Contracts

Notice of Nonpayment

Definition

A written notice an unpaid subcontractor or supplier sends to preserve a payment bond claim or warn the owner and GC that it hasn't been paid; deadlines are set by state law.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

Updated

The notice of nonpayment windowOn a Florida private project with a payment bond, a supplier serves an early notice to the contractor, makes its final delivery on March 10 and is owed $48.5k. The notice of nonpayment must be served on the contractor and the surety no later than 90 days after final furnishing, June 8. It serves on May 20, day 71, inside the window. A bond claim or suit must still follow within the statutory period. Illustrative; rules vary by state.Bonded project, FloridaillustrativeFirst deliveryearly notice to contractorFinal delivery · Mar 10owed $48.5k, unpaid90-day windowday 04590served May 20 · day 71deadline Jun 8served onContractor+ suretythen, if unpaidBond claim orsuit, on timeCount from the last day of furnishing,not the invoice date. Not legal advice.
Fla. Stat. § 713.23 sets the 90-day notice of nonpayment deadline for private payment bonds; other states use different notices and deadlines.

A notice of nonpayment is a written notice from an unpaid subcontractor or supplier telling the general contractor, surety or owner that it hasn’t been paid for labor or materials it furnished. In some states, such as Florida on payment-bonded projects, it is a required step with a strict deadline to preserve a bond claim. Elsewhere it’s a warning before a lien.

The term is used two ways. In its strict, statutory sense it is a specific notice a state requires before a claimant can recover from a payment bond. In everyday use, “notice of nonpayment” also describes any formal letter warning that a lien or bond claim is coming if payment isn’t made. This page is general information, not legal advice. Notice rules, names and deadlines vary by state and by public versus private work.

In plain English

Illustrative: you supplied $48,500 of rebar to a concrete sub on a bonded Florida job and haven’t been paid. The notice of nonpayment is the letter that tells the GC and its surety, “I furnished this, I’m owed this, and I’m keeping my right to claim on your bond.” Miss the 90-day window after your last delivery and you can lose the bond claim even though the debt is real.

What goes in a notice of nonpayment

Item Why it matters
Claimant’s name and address Identifies who is owed
Who hired you (sub or supplier above you) Shows your place in the payment chain
Project name and address, and the bond or permit number if known Ties the notice to the right bond
Labor, services or materials furnished Shows what the debt is for
Amount unpaid The figure the surety will check
Date of last furnishing Starts the statutory clock
Signature, date and proof of service Proves the notice was timely and properly served

Florida’s section 713.23 includes a statutory form for private bonded work. Use the current version from the official statute rather than an old template.

Where it’s a statutory requirement

  • Florida payment bonds. On a private project with a payment bond, a claimant not in direct contract with the contractor generally must serve a notice of nonpayment on the contractor and the surety no later than 90 days after its final furnishing of labor, services or materials (Fla. Stat. § 713.23). Florida’s public works bond statute (§ 255.05) has a similar notice. These are in addition to the earlier notice to contractor many claimants must send near the start of their work.
  • Texas. Lower-tier claimants on private projects must send notices of their unpaid claims on a monthly cycle, by deadlines measured from the month the work was performed (Texas Property Code Chapter 53). Texas changed the forms and deadlines effective 2022, so use the current statute rather than an old template.
  • Other states. Many states have some pre-claim notice for bond or lien rights, under names such as notice of intent to lien, notice of claim or stop payment notice. They are not interchangeable.

How it works

  1. Early notice. The claimant often must first send a preliminary notice (notice to owner, notice to contractor) when it starts work.
  2. Nonpayment. A pay app or invoice goes unpaid past its terms.
  3. Serve the notice. The claimant serves a written notice with the amount owed, the work furnished and the project, on the parties and by the delivery method the statute names.
  4. Respond. The GC and surety check the claim against the subcontract account and either pay, dispute or investigate.
  5. Claim or suit. If unresolved, the claimant files a bond claim or lien and, if needed, sues within the statutory limitation period.
Notice Purpose Typical timing
Preliminary notice / notice to owner Announces that a party is furnishing work, preserving rights Early, near first furnishing
Notice of nonpayment Says payment hasn’t been made; preserves a bond claim in some states After nonpayment, before a statutory deadline
Notice of intent to lien Warns that a lien will be recorded if unpaid Before recording a lien, where required
Stop payment notice Requires the owner, lender or agency to withhold funds After nonpayment, before a statutory deadline
Mechanics lien Encumbers the property Within the statutory recording period
Notice of completion Recorded by the owner; can shorten lien deadlines At completion

