How to fill out a G702/G703 pay application, line by line

A G702/G703-style pay application is two pages that have to agree: a continuation sheet that bills each schedule of values line, and a summary that turns those totals into the payment due. Here is how to fill in every column and line, a worked example that ties, and the checks that stop it coming back.

Charley Forey7 min readBillingPay appsAccounting
On this page
  1. Before the first pay app: get the schedule of values approved
  2. How the continuation sheet (G703) works, column by column
  3. How the summary (G702) works, line by line
  4. Worked example: Pay App #4 on a $1.26M job
  5. The monthly routine, step by step
  6. Why pay applications get sent back
  7. How os.construction handles it
  8. FAQ

To fill out a G702/G703-style pay application, start with the continuation sheet: for every schedule of values line, enter what was billed before (column D), the work done this period (E) and materials stored but not installed (F), then total them (G), work out percent complete and balance to finish (H) and retainage (I). Carry the column totals to the one-page summary, subtract retainage and previous certificates, and what’s left is the current payment due. The two pages have to agree to the dollar, and most rejected pay apps fail on that, not on the work.

This is the procedure, in the order you actually do it each month. If you want to watch a full pay app being built cell by cell, the anatomy of a pay app explainer does that. To build one without a spreadsheet, the free pay application builder does the math in your browser.

About the formsAIA Document G702 (Application and Certificate for Payment) and G703 (Continuation Sheet) are copyrighted AIA forms; the editions most contracts reference are the 1992 ones. This post describes the columns and lines so you can fill them in correctly. It doesn’t reproduce the forms. Use licensed copies, or the owner’s own form, as your contract requires.

Before the first pay app: get the schedule of values approved

The schedule of values is the backbone of every pay app on the job. It breaks the contract sum into lines the owner and architect agree to, and every later application bills against those lines. Agree it before you submit the first application, and build it so it can be checked in the field:

  • Lines that match how the work is inspected. “Drywall, floors 1-3” can be walked. “Interiors” can’t.
  • General conditions and mobilization as their own lines, billed over time or on a milestone, as the contract allows.
  • No heavy front-loading. Architects spot an SOV that bills 30% of the job in month one, and an overbilled job is a cash problem you create for later.
  • Totals that equal the contract sum. The column C total on every G703 must equal the contract sum to date on the G702.

How the continuation sheet (G703) works, column by column

The G703 carries one row per SOV line. Here is what goes in each column.

Column What goes in it Where it comes from
A Item number The SOV line number. Keep it the same all job.
B Description of work The SOV line description. Executed change orders get their own lines.
C Scheduled value The SOV value, or the change order amount for a CO line.
D Work completed, from previous application Last month’s column G minus last month’s column F, for that line.
E Work completed, this period Work installed since the last application, agreed with the field.
F Materials presently stored Stored and not yet installed, and not already in D or E.
G Total completed and stored to date D + E + F. Percent complete is G ÷ C.
H Balance to finish C − G.
I Retainage Used when the rate varies by line; otherwise retainage is worked out on the G702.

Two rules catch people out. Column D is not “last month’s G” when last month included stored material: once that material is installed it moves into column E this month, so it isn’t counted twice. And a change order belongs on the sheet only once it’s executed. Pending changes don’t go on a pay app, however certain they feel.

How the summary (G702) works, line by line

The G702 takes the continuation sheet totals and turns them into the amount due. In order:

  1. Original contract sum. From the agreement. It never changes.
  2. Net change by change orders. The total of executed change orders to date. The G702 also has a change order summary box for additions and deductions; it has to agree.
  3. Contract sum to date. Line 1 plus line 2. Must equal the G703 column C total.
  4. Total completed and stored to date. The G703 column G total.
  5. Retainage. Split into (a) the rate on completed work, columns D + E, and (b) the rate on stored material, column F. If you used column I, line 5 equals its total.
  6. Total earned less retainage. Line 4 minus line 5.
  7. Less previous certificates for payment. Line 6 from the previous application, as certified (not as requested, if the architect cut it).
  8. Current payment due. Line 6 minus line 7.
  9. Balance to finish, including retainage. Line 3 minus line 6.
How G703 totals flow into the G702 payment dueThe continuation sheet’s columns D, E and F add up to column G, total completed and stored. Column G becomes G702 line 4. Retainage on line 5 is subtracted to give line 6, total earned less retainage. Previous certificates on line 7 are subtracted to give line 8, the current payment due. In the worked example: 442,000 plus 217,000 plus 63,000 equals 722,000; less 72,200 retainage is 649,800; less 397,800 previous certificates leaves 252,000 due.G703 CONTINUATION SHEET · COLUMN TOTALSD PREVIOUS$442,000E THIS PERIOD$217,000F STORED$63,000G TO DATE$722,000G702 SUMMARYLINE 4$722,000− LINE 5 RET.$72,200= LINE 6$649,800− LINE 7 PREV.$397,800= LINE 8 PAYMENT DUE$252,000CHECK: (E + F) × 90%$280,000 × 0.9 = $252,000
Column totals become line 4. Retainage and previous certificates come off, and what’s left is this month’s check.

Worked example: Pay App #4 on a $1.26M job

Illustrative numbersA made-up tenant build-out: $1,200,000 original contract, one executed $60,000 change order, 10% retainage on work and stored materials. Pay App #3 had no stored materials.

