On this page
- Step 1: Read what the contract allows
- Step 2: Get off-site storage approved before the material ships
- Step 3: Build the backup package
- Step 4: Bill it in the stored materials column
- Step 5: Apply the right retainage rate
- Step 6: Move it to installed, without billing it again
- Step 7: Keep a stored materials log and check it monthly
- Step 8: Hold subcontractors to the same rules
- Worked example: switchgear stored, then installed
- Common mistakes
- How os.construction handles it
- FAQ
To bill stored materials, confirm the contract allows it, get any off-site storage approved in advance, collect the backup the contract requires, bill the amount in the stored materials column of the pay application, and when the material is installed, move it into work completed and reduce the stored column by the same amount. Track every stored item in a log so nothing is billed twice or left behind after it goes in.
Stored materials close a cash gap that lands on contractors whenever expensive equipment arrives long before it can be installed. Switchgear, air handlers, elevators, curtain wall units and fabricated steel are often paid for on supplier terms that come due well before the work is complete. If the contract allows it, billing those materials when they arrive keeps the contractor from financing the owner’s equipment. If you bill them without meeting the contract’s conditions, the owner’s reviewer will strike them and the whole pay app may come back.
Contracts, lenders and public agencies set different rules. The steps below are a practical routine, not a statement of what your contract requires, so read the payment provisions first and ask counsel about anything unclear.
Step 1: Read what the contract allows
Find the clause on payment for materials not yet incorporated in the work. It usually answers:
- On site, off site or both. Many contracts allow on-site stored materials with fewer conditions and off-site materials only with the owner’s written approval in advance.
- Conditions. Invoices, proof of delivery, insurance covering the material, protection from weather and theft, and documents showing title passes to the owner on payment.
- Retainage. Whether stored materials carry the same retainage rate as completed work or a different one.
- Amount. Many contracts limit stored materials to the invoiced cost of the material. Check whether yours allows anything more before you add markup.
How to read construction contract payment terms covers the rest of the payment section.
Step 2: Get off-site storage approved before the material ships
If the material will sit in a supplier’s yard, a fabricator’s shop or a warehouse, send the owner a written request before you need to bill it. List the items, the value, the location, how it will be identified as belonging to the project, the insurance and when the owner or architect can inspect it. Get the approval in writing. Asking after the material is already sitting in a warehouse puts the bill at the mercy of the reviewer.
Step 3: Build the backup package
Assemble the documents your contract and the owner’s lender ask for. A typical package includes:
- The supplier invoice for the material being billed.
- A delivery ticket or bill of lading.
- Dated photos showing the material, tagged or labeled for the project.
- The storage location, and for off-site storage, the storage agreement.
- A certificate of insurance or endorsement covering the stored material.
- For off-site material, a bill of sale or other document the contract requires to show title.
- If requested, a lien waiver or other evidence that the supplier has been or will be paid.
Attach the package to the pay application rather than promising it later.
Step 4: Bill it in the stored materials column
On the G703 continuation sheet, the amount goes in the materials presently stored column on the schedule of values line it belongs to. It does not go in work completed. The total completed and stored to date column adds both, so the line’s percent complete and the G702 payment due include it. How to fill out a pay application explains every column, and the anatomy of a pay app explainer shows where each number flows.
Step 5: Apply the right retainage rate
Withhold retainage on the stored amount at the rate the contract sets for stored materials. If that rate differs from the rate on completed work, show the two separately on the G702 so the reviewer can check each. The retainage calculator and how to calculate retainage cover the arithmetic.
Step 6: Move it to installed, without billing it again
When stored material is installed, enter the installed value in work completed this period and lower the stored column by the same amount. For that portion, the line’s total completed and stored doesn’t change, so the install adds nothing to the payment due. Only new work adds to the bill. If stored and completed work carry different retainage rates, the move changes retainage, and the G702 should show it.
Step 7: Keep a stored materials log and check it monthly
Keep a log with each item, the pay app it was first billed on, the amount, the location, the documents on file, the amount installed to date and the amount still stored. Before each pay app, reconcile the log to the stored column on the G703, and have someone confirm the material is still where the log says. Stored materials that were installed but never moved, or that left the warehouse for another job, are the classic double count.
Step 8: Hold subcontractors to the same rules
If subcontractors bill you for stored materials, their subcontracts should flow down the same conditions you face with the owner, and you should collect the same backup before you include their stored materials in your pay application. Otherwise you can end up paying a subcontractor for material the owner won’t pay you for. How to review a subcontractor pay application covers that check.
