Lien Registry (MNLR); the GC must first post a notice of commencement within 10 days of starting work.30 days after first furnishing
Prime contractor lien deadline
Post the lien on the MNLR within 90 days after last furnishing for full rights. A lien can still be posted up to 2 years and 90 days after last furnishing, but late liens are limited to what the owner still owes at the time of notice.90 days after last furnishing
Subcontractor and supplier lien deadline
Same 90-day deadline from last furnishing on the MNLR. Liens posted after 90 days (up to 2 years and 90 days) reach only the balance the owner still owes the GC when served.90 days after last furnishing
Enforcement deadline
Suit must be brought within 2 years after the 90-day period following last furnishing ends (about 2 years and 90 days). If the owner serves a written demand, suit is due within 30 days of the demand.2 years after the last day to record the lien
Public projects
No mechanic's lien on public improvements; claimants file a sworn claim with the public body against the retained funds and bond. Claims are due within 30 days after completion and final acceptance (later only if funds remain unpaid and no action is pending); suit may be brought 30 to 60 days after final acceptance. Bond required on contracts of $25,000 or more. Iowa Code ch. 573 (§§573.2, 573.10, 573.16) (official source, opens in a new tab)
Notes
All liens are posted on the statewide Mechanics' Notice and Lien Registry, not with the county. Residential GCs must give the owner a statutory notice or lose lien rights, and residential sub liens are limited to the balance due when the preliminary notice is posted and received.

Sources read: Iowa Code ch. 572 (2026), incl. §§572.9, 572.10, 572.11, 572.13A, 572.13B, 572.27, 572.28, 572.33, Iowa Code ch. 573 (2026), §§573.2, 573.7, 573.10, 573.16

Kansas mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No general preliminary notice on commercial jobs. On owner-occupied residential improvements and new homes for an individual owner, subs and suppliers must mail the owner a statutory warning statement (not needed for claims of $250 or less). For new residential property sold to a buyer, a notice of intent to perform must be filed before the deed is recorded.
Prime contractor lien deadline
File a verified lien statement with the district court clerk within 4 months after last furnishing. On non-residential property, filing a notice of extension within those 4 months extends the deadline to 5 months.4 months after last furnishing
Subcontractor and supplier lien deadline
Subs and suppliers file within 3 months after last furnishing and must serve a copy on an owner. On non-residential property, a notice of extension filed within 3 months (and mailed to the GC) extends the deadline to 5 months.3 months after last furnishing
Enforcement deadline
Suit to foreclose must be brought within 1 year after the lien statement is filed (or 1 year from maturity of a promissory note attached instead of an itemized statement).1 year after the lien is recorded
Public projects
Public contracts over $100,000 require a bond for at least the contract amount, filed with the district court clerk, and no lien attaches once it is filed. Unpaid claimants sue on the bond within 6 months after completion of the improvement. K.S.A. 60-1111 (official source, opens in a new tab)
Notes
The 1-month extension is not available on residential property. Residential owners are only liable for sub claims for amounts they pay the GC after receiving the warning statement.

Sources read: K.S.A. 60-1102, K.S.A. 60-1103, K.S.A. 60-1103a, K.S.A. 60-1103b, K.S.A. 60-1105, K.S.A. 60-1111

Kentucky mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Claimants without a direct contract with the owner must send the owner a written notice of intent to lien, with the amount, within 120 days after last furnishing for claims over $1,000, or within 75 days for claims under $1,000. On owner-occupied 1-2 family homes the notice is due within 75 days regardless of amount.
Prime contractor lien deadline
File a sworn lien statement with the county clerk within 6 months after last furnishing, and mail a copy to the owner within 7 days of filing or the lien is dissolved.6 months after last furnishing
Subcontractor and supplier lien deadline
Same 6 months from last furnishing and 7-day mailing to the owner, plus the earlier notice of intent (75 or 120 days after last furnishing) for anyone without a direct owner contract.6 months after last furnishing
Enforcement deadline
Suit to enforce must be brought within 12 months after the lien statement is filed (plus 6 months after a personal representative qualifies if the owner dies first).12 months after the lien is recorded
Public projects
Public property itself cannot be liened; claimants get a lien on the funds the public owner owes the contractor. File a verified statement with the county clerk (county of the owner's seat of government) by the later of 60 days after the end of the month of furnishing or substantial completion, and deliver an attested copy to the public owner. If the contractor protests, suit must be filed and served within 30 days after notice of the protest is mailed. KRS 376.210, 376.230, 376.250 (official source, opens in a new tab)
Notes
Owner-occupied 1-2 family homes: no lien for amounts the owner paid before receiving the 75-day notice. The statute does not address a claim of exactly $1,000. KRS 376.010 was amended in 2023 (lessee/lessor lien rules, eff. 6/29/2023).

Sources read: KRS 376.010, KRS 376.080, KRS 376.090, KRS 376.210, KRS 376.230, KRS 376.250

Louisiana mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No general preliminary notice under the Private Works Act since the 2019 rewrite (Act 325). On residential work with no notice of contract, a notice of nonpayment sent to the owner at least 10 days before filing extends the filing window to 70 days. Suppliers can trigger a direct surety payment by sending a notice of nonpayment 45+ days after delivery on bonded jobs.
Prime contractor lien deadline
File a statement of privilege within 60 days after the owner files a notice of termination, or 60 days after substantial completion or abandonment if none is filed. If the GC's notice of contract was timely filed, the deadline is 60 days after notice of termination or 7 months after substantial completion. A GC on a contract over $100,000 has no privilege unless a notice of contract was filed before work began.60 days after completion
Subcontractor and supplier lien deadline
Subs, suppliers, laborers and equipment lessors file within 60 days after notice of termination, or after substantial completion or abandonment if none is filed. If a notice of contract was timely filed, the deadline is 30 days after notice of termination (or 6 months after substantial completion if none), and a copy goes to the owner.60 days after completion
Enforcement deadline
Suit against the owner must be instituted within 1 year after filing the statement of claim or privilege.1 year after the lien is recorded
Public projects
The Private Works Act does not cover public works. Claimants file a sworn statement with the public entity and record it in the parish mortgage records within 45 days after recordation of acceptance (or notice of default). Claimants without a contract with the prime also give the contractor written notice within those 45 days, and unpaid suppliers to a sub send a notice of nonpayment to the GC and owner by the 75th day after the end of the month of delivery; suit on the bond within 1 year from recorded acceptance. Payment bond of at least 50% of the price required on contracts over $25,000. La. R.S. 38:2241, 38:2242, 38:2247 (official source, opens in a new tab)
Notes
Deadlines run from the owner's notice of termination or from substantial completion, not from the claimant's last work. Act 325 of 2019 rewrote the Private Works Act and repealed the old supplier notice of nonpayment in 9:4802(G). If the owner files a notice of contract with a proper bond, the owner is relieved of sub claims and claimants look to the bond. 2026 SB 308 (public-works notice of nonpayment) never left committee.

Sources read: La. R.S. 9:4802, La. R.S. 9:4808, La. R.S. 9:4811, La. R.S. 9:4812, La. R.S. 9:4822, La. R.S. 9:4823, La. R.S. 38:2241, La. R.S. 38:2242, La. R.S. 38:2247, 2026 SB 308 bill history

Maine mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required. Claimants without a direct owner contract may send the owner an optional written notice (with the statutory 'paying twice' warning) to cap the owner's payment defense; this matters mainly on residential work, since that defense does not apply to business, commercial or industrial premises unless the owner lives there.
Prime contractor lien deadline
A contractor with a direct contract with the owner does not need to record a lien statement; the lien is preserved by filing suit within 120 days after last furnishing.
Subcontractor and supplier lien deadline
Subs and suppliers without a contract with the owner must record a sworn lien statement with the county register of deeds within 90 days after last furnishing and mail a copy to the owner.90 days after last furnishing
Enforcement deadline
All claimants must file suit in Superior or District Court within 120 days after last furnishing. Non-privity claimants may not serve the owner until 30 days after filing.120 days after last furnishing
Public projects
Contracts over $125,000 for public works require a payment bond for the full contract amount. Claimants with no contract with the prime must give the prime written notice within 90 days after last furnishing; suit may be brought after 90 days unpaid and no later than 1 year after last furnishing. 14 M.R.S. §871 (official source, opens in a new tab)
Notes
Maine's lien statute expressly reaches municipal and other local public buildings (10 M.R.S. §3251), unlike most states. A GC that skips the optional recorded notice may lose out to a bona fide purchaser who takes title before suit notice is recorded. Owners can block future non-privity liens by giving written notice that they will not be responsible.