Worked example

Illustrative: on a bonded private project in Florida, a rebar supplier to the concrete sub makes its final delivery on March 10 and is owed $48,500. The supplier sent its notice to contractor when deliveries started. Counting 90 days from March 10 gives June 8, so the notice of nonpayment must be served on the GC and the surety no later than that day. It serves on May 20. The GC’s AP team checks the concrete sub’s account: the sub was paid through the April pay app, including $41,000 for rebar, but didn’t pay the supplier. The GC issues the next payment as a joint check to the sub and supplier and collects a conditional waiver from the supplier, and the surety closes its file.

Why it matters

For subs and suppliers, missing the deadline can forfeit a bond claim entirely, no matter how valid the debt. For GCs, a notice of nonpayment is an early warning that money paid to a sub isn’t reaching its suppliers, and that the GC may end up paying twice. For sureties, it starts a claim file against the contractor’s bond, which can affect bonding capacity.

Common mistakes

  • Counting the deadline from the invoice date instead of the last day of furnishing.
  • Serving the wrong parties, or by a delivery method the statute doesn’t allow.
  • Using an out-of-date form after a statute changes.
  • GCs paying the sub again without collecting lien waivers from its suppliers.
  • Assuming the notice alone gets you paid; the bond claim or suit deadline still applies.

For how this notice compares with the other two remedies, read notice of non-payment vs stop payment notice vs mechanics lien.

How os.construction handles it

os.construction does not prepare, serve or track statutory notices, and it doesn’t calculate notice deadlines. In the Accounting module, Accounts Payable can put a compliance hold on a vendor’s bills, including a stop pay or a missing lien waiver, and pay by joint check, with overrides requiring approval rights and a reason. Lien waiver tracking generated from payments and pay apps is planned. See Accounts payable and Lien waiver tracking.

FAQ

What is a notice of nonpayment in construction?

A notice of nonpayment is a written notice from an unpaid subcontractor, sub-subcontractor or supplier telling the contractor, surety or owner that it has not been paid for labor or materials it furnished. In some states it is a statutory step required to keep a payment bond claim alive; elsewhere it is an informal warning before a lien or bond claim.

What is the deadline for a notice of nonpayment?

It depends on the state and the type of project. In Florida, a claimant on a payment-bonded project who is not in direct contract with the GC generally must serve the notice of nonpayment no later than 90 days after its final furnishing of labor, services or materials. Other states set different deadlines, so check the statute for the project's state.

Who receives a notice of nonpayment?

Typically the general contractor and the surety that issued the payment bond, and sometimes the owner. Florida's private payment bond statute, for example, requires service on the contractor and the surety. Sending it to the wrong party or by the wrong delivery method can make it ineffective, so follow the statute's service rules.

Is a notice of nonpayment the same as a mechanics lien?

No. A mechanics lien is recorded against the property. A notice of nonpayment is a notice, usually tied to a payment bond claim on a bonded project, and it does not itself encumber title. On bonded or public projects where liens are not available, the notice may be one of the steps that preserves the claimant's right to recover from the bond.

What should a GC do after receiving a notice of nonpayment?

Check the claim against the sub's account: what was billed, paid and still owed, and whether the sub received money it did not pass down. Notify the surety if required, consider paying through a joint check in exchange for releases, and hold the sub's next payment until waivers are in. A fast response limits a surety claim.

What should a notice of nonpayment include?

At a minimum: the claimant's name and address, the party it contracted with, a description of the project, the labor, services or materials furnished, the amount still unpaid and the date it last furnished work. Florida's private payment bond statute, section 713.23, prints a form to follow. Sign it, keep proof of delivery, and serve it on the parties and by the method the statute requires.