The continuation sheet

A B: Description C: Scheduled D: Previous E: This period F: Stored G: To date % H: Balance
1 General conditions 120,000 40,000 10,000 0 50,000 42% 70,000
2 Sitework 90,000 90,000 0 0 90,000 100% 0
3 Concrete 210,000 168,000 42,000 0 210,000 100% 0
4 Framing and drywall 300,000 60,000 90,000 15,000 165,000 55% 135,000
5 Mechanical, electrical, plumbing 420,000 84,000 63,000 30,000 177,000 42% 243,000
6 Finishes 60,000 0 0 0 0 0% 60,000
7 CO #1 storefront 60,000 0 12,000 18,000 30,000 50% 30,000
Totals 1,260,000 442,000 217,000 63,000 722,000 57% 538,000

The summary

Line Amount
1 Original contract sum $1,200,000
2 Net change by change orders $60,000
3 Contract sum to date $1,260,000
4 Total completed and stored to date (column G) $722,000
5a 10% of completed work (D + E = $659,000) $65,900
5b 10% of stored material (F = $63,000) $6,300
5 Total retainage $72,200
6 Total earned less retainage (4 − 5) $649,800
7 Less previous certificates ($442,000 × 90%) $397,800
8 Current payment due (6 − 7) $252,000
9 Balance to finish, including retainage (3 − 6) $610,200

Three checks prove it ties. Line 3 equals the column C total. Line 9 equals column H plus retainage: $538,000 + $72,200 = $610,200. And because the retainage rate didn’t change, the payment due equals this period’s billing less 10%: ($217,000 + $63,000) × 0.9 = $252,000. Run the same numbers through the retainage calculator if you want a second opinion.

The monthly routine, step by step

  1. Know your cutoff. Most contracts set a billing period end date and a submission date. Missing it can push your payment a full cycle.
  2. Send a pencil draft. Many owners and architects want a draft a week ahead so percent complete can be agreed before the formal application. Walk the job with the architect if that’s the practice.
  3. Roll the sheet forward. Last month’s G minus F becomes this month’s D on every line. Add lines for change orders executed since the last application.
  4. Enter this period’s work from the field, by line. Your superintendent’s view and your cost-to-date should both be in the same neighborhood; if billing runs well ahead of cost, check the WIP before the architect does.
  5. Add stored materials with their backup: supplier invoices, delivery tickets, proof of insurance, and for off-site storage whatever evidence of title and location the contract asks for.
  6. Fill in the summary and run the three checks above.
  7. Assemble the package. Typically the signed application, the continuation sheet, conditional lien waivers for this payment and unconditional ones for the last, subcontractor waivers, stored materials backup, and certified payroll on prevailing wage work. Notarize only if the contract requires it.
  8. Submit, then log it. Record the date, the amount requested and the amount certified. If the architect certifies less, the next application’s line 7 uses the certified figure.

Why pay applications get sent back

  • The pages don’t agree. Line 4 isn’t column G, line 3 isn’t column C, or line 7 isn’t last month’s certified line 6.
  • Percent complete ahead of the field. The architect walks the site. Column G that says framing is 55% done when the third floor is open studs will be marked down.
  • Unexecuted change orders billed. Only executed changes go on the sheet.
  • Stored materials without backup, or materials billed in column E before they’re installed.
  • Missing waivers. A pay app missing last month’s unconditional waivers is often held until they arrive.
  • Retainage at the wrong rate, especially after a reduction milestone or on stored materials.

For what reviewers look for from the other side of the desk, see the owner pay app review, and for the whole billing-to-cash cycle, the getting paid in construction guide.

How os.construction handles it

In Project Financials, the Payment Applications tool builds the continuation sheet from the prime contract’s schedule of values and executed change orders, carries previous applications forward, and works out the G702 summary and retainage on screen. A certified owner pay app can draft an AR invoice in Accounting through the billing bridge, which rechecks the G702 math, earlier billings, SOV and retainage before drafting; normal accounting approval still applies (progress billing and accounting). There’s no print or export of the G702/G703 from the app today, and lien waivers and notarized signatures are handled outside it.

General information, not legal or accounting advice. Payment terms, retainage rates, notarization and supporting documents are set by your contract and, on public work, by statute; rules vary by state. Sources: AIA G702-1992 instructions, AIA guidance on completing G702 and G703, AIA A201-2017 General Conditions (Article 9, Payments and Completion).

FAQ

What is the difference between the G702 and the G703?

The G703 continuation sheet is the detail: one row per schedule of values line, showing work completed in earlier periods, this period, stored materials, total to date, percent complete, balance to finish and retainage. The G702 is the one-page summary: it takes the G703 totals, subtracts retainage and previous certificates, and states the current payment due. The architect certifies on the G702.

How do you calculate the current payment due on a pay application?

Take total completed and stored to date (G703 column G), subtract retainage held on it, and you have total earned less retainage. Subtract that same figure from the previous application, which is the total of previous certificates, and the rest is the current payment due. When the retainage rate hasn't changed, the payment due also equals this period's work plus new stored materials, less retainage on them.

Do pay applications have to be notarized?

Only if the contract or the owner requires it. The AIA G702 has a notary block and many owners and lenders still want it, but plenty of contracts accept an unnotarized or electronically signed application. Check the payment provisions and the owner's billing instructions before the first submission.

Can I bill for materials that are not installed yet?

Usually, if the contract allows it and you meet its conditions. Stored materials go in G703 column F, not column E. Owners typically want invoices, proof of insurance, and for off-site storage a bill of sale or similar evidence of title, and some hold a different retainage rate on them. When the materials are installed, the value moves from column F into column E.

Can I use the AIA forms without buying them?

The AIA G702 and G703 are copyrighted documents licensed through AIA Contract Documents. If your contract calls for the AIA forms, use licensed copies. Many owners accept a G702/G703-style application that carries the same columns and math, and some issue their own form.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Open file