Sources read: 10 M.R.S. §3251, 10 M.R.S. §3252, 10 M.R.S. §3253, 10 M.R.S. §3255, 14 M.R.S. §871

Maryland mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Subcontractors and suppliers (not the GC) must give the owner a written notice of intention to claim a lien within 120 days after doing the work or furnishing the materials, by certified or registered mail or personal delivery (posting allowed if the owner can't be reached).
Prime contractor lien deadline
File a petition to establish the mechanic's lien in the county circuit court within 180 days after the work is finished or materials furnished. The court then decides whether the lien attaches after a show-cause process.180 days after last furnishing
Subcontractor and supplier lien deadline
Same 180-day petition deadline, and the petition must show that the 120-day notice to the owner was properly given.180 days after last furnishing
Enforcement deadline
The right to enforce expires 1 year after the petition to establish the lien was first filed; a petition to enforce (or to execute on a release bond) must be filed in the lien case within that year.1 year after the lien is recorded
Public projects
No liens on public property; claimants sue on the payment security, which is required (at least 50% of the contract) on construction contracts above the small procurement amount. Suppliers to a sub with no contract with the prime must give the prime written notice within 90 days after last supplying; suit is due within 1 year after the public body finally accepts the work. Md. Code, State Fin. & Proc. §§17-101 to 17-111 (official source, opens in a new tab)
Notes
The 120-day notice runs from when the work was done or materials furnished, so a sub working over a long period should send it early enough to cover earlier work. For a single-family home built on the owner's land as the owner's residence, a sub has no lien if the owner paid the GC in full before getting the notice, and the lien is capped at what the owner still owed when notified.

Sources read: Real Prop. §9-104, Real Prop. §9-105, Real Prop. §9-106, Real Prop. §9-109, State Fin. & Proc. §17-103, State Fin. & Proc. §17-108, State Fin. & Proc. §17-109

Massachusetts mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Optional but important for lower tiers: a claimant with no contract with the GC should send the GC a notice of identification by certified mail within 30 days of starting work, or its lien is capped at what the GC still owes the claimant's upstream subcontractor. Subs must also give the owner actual notice of their recorded notice of contract.30 days after first furnishing
Prime contractor lien deadline
Two recordings at the registry of deeds. First a notice of contract, by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after the last work on the job. Then a statement of account, by the earliest of 90 days after a notice of substantial completion, 120 days after a notice of termination, or 120 days after the last work on the job.90 days after last furnishing
Subcontractor and supplier lien deadline
Same two steps and deadlines as the GC (written contract required). Both deadlines are measured from the last day the GC or anyone under it worked on the job, not the sub's own last day. The sub's lien is capped at what the owner owes the GC when the owner gets notice.90 days after completion
Enforcement deadline
File suit within 90 days after recording the statement of account, and record an attested copy of the complaint at the registry of deeds within 30 days after filing suit, or the lien dissolves.90 days after the lien is recorded
Public projects
No liens on public property; payment bond of at least half the contract price required on public contracts over $25,000. Second-tier claimants (contract with a sub, none with the prime) must give the prime written notice within 65 days after last furnishing; suit is due within 1 year after last furnishing. M.G.L. c. 149, §29 (official source, opens in a new tab)
Notes
The clocks shown are for the first step (notice of contract, 90 days); the statement of account follows by 120 days. Both are cut short if the owner records a notice of substantial completion (60/90 days) or a notice of termination. A written contract is required. Design professionals have their own lien sections (c. 254, §§2C-2D).

Sources read: M.G.L. c. 254, §2, M.G.L. c. 254, §4, M.G.L. c. 254, §5, M.G.L. c. 254, §8, M.G.L. c. 254, §11, M.G.L. c. 149, §29

Michigan mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Subs and suppliers must serve a notice of furnishing within 20 days after first furnishing. It goes to the designee and GC named in the notice of commencement, personally or by certified mail. Late notice still preserves the lien, except for amounts the owner already paid under sworn statements or waivers. GCs in direct contract with the owner don't send one.20 days after first furnishing
Prime contractor lien deadline
Record the claim of lien with the county register of deeds within 90 days after the claimant's last labor or materials. Serve it on the designee (or owner) within 15 days after recording.90 days after last furnishing
Subcontractor and supplier lien deadline
Subs, suppliers and laborers have the same 90 days after their own last furnishing, then service within 15 days. Subs and suppliers must attach proof of service of their notice of furnishing.90 days after last furnishing
Enforcement deadline
File suit to foreclose within 1 year after the claim of lien was recorded, and record a lis pendens when the action starts.1 year after the lien is recorded
Public projects
Public contracts over $50,000 require payment and performance bonds. Claimants without a direct contract with the prime must send notice to the prime within 30 days of first furnishing. They must also notify the prime and the government unit within 90 days of last furnishing, both by certified mail. Suit is due within 1 year after final payment to the prime. MCL 129.201 et seq. (official source, opens in a new tab)
Notes
Laborers have their own notice rules: 30 days after unpaid wages were due, and the 5th of the 2nd month for fringe benefits. 570.1109 was last amended by 2018 PA 367. On residential jobs, sub and supplier liens can't include interest accruing more than 90 days after recording. Other residential owner protections in the Act weren't verified here.

Sources read: MCL 570.1107, MCL 570.1109, MCL 570.1111, MCL 570.1117, MCL 129.201, MCL 129.207, MCL 129.209

Minnesota mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Where pre-lien notice applies, anyone without a direct owner contract must deliver a written notice to the owner (personally or by certified mail) within 45 days of first furnishing, and the GC must put the statutory notice in its owner contract (or deliver it within 10 days of agreeing on the work). Not required on most larger commercial jobs: nonresidential projects adding or involving more than 5,000 usable sq ft, or wholly residential projects with more than four units.45 days after first furnishing
Prime contractor lien deadline
Record a verified lien statement with the county recorder (or registrar of titles) and serve a copy on the owner within 120 days after last furnishing.120 days after last furnishing
Subcontractor and supplier lien deadline
Same 120 days after last furnishing to record and serve, plus the 45-day pre-lien notice where it applies.120 days after last furnishing
Enforcement deadline
File a complaint (or answer in another lien action) within 1 year after the last item of work shown in the recorded lien statement, and record a notice of lis pendens.1 year after last furnishing
Public projects
No liens on public property; public contracts at or above the small-contract threshold in Minn. Stat. 471.345, subd. 3 need payment and performance bonds of at least the contract price. All claimants serve written notice of claim on the surety and contractor within 120 days after last furnishing; suit within 1 year after last furnishing. Minn. Stat. §§574.26-574.32 (official source, opens in a new tab)
Notes
A GC that is required to give the owner notice and fails to loses its lien entirely; the same goes for a sub that misses the 45-day notice where required. The pre-lien notice also does not apply when the contractor and owner are under common control.

Sources read: Minn. Stat. §514.011, Minn. Stat. §514.08, Minn. Stat. §514.12, Minn. Stat. §574.26, Minn. Stat. §574.31

Mississippi mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Only on single-family residential work: subs, suppliers and design professionals without a contract with the owner must give the owner a written pre-lien notice at least 10 days before filing a claim of lien. Not required on commercial projects.
Prime contractor lien deadline
File the claim of lien with the chancery clerk in the county where the property sits within 90 days after the claimant's last work or materials. Within 2 business days of filing, send a copy to the owner by registered or certified mail or overnight delivery.90 days after last furnishing
Subcontractor and supplier lien deadline
Same 90 days from the claimant's own last furnishing. Within 2 business days, copies go to both the owner and the GC. Lien rights reach subs and suppliers hired by the GC or by a first-tier sub; lower tiers have no lien.90 days after last furnishing
Enforcement deadline
File a payment action (with a lis pendens) within 180 days after the claim of lien is filed, or the lien expires. The owner or GC can shorten this by recording a notice of contest of lien.180 days after the lien is recorded
Public projects
Contractors on public building and public works contracts must furnish performance and payment bonds equal to the contract amount; small contracts paid lump-sum on completion are exempt. Claimants may sue on the bond if unpaid 90 days after last furnishing; those with no contract with the prime must first give it written notice within 90 days after last furnishing. Miss. Code Ann. §31-5-51 (official source, opens in a new tab)
Notes
Mississippi's official code is published through LexisNexis and could not be read directly; lien rules were read from the enrolled 2014 act (effective April 11, 2014), and the later amendment bills found (2016-2024) all died. No lien for contractors or subs who are not properly licensed. The public bond suit deadline (§31-5-53) and the exact lump-sum exemption threshold were not verified.