Worked example: switchgear stored, then installed
The electrical line on the schedule of values is $640,000. The owner approved off-site storage of the switchgear at the supplier’s bonded warehouse before it shipped. The switchgear invoice is $186,000.
Pay App #6. Rough-in work this period is $32,000, and the switchgear is billed as stored.
| Column | Amount |
|---|---|
| From previous application | $96,000 |
| Work completed this period | $32,000 |
| Materials presently stored | $186,000 |
| Total completed and stored | $314,000 |
| Percent complete | 49.1% |
| Retainage at 10% | $31,400 |
total = $96,000 + $32,000 + $186,000 = $314,000
percent complete = $314,000 ÷ $640,000 = 49.1%
Pay App #7. Two of the three switchgear sections, invoiced at $120,000, are installed. Other electrical work this period is $40,000.
| Column | Amount |
|---|---|
| From previous application | $128,000 |
| Work completed this period | $160,000 |
| Materials presently stored | $66,000 |
| Total completed and stored | $354,000 |
| Percent complete | 55.3% |
| Retainage at 10% | $35,400 |
from previous = $96,000 + $32,000 = $128,000
this period = $120,000 installed switchgear + $40,000 other work = $160,000
stored = $186,000 − $120,000 = $66,000
total = $128,000 + $160,000 + $66,000 = $354,000
The line’s total rose from $314,000 to $354,000, an increase of $40,000. That’s the other electrical work. The $120,000 of switchgear was already billed on Pay App #6, so moving it into work completed adds nothing. Retainage to date rose from $31,400 to $35,400, an increase of $4,000, and the amount due on this line for Pay App #7 is $40,000 − $4,000 = $36,000.
The mistake to avoid is entering the $120,000 in this period without lowering the stored column. The total would read $474,000 and the owner would be billed for the same switchgear twice. A careful reviewer will catch it, and the pay app goes back. A careless one won’t, and the over billing surfaces later in a harder conversation.
For the cash side, stored materials billing changes when money comes in, not how much. The cash flow calculator shows how pay timing moves your low point.
Common mistakes
- Billing off-site material without written approval in advance.
- Sending the backup later, so the reviewer strikes the line now.
- Adding markup the contract doesn’t allow to stored material.
- Installing material without moving it out of the stored column, which double bills.
- No physical check, so the log says material is in a warehouse that shipped it to another job.
- Paying subcontractors for stored material on terms the owner won’t match.
- One retainage rate applied when the contract sets two.
How os.construction handles it
On a payment application, Materials Stored is its own column on every schedule of values line. A new pay app carries stored materials forward in that column, not in From Previous, so they keep the stored materials retainage rate. When material is installed, you add it to This Period and lower Materials Stored by the same amount, and lowering Materials Stored by more than the work added that period is refused. Subcontractor invoices on commitments have the same Materials Stored column. In company Accounting, retainage is calculated separately on completed work and stored materials, as described in accounts receivable. For trade examples, see stored gear for electrical contractors, and for how billing and the ledger connect, see construction accounting software.
FAQ
Can you bill for materials that are not installed yet?
Often, if the contract allows it. Many construction contracts let the contractor bill for materials delivered and suitably stored on site, and some allow materials stored off site with the owner's approval in advance. The contract usually sets conditions such as invoices, insurance, proof that title will pass to the owner and access for inspection. If the contract is silent or prohibits it, ask before you bill.
Where do stored materials go on a G703?
In the materials presently stored column, kept apart from the work completed columns for previous applications and this period. The total completed and stored to date column adds them together, so stored materials count toward the line's percent complete and the payment due.
What happens to stored materials when they are installed?
Move the installed amount from the stored materials column into work completed this period, and reduce the stored column by the same amount. The line's total completed and stored does not change for that portion, so installing material you already billed is not new billing.
Is retainage held on stored materials?
Usually, yes. Many contracts withhold retainage on stored materials, sometimes at a different rate from completed work. When the material is installed, the amount moves to the completed work rate. Check your contract for the rate that applies to each.
What documentation do owners ask for with stored materials?
Common requests are the supplier invoice, a bill of lading or delivery ticket, photos, the storage location, evidence of insurance covering the stored material, and for off-site storage a bill of sale or other document showing title, a storage agreement and access for inspection. Some owners and lenders also ask for proof the supplier has been paid. The contract and the owner's lender set the actual list.
Share this article