A notice of non-payment is a written notice from an unpaid sub or supplier to the general contractor, the surety or the owner saying it hasn’t been paid; in some states it is a required step to keep a payment bond claim. A stop payment notice is served on the owner, construction lender or public agency and makes it hold back project funds to cover the claim. A mechanics lien is recorded against the property itself and can be foreclosed. One warns people, one freezes the money, one attaches to the real estate.
They get mixed up because they often show up on the same job, a few weeks apart, from the same unpaid party. This post walks through each one, with the actual statute sections for California, Florida and Texas, and what to do if you’re the GC on the receiving end.
The three side by side
| Notice of non-payment | Stop payment notice | Mechanics lien | |
|---|---|---|---|
| What it reaches | People: GC, surety, sometimes owner | Undisbursed construction funds | The property |
| Served on or recorded with | GC and surety, by the statute’s delivery method | Owner, construction lender or public agency | County recorder, against the land |
| Immediate effect | A warning, or a bond claim kept alive | Recipient withholds the claimed amount | Clouds title, can be foreclosed |
| Works on public jobs | Yes, often as the bond claim step | Yes, in states that provide it | Generally no |
| Main example | Florida § 713.23 | California § 8044 and §§ 8500–8560 | Every state, rules vary |
Notice of non-payment: two meanings
In its strict sense, a notice of nonpayment is a statutory step to preserve a payment bond claim. Florida is the clearest case. On a private project with a payment bond, a claimant who isn’t in direct contract with the contractor generally must serve a notice of nonpayment on the contractor and the surety no later than 90 days after its final furnishing of labor, services or materials (Fla. Stat. § 713.23). Miss it and the bond claim can be lost, no matter how good the underlying debt is.
Texas reaches a similar result through a monthly cycle. A sub or supplier that hasn’t been paid sends a notice of its unpaid claim to the owner and the original contractor no later than the 15th day of the third month after the month the work was done or the materials delivered, or the second month on residential jobs (Tex. Prop. Code § 53.056). Texas rewrote these notices and their forms for contracts entered on or after January 1, 2022, so an older template is a risk.
In everyday use, “notice of non-payment” also just means a formal letter: pay by this date or we file. That letter has no statutory effect unless your state gives it one, but it often gets the money moving.
Watch the direction outside the US. Under Ontario’s prompt payment rules, a “notice of non-payment” is sent by the payer, the owner or contractor disputing an invoice, not by the unpaid party. The UK’s “pay less notice” is the same idea. Same words, opposite sender. See holdback vs retainage for the Ontario version.
Stop payment notice: freeze the money
A stop payment notice (stop notice) goes to whoever is still holding the project’s money. California defines it in Civil Code § 8044 and sets the private-works rules in §§ 8500–8560:
- Preliminary notice first. Giving a valid preliminary notice is a prerequisite to a valid stop payment notice, as it is for a lien (§ 8200).
- Bonded notice to a lender. A claimant can give a construction lender a stop payment notice with a bond of 125 percent of the claim (§ 8532).
- Release bond. Anyone who wants the frozen money released can give the holder a release bond from an admitted surety, equal to 125 percent of the amount claimed, and the funds must then be released (§ 8510).
- Sue or lose it. The claimant may sue to enforce the notice any time after 10 days from giving it, and must sue no later than 90 days after the period for giving a stop payment notice expires. If it doesn’t, the notice stops being effective and the funds are released (§ 8550).
On California public works, where liens on public property aren’t available, the stop payment notice and the payment bond claim are the main remedies. They have their own sections starting at § 9350, with a notice deadline tied to the recording of a notice of completion or cessation.
Mechanics lien: attach the property
A mechanics lien is recorded with the county against the improved property. In California a subcontractor or supplier generally must record within 90 days after completion of the work of improvement, or within 30 days after the owner records a notice of completion; a direct contractor gets 60 days after a recorded notice of completion (§§ 8412, 8414). The claimant must then sue to enforce the lien within 90 days after recording it, or the lien expires (§ 8460).
A lien is the heaviest tool. It clouds the owner’s title, can block a refinance or sale, and usually triggers the owner’s demand that the GC clear it. That pressure is why many unpaid parties start with a notice and save the lien for when the deadline forces their hand.
How they stack: an illustrative example
A drywall supplier on a private California project with a construction loan is owed $62,000 by a drywall sub. The numbers are made up to show the sequence:
- Week 1 of its work: the supplier serves a 20-day preliminary notice on the owner, the GC and the lender. Without it, the later steps don’t work.
- Two invoices go unpaid. It sends the GC a demand letter, a notice of non-payment in the everyday sense. Here the letter is a warning, not a statutory step.
- No answer. It serves a bonded stop payment notice on the lender. The GC’s next draw of $1,450,000 funds at $1,388,000, with $62,000 withheld.
- The building is finished and the owner records a notice of completion. The supplier records a mechanics lien inside its 30-day window, as backup.
- The GC resolves it by paying the supplier through a joint check in exchange for a release of the stop notice and the lien, or, if it disputes the debt, by posting a release bond of $77,500 (125 percent) so the lender releases the money.
Every step had a deadline. The unpaid party who waits to see if the money shows up usually loses the strongest tool first.
If you’re the GC and one lands on your desk
- Read it the day it arrives. Note the claimant, the amount, the tier and the deadlines it starts.
- Reconcile the sub’s account. What did you pay the sub for this scope, and did the sub pass it down? Check the lien waivers you collected: a sub’s unconditional waiver doesn’t cover its supplier.
- Hold the sub’s next payment until the claim is resolved or the supplier’s conditional waiver is in hand.
- Pay by joint check where the subcontract allows it, against a release of the notice and any lien.
- Bond around a disputed claim instead of letting it freeze a whole draw, and tell your surety if a bond claim is in play.
- Fix the process. Log every preliminary notice at the start of the job, and require lower-tier waivers before paying the sub above them.
The full payment chain, from preliminary notice to final retainage, is in the getting paid guide.
How os.construction handles it
os.construction doesn’t file or track statutory notices or liens for you. What it does today: in the Accounting module, Accounts Payable records conditional and unconditional, progress and final waivers for a vendor or a lower-tier party, holds a bill when a waiver is missing or a stop pay is on the vendor, and supports joint checks. Overrides need approval rights and a reason. Generating waiver requirements from each payment and pay app is planned; see lien waiver tracking.