Sources read: 2014 SB 2622 as sent to Governor (Laws 2014, enacting §§85-7-401 to 85-7-433, incl. §§85-7-403, -405, -409, -423), 2022 SB 2465 history (amendment to §85-7-405 died in committee), 2024 HB 1569 history (lien revisions died in committee), 2026 HB 496 as introduced (reproduces current §31-5-51; died in committee)

Missouri mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Original contractors must give the owner a statutory written lien-rights disclosure (at contract signing, first delivery, start of work or with the first invoice) before receiving any payment; it is a condition of the lien. Subs and suppliers must give the owner 10 days' notice of the claim before filing a lien.
Prime contractor lien deadline
File the lien statement with the circuit court clerk in the county within 6 months after the debt accrues (generally the last furnishing).6 months after last furnishing
Subcontractor and supplier lien deadline
Same 6 months after the debt accrues, after serving the owner a 10-day notice of intent. Rented equipment claims: 60 days after the equipment is last removed.6 months after last furnishing
Enforcement deadline
Suit to enforce must be started within 6 months after the lien is filed, or the lien expires.6 months after the lien is recorded
Public projects
No liens on public property; contractors on public works estimated over $50,000 must furnish a payment bond. Remote suppliers must give the contractor written notice of nonpayment within 90 days of last delivery to claim on the bond. RSMo §107.170 (official source, opens in a new tab)
Notes
Original contractor disclosure (§429.012, amended eff. 1/1/2017) does not apply to new residences with title-insurer lien protection. §107.170 amended eff. 8/28/2025; a compliant public-works bond bars sub/supplier liens. Bond suit deadline not verified.

Sources read: RSMo §429.012, RSMo §429.080, RSMo §429.100, RSMo §429.170, RSMo §107.170

Montana mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Subs and suppliers send a notice of right to claim a lien to the contracting owner within 20 days of first furnishing (45 days in some lender-funded projects) and file a copy with the county clerk and recorder within 5 business days. Not required for original contractors, wage earners, 5+ family dwellings, or partly or wholly commercial improvements.
Prime contractor lien deadline
File the lien with the county clerk and recorder no later than 90 days after final furnishing, or 90 days after the owner files a notice of completion, and certify that a copy was served on the owner of record.90 days after last furnishing
Subcontractor and supplier lien deadline
Same 90-day deadline. On non-commercial work, an unexpired notice of right to claim a lien must be on file; late notice limits the lien to work furnished in the 20 days before the notice.90 days after last furnishing
Enforcement deadline
All actions under the lien law must be started within 2 years from the date the lien was filed.2 years after the lien is recorded
Public projects
No liens on public property; public bodies require a payment bond or deposit (may be waived for building projects under $150,000, or under $7,500 for school districts). Claimants file written notice with the public body within 90 days after the contract is completed and accepted. MCA §§18-2-201, 18-2-204 (official source, opens in a new tab)
Notes
Text checked in MCA 2025. Statute lists final furnishing or owner's notice of completion as the 90-day trigger without saying which controls. No statutory deadline to sue on the public bond found.

Sources read: MCA §71-3-531, MCA §71-3-535, MCA §71-3-562, MCA §18-2-201, MCA §18-2-204

Nebraska mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required. Any claimant may send the contracting owner a notice of right to assert a lien after contracting; on residential (protected-party) jobs it limits the owner's later payments and caps non-prime liens, so it is worth sending there.
Prime contractor lien deadline
Record the lien with the register of deeds no later than 120 days after final furnishing, and send the owner a copy within 10 days after recording.120 days after last furnishing
Subcontractor and supplier lien deadline
Same: record within 120 days after the claimant's final furnishing. Against a residential protected-party owner, the lien is capped by what remains unpaid on the prime contract when the owner gets notice.120 days after last furnishing
Enforcement deadline
The lien stays enforceable for 2 years after recording. An owner's written demand can shorten this to 30 days after the claimant receives it.2 years after the lien is recorded
Public projects
No liens on public property; a payment bond equal to the contract price is required (state jobs over $15,000; local jobs over $10,000). Claimants without a contract with the prime give the contractor written notice within 4 months after last labor or materials; suit within 1 year after final settlement of the prime contract. Neb. Rev. Stat. §§52-118 to 52-118.02 (official source, opens in a new tab)
Notes
Current text gives 120 days to record (older guides cite 90 days). Notice of commencement affects priority, not the recording deadline.

Sources read: Neb. Rev. Stat. §52-135, Neb. Rev. Stat. §52-136, Neb. Rev. Stat. §52-137, Neb. Rev. Stat. §52-140, Neb. Rev. Stat. §52-118, Neb. Rev. Stat. §52-118.01, Neb. Rev. Stat. §52-118.02

Nevada mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Subs and suppliers deliver a notice of right to lien to the owner in person or by certified mail (copy to the prime contractor). It covers work furnished in the 31 days before the notice and everything after, so send it within 31 days of first furnishing. Prime contractors and labor-only claimants are exempt.31 days after first furnishing
Prime contractor lien deadline
Record the notice of lien within 90 days after the latest of completion of the work of improvement, the claimant's last delivery, or last work performed. A recorded and served notice of completion shortens this to 40 days after it is recorded.90 days after completion
Subcontractor and supplier lien deadline
Same 90-day rule (40 days after a notice of completion), and a notice of right to lien must have been given. On residential jobs, non-laborers must also serve a 15-day notice of intent to lien on the owner and prime contractor, which extends the deadline by 15 days.90 days after completion
Enforcement deadline
Suit must be filed within 6 months after the notice of lien is recorded, unless a written extension (up to 1 year from recording) is recorded within that period.6 months after the lien is recorded
Public projects
No liens on public property; contracts over $100,000 need a payment bond of at least 50% of the contract amount. Claimants without a contract with the prime notify the contractor within 30 days of first furnishing and again within 90 days of last furnishing; suit within 1 year after last furnishing. NRS 339.025-339.055 (official source, opens in a new tab)
Notes
The 90-day lien period runs from the latest of project completion or the claimant's last work, so the completion clock is the outer date. The 15-day notice of intent applies only to residential projects.

Sources read: NRS 108.226, 108.233, 108.245, NRS 339.025, 339.035, 339.055

New Hampshire mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Subs and suppliers without a contract with the owner must give the owner written notice before starting work or furnishing materials. Later notice is allowed but only reaches amounts then due or becoming due to the contractor above them. They should also give the owner an account at least every 30 days.
Prime contractor lien deadline
No lien is recorded. The lien arises automatically and lasts 120 days after the services or materials are furnished; it must be secured by a court attachment of the property within that 120 days.120 days after last furnishing
Subcontractor and supplier lien deadline
Same 120-day lien period, secured by attachment, but only if the prior notice to the owner was given; the lien is limited to what the owner still owes up the chain.120 days after last furnishing
Enforcement deadline
Secure the lien by a writ of attachment (stating that purpose) while the lien continues, i.e. within 120 days after the services or materials are furnished.120 days after last furnishing
Public projects
Bond of at least 100% of the price required on contracts of $75,000 (state) or $125,000 (political subdivisions). File a statement of claim within 90 days after completion and acceptance of the project, with copies to principal and surety; petition in superior court within 1 year after filing the claim. RSA 447:15-447:18 (official source, opens in a new tab)
Notes
New Hampshire has no recorded lien statement; the attachment is the enforcement step and must happen inside the 120-day window. Courts require strict compliance.

Sources read: RSA 447:2-447:18 (merged chapter)

New Jersey mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No preliminary notice is required on commercial jobs. Filing an optional Notice of Unpaid Balance and Right to File Lien gives the lien priority over later-recorded conveyances and mortgages. On residential contracts, the claimant must record that notice within 60 days of last furnishing, followed by arbitration.
Prime contractor lien deadline
Lodge the lien claim for record with the county clerk within 90 days after the last work, services, materials or equipment. Serve a copy on the owner and any contractor or sub involved within 10 days after lodging. Warranty or service calls don't extend the date.90 days after last furnishing
Subcontractor and supplier lien deadline
Subs and suppliers face the same deadline: 90 days after their last furnishing, then service within 10 days. Residential claims follow the notice-and-arbitration process and must be lodged within 120 days of last furnishing.90 days after last furnishing
Enforcement deadline
Sue in Superior Court within 1 year after the last furnishing. If the owner, contractor or sub serves a written demand to sue, the deadline becomes 30 days after the claimant receives it.1 year after last furnishing
Public projects
Public works carry a payment bond. Beneficiaries without a direct contract with the prime should give the prime written notice before starting work; rights run only from the date of notice. Send the sureties a statement of the amount due within 1 year after last furnishing. Suit can be filed 90 days after the statement and no later than 1 year after last furnishing. The bond may be waived on local contracts up to $100,000 and State contracts up to $200,000. N.J.S.A. 2A:44-143 to 2A:44-148 (official source, opens in a new tab)
Notes
Deadlines reflect the 2010 amendments (P.L.2010, c.119). Residential contracts require a Notice of Unpaid Balance within 60 days and arbitration, then lodging within 10 days of the arbitrator's decision and within 120 days of last furnishing. The official statute database has no stable per-section links; search the section number there.

Sources read: N.J.S.A. 2A:44A-6 (NJ Legislature statutes database, updated through P.L.2026, c.70), N.J.S.A. 2A:44A-7, N.J.S.A. 2A:44A-14, N.J.S.A. 2A:44A-20, N.J.S.A. 2A:44A-21, N.J.S.A. 2A:44-143, N.J.S.A. 2A:44-145

New Mexico mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Claimants who do not contract with the owner or the original contractor, on liens over $5,000, give written notice of right to claim a lien to the owner or original contractor within 60 days of first furnishing. Late notice limits the lien to work from 30 days before the notice. Not required on residential property of 4 or fewer units.60 days after first furnishing
Prime contractor lien deadline
The original contractor files the lien claim with the county clerk within 120 days after completing its contract, and sends the owner a copy within 15 days of filing.120 days after completion
Subcontractor and supplier lien deadline
Everyone else files within 90 days after completion of the building or improvement (not their own last work), and sends the owner a copy within 15 days of filing.90 days after completion
Enforcement deadline
The lien lapses 2 years after the claim is filed unless court or binding arbitration proceedings to enforce it are started within that time.2 years after the lien is recorded
Public projects
Not verified here: verify with counsel
Notes
The official compiled NMSA site (nmonesource.com) blocked access, so rules were read from the enacting bills on nmlegis.gov: §48-2-6 as amended in 2023 (owner copy within 15 days; missing it may forfeit interest, fees and costs) and §§48-2-2.1, 48-2-10 as amended in 2007. Later amendments to those two sections were not checked. Public works bond rules (NMSA §13-4-18 et seq.) not verified.

Sources read: 2023 HB 179 (amends §48-2-6), amendments in context, 2007 SB 574 final (amends §§48-2-2.1, 48-2-10)

New York mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice is required before filing a notice of lien on a private project. A copy of the filed lien must be served on the owner (see lien summary).
Prime contractor lien deadline
File the notice of lien with the county clerk during the work or within 8 months after the last work or materials (4 months for a single-family dwelling). Serve a copy on the owner from 5 days before to 30 days after filing, and file proof of service within 35 days of filing or the lien terminates.8 months after last furnishing
Subcontractor and supplier lien deadline
Same deadline as contractors: 8 months after the claimant's last work or materials (4 months for a single-family dwelling), with the same owner service and 35-day proof-of-service rule.8 months after last furnishing
Enforcement deadline
The lien lapses 1 year after filing unless a foreclosure action is started and a notice of pendency filed. It can be extended by filing an extension with the county clerk (up to 1 year each); liens on single-family dwellings can only be extended by court order.1 year after the lien is recorded
Public projects
Public improvement liens attach to contract funds: file a notice of lien with the head of the department and the comptroller/financial officer before, or within 30 days after, completion and acceptance; the lien lasts 1 year unless foreclosure is started or it is extended (Lien Law §§12, 18). On state contracts a payment bond is required (may be waived under $100,000); claimants with no direct contract with the prime must give written notice to the prime within 120 days of last furnishing, and suit must be filed within 1 year after the improvement is completed and accepted (State Finance Law §137). Lien Law §§12, 18; State Finance Law §137 (official source, opens in a new tab)
Notes
Single-family dwelling: 4-month filing window and court-order-only extensions (developer-owned subdivision units are excluded from the single-family rule). Retainage liens may be filed within 90 days after the retainage was due to be released.

Sources read: Lien Law §10, Lien Law §11, Lien Law §12, Lien Law §17, Lien Law §18, State Finance Law §137

North Carolina mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
On projects that need a lien agent (improvements costing $40,000 or more, except work on an existing owner-occupied single-family home), every potential lien claimant sends a Notice to Lien Agent within 15 days after first furnishing. A later notice still works if sent before the property is sold to a bona fide purchaser, but the lien may then rank behind mortgages recorded first.15 days after first furnishing
Prime contractor lien deadline
File the claim of lien on real property with the clerk of superior court within 120 days after the last furnishing of labor or materials at the site.120 days after last furnishing
Subcontractor and supplier lien deadline
Subcontractors file a claim of lien on real property (through the contractor above them) within 120 days after their own last furnishing. They can also serve a notice of claim of lien upon funds on the owner or other obligor at any time, which makes the obligor hold back unpaid funds. Second- and third-tier claimants can lose lien rights if the owner posts a notice of contract and they do not serve a notice of subcontract.120 days after last furnishing
Enforcement deadline
Sue to enforce the lien in the county where the property is located no later than 180 days after the last furnishing of labor or materials.180 days after last furnishing
Public projects
Claimants use the payment bond, which equals 100% of the contract and is required for each contract over $50,000 when the project's contracts total more than $300,000 ($500,000 for State agencies and UNC). A claimant with no contract with the prime gives the prime written notice within 120 days after last furnishing. Suit no earlier than 90 days after last furnishing, and within 1 year after last furnishing or final settlement with the contractor, whichever is later. G.S. 44A-25 to 44A-35 (official source, opens in a new tab)
Notes
No lien agent is required for improvements to an existing single-family home the owner occupies. A Notice to Lien Agent lasts 5 years and can be renewed once. A notice of claim of lien upon funds is served on the obligor, not recorded.

Sources read: G.S. ch. 44A, art. 2 (44A-7 to 44A-24), G.S. 44A-11.2, G.S. ch. 44A, art. 3 (44A-25 to 44A-35)

North Dakota mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No notice at the start of work. Before recording, the claimant must send the legal or equitable owner written notice by certified mail that a lien will be claimed, at least 10 days before recording.
Prime contractor lien deadline
Record the lien with the county recorder within 90 days after all of the claimant's contribution is done, after the 10-day pre-recording notice to the owner.90 days after last furnishing
Subcontractor and supplier lien deadline
Same 90 days after the claimant's last contribution. A late lien still binds the owner, except for amounts already paid to the contractor before recording, but not good-faith purchasers or lenders; no lien may be filed more than 3 years after first furnishing.90 days after last furnishing
Enforcement deadline
Start a suit and record a lis pendens within 3 years after recording the lien, or within 30 days after an owner's written demand. Give the owner notice of intent to enforce at least 10 days (personal service) or 20 days (registered mail) before suing.3 years after the lien is recorded
Public projects
No liens on public property; public improvements over $250,000 require a payment bond equal to the contract price. Claimants not paid within 90 days of completing their work may sue on the bond; those without a contract with the prime must give the contractor written notice by registered mail within 90 days after completing their contribution. NDCC §§48-01.2-10, 48-01.2-11 (official source, opens in a new tab)
Notes
The 10-day pre-recording notice sits in §35-27-02(4), the subsection on persons contracting through a contractor or sub; sending it is prudent for every claimant. A statutory deadline to sue on the public bond was not found in ch. 48-01.2.

Sources read: NDCC ch. 35-27 (§§35-27-02, -13, -14, -24, -25), NDCC ch. 48-01.2 (§§48-01.2-10, -11)

Ohio mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
If a notice of commencement was recorded, subs and suppliers not in direct contract with the owner serve a notice of furnishing on the owner's designee and the GC within 21 days of first furnishing. Late notice preserves only work from 21 days before service onward. Not required of GCs, laborers, or on home construction contracts.21 days after first furnishing
Prime contractor lien deadline
Record the lien affidavit with the county recorder within 75 days after your last labor or materials (60 days for a 1-2 family dwelling or residential condo unit). Serve a copy on the owner within 30 days after filing.75 days after last furnishing
Subcontractor and supplier lien deadline
Same as contractors: 75 days after the claimant's last labor or materials (60 days residential), copy to the owner within 30 days of filing; a notice of furnishing is needed first if a notice of commencement was recorded.75 days after last furnishing
Enforcement deadline
The lien stays in force 6 years after the affidavit is filed (longer if suit is pending). If the owner or another interested party serves a notice to commence suit, suit must be filed within 60 days or the lien is void.6 years after the lien is recorded
Public projects
No lien on public property; subs and suppliers can serve a lien affidavit on the public authority within 120 days of last furnishing to reach contract funds (R.C. 1311.26). On the contract bond, claimants send the surety a statement of amount due no later than 90 days after completion and acceptance, wait 60 days, and sue within 1 year of acceptance; subs/suppliers not in privity with the prime whose work costs more than $30,000 must also serve a notice of furnishing (recovery limited to work from 21 days before service onward). R.C. 153.54-153.57, 1311.26 (official source, opens in a new tab)
Notes
60-day lien deadline for 1-2 family dwellings and residential condo units; 120 days for oil and gas well liens (R.C. 1311.021). No dollar threshold for the public bond is stated in 153.54; the bond is filed with the bid on state and political-subdivision public improvements (ODOT excluded).

Sources read: R.C. 1311.05, R.C. 1311.06, R.C. 1311.07, R.C. 1311.11, R.C. 1311.13, R.C. 1311.26, R.C. 153.54, R.C. 153.56, R.C. 153.57

Oklahoma mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Claimants other than the original contractor send a pre-lien notice to the original contractor and an owner no later than 75 days after their last supply, and before filing the lien. Not required for claims under $10,000 aggregate or on non-owner-occupied residential projects of 4 or fewer units; it is required on owner-occupied dwellings.
Prime contractor lien deadline
The original contractor files a verified lien statement with the county clerk within 4 months after the date materials or equipment were last furnished or labor was last performed.4 months after last furnishing
Subcontractor and supplier lien deadline
Subs and suppliers file within 90 days after last furnishing or last labor under the subcontract, with an affidavit of pre-lien notice compliance. The clerk mails notice of the lien to the owner within 5 business days after filing.90 days after last furnishing
Enforcement deadline
Suit to enforce must be brought within 1 year after the lien is filed with the county clerk.1 year after the lien is recorded
Public projects
No liens on public property; public construction contracts over $100,000 require a payment bond for the full contract price. Claimants without a contract with the prime give written notice to the contractor and surety within 90 days after last furnishing; suit on the bond within 1 year after last furnishing. 61 O.S. §§1, 2 (official source, opens in a new tab)
Notes
Pre-lien notice runs from last supply (not first), so no first-furnishing clock; unnoticed portions of the claim are unenforceable. §142.6 last amended by Laws 2025, c. 486 (eff. 1/1/2026). Bond suit window extends to 2 years if a claim was filed within the first year.

Sources read: 42 O.S. §142, 42 O.S. §142.6, 42 O.S. §143, 42 O.S. §143.1, 42 O.S. §172, 61 O.S. §1, 61 O.S. §2

Oregon mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Claimants not hired by the owner deliver a notice of right to lien to the owner (in person or by registered or certified mail); it only protects work furnished from 8 business days before delivery, so send it within 8 business days of first furnishing. Not needed for labor on commercial improvements. On residential contracts over $2,000 the original contractor must give the owner the statutory Information Notice to Owner.
Prime contractor lien deadline
File the claim of lien with the county recording officer no later than 75 days after the claimant stopped furnishing labor, equipment or materials, or 75 days after completion of construction, whichever is earlier. Mail notice of the filing to the owner and mortgagee within 20 days.75 days after last furnishing
Subcontractor and supplier lien deadline
Same 75-day rule (earlier of last furnishing or completion of construction), limited to work covered by a timely notice of right to lien.75 days after last furnishing
Enforcement deadline
Suit to foreclose must be filed within 120 days after the claim of lien is filed (longer only if extended credit terms are stated in the claim, never past 2 years). Give the owner and mortgagee written notice of intent to foreclose at least 10 days before suing.120 days after the lien is recorded
Public projects
No liens on public improvements; contracts estimated over $100,000 ($50,000 for transportation work) need a payment bond for the full contract price. Claimants give written notice of claim to the contractor and the contracting agency within 180 days after last furnishing; suit within 2 years after last furnishing. ORS 279C.380, 279C.600-279C.610 (official source, opens in a new tab)
Notes
Read in the 2025 ORS edition. The legislature flags 2026-session amendments to some ch. 279C sections; check them before relying on the public-work figures. Missing the 20-day filing notice or 10-day foreclosure notice costs fee recovery, not the lien.

Sources read: ORS ch. 87 (87.021, 87.035, 87.039, 87.055, 87.057, 87.093), 2025 ed., ORS ch. 279C (279C.380, 279C.600, 279C.605, 279C.610), 2025 ed.

Pennsylvania mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
On searchable projects ($1.5M or more) where the owner filed a Notice of Commencement in the State Construction Notices Directory, subcontractors must file a Notice of Furnishing in the directory within 45 days of first furnishing or lose lien rights. Separately, every subcontractor must give the owner a formal notice of intent at least 30 days before filing a lien.45 days after first furnishing
Prime contractor lien deadline
File the claim with the prothonotary within 6 months after completing your work (last labor or materials), and serve notice of filing on the owner within 1 month after filing; file the affidavit of service within 20 days after service.6 months after last furnishing
Subcontractor and supplier lien deadline
Same 6-month filing and 1-month service rules, plus a formal notice of intent to the owner at least 30 days before filing. Only subs contracting with the GC or with a first-tier sub can lien.6 months after last furnishing
Enforcement deadline
An action to obtain judgment must be commenced within 2 years from filing the claim (unless the owner extends in writing), and a verdict or judgment must be obtained within 5 years of filing.2 years after the lien is recorded
Public projects
No lien for work done for a purely public purpose. Prime contractors post a 100% payment bond on public contracts over $5,000. Claimants with no contract with the prime must give written notice to the prime within 90 days of last furnishing. Suit may be brought once 90 days pass after last furnishing unpaid, and must be filed within 1 year (42 Pa.C.S. §5523(3)). Public Works Contractors' Bond Law of 1967, 8 P.S. §191 et seq.; 42 Pa.C.S. §5523 (official source, opens in a new tab)
Notes
Claims must exceed $500. Subcontractors have no lien on an owner-occupied 1-2 unit home or single townhouse if the owner paid the contractor in full (§301(b), 2014 amendment). §§501-502 amended by Act 52 of 2006; directory notices added by Act 142 of 2014 (apply to projects started after the directory became operational). Bond law allows alternate financial security on contracts over $10,000.

Sources read: Mechanics' Lien Law of 1963 (Act 497), §§201, 301, 303, 501-501.4, 502, 701, Public Works Contractors' Bond Law of 1967 (Act 385), §§3, 3.1, 4, 42 Pa.C.S. §5523

Rhode Island mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
A contractor in direct contract with the owner (not a material supplier) must give a Notice of Possible Mechanic's Lien before starting work or delivering materials, either conspicuously in the written contract or by certified mail; without it that contractor has no lien. Subs and suppliers have no preliminary notice requirement.
Prime contractor lien deadline
Mail a notice of intention to claim a lien to the owner of record by registered or certified mail and record a copy in the land evidence records of the city or town, before or within 200 days after the work or materials were furnished.200 days after last furnishing
Subcontractor and supplier lien deadline
Same as the general contractor: mail the notice of intention to the owner and record it within 200 days after the work or materials were furnished. If the mailed notice comes back undelivered, it can be filed with the returned envelope within 30 days of its return (no later than 200 days after mailing).200 days after last furnishing
Enforcement deadline
File the complaint to enforce and a notice of lis pendens within 40 days after recording the notice of intention (the complaint on the same day as the lis pendens or within 7 days after).40 days after the lien is recorded
Public projects
No mechanics' liens on improvements built for, or land owned by, the state or a city or town. State contracts over $150,000 need a payment bond. Claimants without a direct contract with the prime must give the prime written notice by certified mail within 90 days of last furnishing; suit within 2 years of last furnishing (or the bond's longer limit). R.I. Gen. Laws §§ 34-28-31, 37-12-1, 37-12-2, 37-12-5 (official source, opens in a new tab)
Notes
The 200-day window runs from the doing of the work or furnishing of materials; the enforcement window is short (40 days from recording). Architects and engineers follow § 34-28-7 (not reviewed).

Sources read: R.I. Gen. Laws ch. 34-28 index, R.I. Gen. Laws § 34-28-4, R.I. Gen. Laws § 34-28-4.1, R.I. Gen. Laws § 34-28-10, R.I. Gen. Laws § 34-28-30, R.I. Gen. Laws § 34-28-31, R.I. Gen. Laws § 37-12-1, R.I. Gen. Laws § 37-12-2, R.I. Gen. Laws § 37-12-5

South Carolina mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No general preliminary notice. If a Notice of Project Commencement is filed, a sub-subcontractor or supplier who does not send the contractor a notice of furnishing by certified or registered mail has its lien capped at what the contractor owes the subcontractor. Claimants hired by someone other than the owner must notify the owner in writing of what they furnished for the lien to attach against the owner.
Prime contractor lien deadline
Serve the owner and file a sworn statement of account with the register of deeds or clerk of court within 90 days after you last furnish labor or materials.90 days after last furnishing
Subcontractor and supplier lien deadline
Same 90-day rule for subcontractors and suppliers: serve the owner and file the sworn statement within 90 days after last furnishing. Total liens cannot exceed what the owner still owes on the contract.90 days after last furnishing
Enforcement deadline
Start a suit to enforce the lien and file a notice of pendency of action within 6 months after you stop furnishing labor or materials.6 months after last furnishing
Public projects
State construction contracts require a 100% payment bond (may be waived at $50,000 or less). Claimants without a direct contract with the prime must give the prime written notice within 90 days of last furnishing; suit on the bond within 1 year of last furnishing. S.C. Code § 11-35-3030; § 29-5-440 (official source, opens in a new tab)
Notes
Notice of Project Commencement (§ 29-5-23) is filed by the owner's contractor within 15 days of starting work; if none is filed, the notice-of-furnishing lien cap does not apply. Enforcement is measured from the claimant's own last furnishing.

Sources read: S.C. Code §§ 29-5-20, 29-5-23, 29-5-40, 29-5-90, 29-5-120, 29-5-440, S.C. Code § 11-35-3030

South Dakota mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Only when a Notice of Project Commencement has been filed: sub-subcontractors and suppliers to subcontractors must send a notice of furnishing by certified or registered mail to the contractor named in that notice, with a copy to the owner, no later than 60 days after their last work. Individual laborers with liens under $2,000 are exempt.
Prime contractor lien deadline
File a verified lien statement with the county register of deeds within 120 days after the last work or furnishing. A copy must first be mailed to the owner by registered or certified mail, with the receipt attached to the statement.120 days after last furnishing
Subcontractor and supplier lien deadline
Same 120-day filing deadline for subcontractors and suppliers. Where a Notice of Project Commencement was filed, lower-tier claimants must also have sent the 60-day notice of furnishing.120 days after last furnishing
Enforcement deadline
Assert the lien by complaint or answer within 6 years of the last item in the lien statement. If the owner, owner's agent or contractor serves a written demand, suit must be started within 30 days of service or the lien is forfeited.6 years after last furnishing
Public projects
Public contractors must give a surety bond for prompt payment of laborers and suppliers (waivable on small contracts under the § 5-18A-14 limit). Unpaid claimants may sue on the bond if the public body hasn't within 6 months of completion and final settlement; suit no earlier than 6 months after completion and within 1 year after that. SDCL ch. 5-21 (official source, opens in a new tab)
Notes
Notice of Project Commencement is filed by the owner or prime within 30 days of starting work (§ 44-9-50). Residential-specific rules were not reviewed. The 6-year enforcement clock runs from the last item on the lien statement, which is usually the last furnishing date.

Sources read: SDCL ch. 44-9 (index), SDCL § 44-9-15, SDCL § 44-9-17, SDCL § 44-9-24, SDCL § 44-9-26, SDCL § 44-9-50, SDCL § 44-9-53, SDCL ch. 5-21 (index), SDCL § 5-21-1.1, SDCL § 5-21-6

Tennessee mechanics lien deadlines

Not verified
Preliminary notice Verify
Not verified here: verify with counsel
Prime contractor lien deadline
Not verified here: verify with counsel
Subcontractor and supplier lien deadline
Not verified here: verify with counsel
Enforcement deadline
Not verified here: verify with counsel
Public projects
Not verified here: verify with counsel
Notes
Not verified. Tennessee publishes its code only through the LexisNexis public-access site, which is a JavaScript app that would not load for automated reading, and no other official copy of §§ 66-11-112, 66-11-115 or 66-11-145 could be reached. Check the statute with counsel.

Sources read: none

Texas mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Subs and suppliers (anyone other than the original contractor) send a notice of claim for unpaid labor or materials to the owner and the original contractor by the 15th day of the 3rd month after each month work was done (2nd month for residential). The calculator date covers only the final month of work. Unpaid retainage not already noticed needs its own notice within 30 days after the claimant's contract ends, or after the original contract is terminated or abandoned if that comes first.15th day of the 3rd month after the month of last furnishing
Prime contractor lien deadline
The original contractor files the lien affidavit by the 15th day of the 4th month after the month its work was completed, terminated or abandoned (3rd month for residential). A copy goes to the owner within 5 days after filing.15th day of the 4th month after the month of completion
Subcontractor and supplier lien deadline
Subs and suppliers file the lien affidavit by the 15th day of the 4th month after the month they last provided labor or materials (3rd month for residential). Retainage claims are due by the 15th day of the 3rd month after the original contract is completed, terminated or abandoned. A copy goes to the owner and original contractor within 5 days after filing.15th day of the 4th month after the month of last furnishing
Enforcement deadline
Suit to foreclose must be filed within 1 year after the last day the claimant could have filed the lien affidavit. A recorded written agreement with the owner can extend this to 2 years after the affidavit was filed.1 year after the last day to record the lien
Public projects
No liens on public property; claimants use the payment bond. Payment bond required on contracts over $25,000 ($50,000 for municipalities); performance bond over $100,000. Claimants mail a notice of claim with a sworn statement of account to the prime and the surety by the 15th day of the 3rd month after each month of work. Claimants without a direct contract with the prime must also notify the prime by the 15th day of the 2nd month. Suit may be filed if the claim is still unpaid 60 days after notice, and no later than 1 year after the notice was mailed. Gov't Code ch. 2253 (official source, opens in a new tab)
Notes
Reflects HB 2237 (Acts 2021, ch. 690), effective January 1, 2022: one notice deadline for all tiers, statutory notice forms, and a 1-year foreclosure deadline. Residential projects use shorter deadlines (2nd month for the notice, 3rd month for the affidavit).

Sources read: Prop. Code ch. 53 (§§53.052, 53.055, 53.056, 53.057, 53.158), Gov't Code ch. 2253 (§§2253.021, 2253.041, 2253.047, 2253.048, 2253.073, 2253.078)

Utah mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Everyone who wants lien rights, including the prime contractor, must file a preliminary notice with the State Construction Registry within 20 days after first providing work. A late notice only covers work provided from 5 days after it is filed, and has no effect if filed more than 10 days after a notice of completion.20 days after first furnishing
Prime contractor lien deadline
Record a notice of construction lien with the county recorder within 180 days after final completion of the original contract, or within 90 days after a notice of completion is filed (never later than 180 days after final completion). Mail a copy to the owner by certified mail within 30 days after filing.180 days after completion
Subcontractor and supplier lien deadline
Same deadline as the prime: 180 days after final completion of the original contract, or 90 days after a notice of completion. A subcontractor doing substantial work after the certificate of occupancy or final inspection has until 180 days after finishing its own work.180 days after completion
Enforcement deadline
File an action to enforce and record a notice of pendency of action within 180 days after recording the notice of construction lien, or the lien is void (extended to 90 days after the stay lifts if the owner files bankruptcy).180 days after the lien is recorded
Public projects
Public construction contracts awarded under the Procurement Code require a 100% payment bond (waivable by rule; since a 2026 amendment, contracts administered by the state facilities division (DFCM) need a bond only when the division requires one). Claimants unpaid 90 days after last furnishing may sue on the bond within 1 year after last furnishing. Utah Code § 63G-6a-1103 (official source, opens in a new tab)
Notes
Deadlines run from final completion of the whole original contract, not the claimant's last work. Owner-occupied residences have extra protections under the Residence Lien Restriction and Lien Recovery Fund Act (Title 38, ch. 11), and enforcement complaints on a residence must include required owner instructions and forms.

Sources read: Utah Code § 38-1a-501, Utah Code § 38-1a-502, Utah Code § 38-1a-701, Utah Code § 63G-6a-1103

Vermont mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No preliminary notice for contractors hired by the owner. Subcontractors and suppliers get a lien only by giving the owner (or owner's agent) written notice, stating the payment due date if known; the lien covers only the contract price still unpaid when the owner receives it, so send it early.
Prime contractor lien deadline
File a signed lien memorandum with the town clerk where the property is located within 180 days after payment became due for the last labor or materials.
Subcontractor and supplier lien deadline
Same 180-day filing deadline (from when payment became due for the last labor or materials), after the written notice to the owner. Recovery is limited to what the owner still owed on the contract when notice was received.
Enforcement deadline
Start suit and attach the property within 180 days after filing the lien memorandum, or within 180 days after payment becomes due if it was not yet due when you filed.180 days after the lien is recorded
Public projects
For state transportation contracts, the contractor files a payment bond with the Secretary of Transportation (waivable at $250,000 or less). Claimants file a sworn statement within 90 days after the state's final acceptance of the project and petition Superior Court within 1 year after filing. No general statewide public-works bond statute was confirmed. 19 V.S.A. § 10(9) (official source, opens in a new tab)
Notes
Vermont's lien clocks run from when payment became due, not from last furnishing, so no calculator clock is given for the lien filing. Liens cannot be waived in advance of the work. The legislature's site labels its text an unofficial convenience copy.

Sources read: 9 V.S.A. ch. 51 (§§ 1921, 1923, 1924), 19 V.S.A. § 10

Virginia mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
No preliminary notice on commercial projects. On one- or two-family homes where the building permit names a mechanics' lien agent, claimants must notify that agent within 30 days of first furnishing (or of permit issuance). If they're late, the lien covers only work done after the notice.
Prime contractor lien deadline
Record a memorandum of lien no later than 90 days after the last day of the month of last work or materials, and no later than 90 days after the structure is completed. The memorandum can't cover work more than 150 days before the last furnishing, except retainage up to 10% of the contract.
Subcontractor and supplier lien deadline
Subs, sub-subs and suppliers follow the same 90-day recording rule. They must also give written notice of the amount and character of the claim to the owner, and second-tier claimants to the GC as well. A sub's lien is capped at what the owner owes the GC.
Enforcement deadline
File suit within 6 months after recording the memorandum, or within 60 days after the structure is completed or work otherwise ends, whichever is later.6 months after the lien is recorded
Public projects
Claimants on public projects use the payment bond. Claimants without a direct contract with the prime must send notice to the prime by registered or certified mail within 90 days after their last furnishing. Suit is due within 1 year after the claimant's last labor or materials. Bonds are required on non-transportation contracts over $500,000 and Commonwealth-funded transportation contracts over $350,000. Va. Code 2.2-4337, 2.2-4341 (official source, opens in a new tab)
Notes
The recording deadline runs from the end of the month of last furnishing, which the calculator can't express, so there's no lien clock. A GC must also file a certification that a copy was mailed to the owner. The sub notice under 43-7 and 43-9 has no separate statutory deadline.

Sources read: Va. Code 43-4, Va. Code 43-4.01, Va. Code 43-7, Va. Code 43-9, Va. Code 43-17, Va. Code 2.2-4337, Va. Code 2.2-4341

Washington mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Sometimes
Suppliers and others who furnish professional services, materials or equipment without a direct contract with the owner or the prime send the owner a notice of right to claim a lien (and the prime, in some cases). It can be sent any time but only protects items supplied within 60 days before it was sent (10 days for a new single-family home). Laborers, first-tier subcontractors and anyone contracting directly with the owner are exempt.
Prime contractor lien deadline
Record the claim of lien within 90 days after you stop furnishing labor, professional services, materials or equipment. Give the owner a copy within 14 days of recording, or lose any claim to attorneys' fees and costs against the owner.90 days after last furnishing
Subcontractor and supplier lien deadline
Same deadline for subcontractors and suppliers: record within 90 days after their last furnishing, and copy the owner within 14 days of recording.90 days after last furnishing
Enforcement deadline
File suit in superior court in the property's county within 8 calendar months after the lien is recorded, and serve the owner within 90 days after filing.8 months after the lien is recorded
Public projects
Claimants use the contractor's bond, which equals the full contract price for state work (cities and towns can set as little as 25%). File a written claim notice with the public body within 30 days after completion and acceptance of the work. Suppliers to a subcontractor must notify the prime within 10 days of first delivery. On contracts of $150,000 or less the agency can hold 10% retainage instead of a bond. RCW 39.08 (official source, opens in a new tab)
Notes
Remodels of an existing owner-occupied single-family home: claimants without a direct contract with the owner must notify the owner, and their lien is limited to what the owner has not yet paid the prime when the notice arrives. RCW 39.08.030 was last amended in 2025 (c 103) and sets no suit deadline. The prelim has no fixed deadline, so no clock is given (send within 60 days of first furnishing to cover everything).

Sources read: RCW 60.04.031, RCW 60.04.091, RCW 60.04.141, RCW 39.08.010, RCW 39.08.030, RCW 39.08.065

West Virginia mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No required preliminary notice. Anyone working for the owner's contractor may optionally notify the owner, before starting work, that they will look to the owner if unpaid.
Prime contractor lien deadline
Record a sworn notice of lien with the county clerk where the property is located within 100 days after completing the work under your contract with the owner.100 days after completion
Subcontractor and supplier lien deadline
Subcontractors, and suppliers to a contractor or subcontractor, must record the notice of lien with the county clerk and serve it on the owner (as a legal notice or summons is served) within 100 days after completing the subcontract or ceasing to furnish materials.100 days after last furnishing
Enforcement deadline
Start a circuit court action to enforce the lien within 6 months after recording the notice of lien, or the lien is discharged.6 months after the lien is recorded
Public projects
No lien on public buildings or the land under them. The public body must require a recorded payment bond covering the reasonable cost of labor and materials, and unpaid suppliers and laborers recover from the bond. The statute sets no bond claim notice or suit deadline. W. Va. Code § 38-2-39 (official source, opens in a new tab)
Notes
The prime contractor's 100 days run from completion of its own contract. Suppliers contracting directly with the owner record within 100 days after they stop furnishing (§ 38-2-10). If the owner demands an account in writing, it must be filed within 60 days (§§ 38-2-19, 38-2-20).

Sources read: W. Va. Code art. 38-2 (index), W. Va. Code § 38-2-7, W. Va. Code § 38-2-8, W. Va. Code § 38-2-9, W. Va. Code § 38-2-10, W. Va. Code § 38-2-11, W. Va. Code § 38-2-20, W. Va. Code § 38-2-34, W. Va. Code § 38-2-39

Wisconsin mechanics lien deadlines

Verified November 18, 2026
Preliminary notice No
No preliminary notice on nonresidential projects or residential projects adding more than 4 living units. Everyone must still serve the owner a 30-day notice of intent to file a lien before filing (see lien deadlines).
Prime contractor lien deadline
Serve the owner a written notice of intent to file a lien at least 30 days before filing, then file the claim for lien with the clerk of circuit court within 6 months after your last labor or materials. Serve a copy of the filed claim on the owner within 30 days after filing.6 months after last furnishing
Subcontractor and supplier lien deadline
Same as the prime: 30-day notice of intent to the owner, then file the claim for lien within 6 months after your last labor or materials and serve a copy on the owner within 30 days after filing.6 months after last furnishing
Enforcement deadline
Bring an action, with summons and complaint filed, within 2 years after filing the claim for lien.2 years after the lien is recorded
Public projects
Payment and performance bonds are required on state contracts over $369,000 and local contracts over $148,000 (over $74,000 locally, a bond or substitute payment assurance). Subs and suppliers must serve the prime written notice within 60 days of first furnishing (not needed for contracts of $5,000 or less or for subs listed in the prime's contract) and sue on the bond within 1 year after completion of the work. Claimants can also claim against public funds owed to the prime before the prime is paid (§ 779.15). Wis. Stat. §§ 779.14, 779.15 (official source, opens in a new tab)
Notes
On residential projects of 4 or fewer units, the prime must put a lien notice in its written contract with the owner (or serve it within 10 days of first work), and subs and suppliers must serve the owner notice within 60 days of first furnishing or they lose lien rights (§ 779.02(2)).

Sources read: Wis. Stat. § 779.02, Wis. Stat. § 779.06, Wis. Stat. § 779.14, Wis. Stat. § 779.15

Wyoming mechanics lien deadlines

Verified November 18, 2026
Preliminary notice Yes
Everyone must send the record owner a written notice of lien rights (form in W.S. 29-10-101): the prime contractor before receiving any payment, including advances, and subs and suppliers within 30 days after first furnishing, with a copy to the contractor they work for. Missing it bars the lien.30 days after first furnishing
Prime contractor lien deadline
Send the owner a notice of intent to lien at least 20 days before filing, then file the lien statement within 150 days after the earlier of your last work or materials or substantial completion of the project. An owner's recorded notice of substantial completion is presumed to set that date.150 days after last furnishing
Subcontractor and supplier lien deadline
Subcontractors and suppliers file within 120 days after the earlier of their last work or materials or substantial completion of the project (for a subcontractor, after the last day it worked at the contractor's direction), after a 20-day notice of intent to the owner.120 days after last furnishing
Enforcement deadline
Start an action to foreclose within 180 days after filing the lien statement, or the lien ends.180 days after the lien is recorded
Public projects
Public works contracts over $150,000 require a 100% payment and performance bond (smaller contracts may use another guarantee). Claimants sue on the bond, notifying the obligee, within 1 year after the public entity's date of final completion. No pre-suit notice deadline is set in the statute. W.S. 16-6-112 to 16-6-117 (official source, opens in a new tab)
Notes
Filing deadlines run from the earlier of last furnishing or substantial completion, so the last-furnishing estimate can be too late if the project finished first. The parties can sign and record an agreement extending the filing time (up to double).

Sources read: W.S. Title 29 (§§ 29-2-106, -107, -109, -112, -113), W.S. Title 16 (§§ 16-6-112 to 16-6-117)

Terms used on this page

Related: Getting paid in construction · Construction bonds explained · Retainage calculator and state retainage rules · Retainage, lien waivers and pay apps on one record

When the spreadsheet stops scaling

Keep waivers, holds and payments on one record

  • Lien waiver holds. Accounts Payable can hold a bill until the lien waiver it needs is on file, and record conditional or unconditional, progress or final waivers, including from lower tiers.
  • Joint checks and stop pays. Pay a sub and its supplier together, or stop pay on a vendor, with approval rights and a reason on record.
  • What it does not do. os.construction does not calculate or file statutory lien notices or deadlines for you. Use this page, the statute and your counsel for that.

See how AP handles lien waivers Start a free trial

FAQ

Mechanics lien deadline questions

What is the deadline to file a mechanics lien?

It depends on the state and on your role. Lien recording deadlines run from about 60 days to 6 months after the claimant's last furnishing or completion of the project, and several states give prime contractors longer than subcontractors and suppliers. Use the table for your state, then read the statute linked in that row.

What is the mechanics lien deadline in Texas?

For private commercial work in Texas. Prime contractors: The original contractor files the lien affidavit by the 15th day of the 4th month after the month its work was completed, terminated or abandoned (3rd month for residential). A copy goes to the owner within 5 days after filing. Subcontractors and suppliers: Subs and suppliers file the lien affidavit by the 15th day of the 4th month after the month they last provided labor or materials (3rd month for residential). Retainage claims are due by the 15th day of the 3rd month after the original contract is completed, terminated or abandoned. A copy goes to the owner and original contractor within 5 days after filing. Enforcement: Suit to foreclose must be filed within 1 year after the last day the claimant could have filed the lien affidavit. A recorded written agreement with the owner can extend this to 2 years after the affidavit was filed. See Prop. Code ch. 53 and read the statute before relying on a date (last verified November 18, 2026).

What is the mechanics lien deadline in California?

For private commercial work in California. Prime contractors: A direct contractor records the claim of lien after finishing its contract and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 60 days after that recording, whichever comes first. Subcontractors and suppliers: Subs and suppliers record after they stop providing work and within 90 days after completion of the project. If the owner records a notice of completion or cessation, the deadline is 30 days after that recording, whichever comes first. Enforcement: Suit to foreclose must be filed within 90 days after the lien is recorded, or the lien expires. A recorded credit extension can push this out, but never past 1 year after completion. See Civ. Code §§8000-9566 (private works liens: §§8400-8494) and read the statute before relying on a date (last verified November 18, 2026).

What is the mechanics lien deadline in Florida?

For private commercial work in Florida. Prime contractors: Record the claim of lien within 90 days after the lienor's final furnishing of labor, services or materials. If the contract is terminated, the deadline is 90 days after termination or 90 days after final furnishing, whichever is first. Subcontractors and suppliers: Same as contractors: record within 90 days after the claimant's final furnishing. A timely Notice to Owner is a prerequisite. Enforcement: Suit to enforce must be filed within 1 year after the claim of lien is recorded, or after an amended claim showing a later final-furnishing date. An owner's notice of contest cuts this to 60 days after service. See Fla. Stat. ch. 713, part I and read the statute before relying on a date (last verified November 18, 2026).

Which states require a preliminary notice?

In this table, 8 jurisdictions require some form of preliminary notice from at least some claimants to keep lien rights, 30 require one only in some situations (for example only for lower tiers, residential work, or when the owner records a notice of commencement), and 11 have no general preliminary notice requirement. The names differ: notice to owner, 20-day notice, notice of furnishing, notice of intent. Filter the table by "Preliminary notice" to see each list.

Does the deadline move if it falls on a weekend or holiday?

Sometimes. Many states have a general rule that moves a deadline that falls on a weekend or legal holiday to the next business day, but whether it applies to lien recording, and how the county recorder treats it, varies. Do not plan around an extension: record before the computed date, and count from the earliest date a court could treat as your last furnishing.

Does warranty or punch list work extend the lien deadline?

Often not. Many courts treat warranty, corrective or trivial remedial work as not extending the last furnishing date, while substantial work under the original contract may. The rules are state-specific and fact-specific, so date the deadline from the last substantial work and get advice before relying on later work.

Can you file a mechanics lien on a public project?

Generally no. Public property cannot be liened in most states, so subcontractors and suppliers on public work rely on the payment bond the prime contractor must post under the state's "Little Miller Act" (or the federal Miller Act on federal projects). Bond claims have their own notice and suit deadlines, shown in the Public projects column. A few states also allow a stop notice or a claim against funds held by the public owner.

What is the difference between the lien deadline and the enforcement deadline?

Recording the lien preserves the claim. The enforcement deadline is the separate, later date by which you must file a lawsuit to foreclose it. Miss that date and the lien expires, even if it was recorded on time. Some states let the owner shorten the enforcement window by serving a demand or notice to commence suit.

How accurate is this table?

Each row was checked against the statute text on the official legislature or state government website linked in the row, on the date shown (on November 18, 2026). Summaries leave out exceptions. Where we could not confirm a field in official text, the cell says "verify with counsel" instead of guessing. This is general information, not legal advice.

Open file