A WIP (work-in-progress) schedule, also called a WIP report, lists every open job with its contract value, estimated total cost, cost to date, percent complete, earned revenue, billed to date and the resulting over or under billing. It is the bridge between job cost and the financial statements, and it is usually the first report a surety or lender asks for.
How it works
Each row is one contract. The columns build on each other, so one bad input spreads across the row.
| Column | Formula or source |
|---|---|
| Contract value | Original contract + approved change orders |
| Estimated total cost | Cost to date + cost to complete, from the PM forecast |
| Projected gross profit | Contract value − estimated total cost |
| Cost to date | Posted job cost through the period end |
| Percent complete | Cost to date ÷ estimated total cost (cost-to-cost) |
| Earned revenue | Percent complete × contract value |
| Gross profit to date | Earned revenue − cost to date |
| Billed to date | Pay app billings, including retainage |
| Over / (under) billing | Billed to date − earned revenue |
| Cost to complete | Estimated total cost − cost to date |
| Backlog | Contract value − earned revenue |
Most contractors recognize revenue over time under ASC 606, and the WIP is where that calculation lives. The month-end entry books the difference between billed and earned: overbillings as a contract liability, underbillings as a contract asset. If estimated total cost exceeds contract value, the whole expected loss is recognized now as a loss provision, not spread over the remaining work.
A good WIP also carries the prior period’s projected margin next to the current one. The difference is margin fade (or gain), and it is the column sureties read most closely.
Why it matters
The WIP shows whether reported profit is real. It exposes jobs where billing has run ahead of work, jobs where the cost forecast hasn’t been updated, and margin that is fading month over month. Without it, the income statement just shows what was billed.
It also drives outside decisions. Sureties use the WIP with the financial statements to size bonding capacity. Banks use it to test working capital covenants. Inside the company, the WIP is where the CFO asks a PM why a job’s margin dropped two points since last month.
What sureties and lenders look for
- Margin fade or gain on each job compared with the last WIP and the original estimate.
- Total overbillings against cash. Cash below overbillings means the company has spent money it hasn’t earned yet.
- Large underbillings, which can mean unapproved change work counted as revenue or a cost forecast that is too low.
- Loss jobs, and whether the full expected loss has been recognized.
- Gross profit left in backlog, which shows how much margin the company still has to earn.
- A tie-out between the WIP totals and the balance sheet.
Worked example
Illustrative numbers for Riverside Medical Center at the Pay App #9 period end:
| Line | Amount |
|---|---|
| Contract (incl. approved COs) | $49,300,000 |
| Estimated total cost | $43,679,800 |
| Projected gross profit | $5,620,200 (11.4%) |
| Cost to date | $31,700,000 |
| Percent complete (cost-to-cost) | 72.6% |
| Earned revenue | $35,778,781 |
| Gross profit to date | $4,078,781 |
| Billed to date (through Pay App #9) | $33,000,000 |
| Under billing | $2,778,781 |
| Cost to complete | $11,979,800 |
Percent complete is $31.7M ÷ $43.68M = 72.6%, and earned revenue is 72.6% of $49.3M. Billed minus earned is negative, so the job is under billed by about $2.78M, which the WIP entry records as a contract asset.
Note that billed percent ($33.0M ÷ $49.3M = 66.9%) is not percent complete. An underbilling this size is a question for the PM: is there approved work not yet billed, is the cost forecast too low, or is cost to date carrying something that isn’t progress, like uninstalled materials?
Common mistakes
- Stale estimated total cost. It makes percent complete and earned revenue wrong at the same time. Run the cost-to-complete review first.
- Re-keying from three systems. A WIP built in a spreadsheet from job cost, billing and forecast exports is easy to get out of sync with the ledger.
- Ignoring unapproved change orders, or counting them too early. Pending change orders belong in the contract value only to the extent a significant revenue reversal isn’t probable (ASC 606 variable consideration).
- Counting uninstalled materials as progress. Material delivered but not installed inflates percent complete. Exclude it from the measure of progress.
- Netting jobs. Each job’s over or under billing is presented separately; one job’s overbilling doesn’t cancel another’s underbilling.
- Not tying to the ledger. The posted WIP totals should match the contract asset, contract liability and revenue accounts every month.
This is general information, not accounting advice. Apply ASC 606 with your auditor or CPA.
How os.construction handles it
The Accounting module’s WIP app computes dated, versioned snapshots for an entity at a period end. Contract value is the executed prime schedule of values plus approved prime change orders, cost is posted job cost, billed is posted AR, and the estimate is the job cost forecast frozen at the period end. Pending change orders show as a memo column and enter the contract value only through an override with a reason. A controller other than the preparer approves before posting, and exceptions block approval until reviewed. Posting books over and under billings and loss provisions at period end with a reversal the next day. The WIP schedule, completed contracts and WIP-to-GL reconciliation reports read the posted snapshot. See Job cost and WIP, live dashboards and WIP and the WIP report guide.
Watch the explainer · 1:45
Over billing vs under billing on a WIP schedule
- 0:00Earned vs billed
- 0:13Percent complete and earned revenue
- 0:36Over billing
- 0:54Under billing
- 1:10Reading the trend
- 1:26WIP from the posted record
Read the transcript
A WIP schedule compares what you've earned on each job with what you've billed. The gap between those two numbers is over billing or under billing, and it's one of the first things a banker or surety reads.
Start with percent complete. With the cost-to-cost method, it's cost to date divided by total estimated cost. Take an illustrative job: a one million dollar contract with eight hundred thousand dollars of estimated cost. You've spent four hundred thousand, so the job is fifty percent complete, and you've earned half the contract: five hundred thousand dollars.
Now look at billing. If you've billed six hundred thousand, you've billed one hundred thousand more than you've earned. That's over billing. It shows up as a liability, often called billings in excess of costs and estimated earnings, because you still owe the customer that work.
If you've billed only four hundred twenty thousand, you've earned eighty thousand more than you've billed. That's under billing. It's an asset, costs and estimated earnings in excess of billings: revenue you've earned but haven't invoiced yet.
Neither one is automatically good or bad. Some over billing can mean healthy cash flow. Under billing that keeps growing can mean you're slow to bill, or that costs are running ahead of the estimate and profit is fading. Watch the trend, job by job, month by month.
In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a WIP schedule in construction?
A WIP (work-in-progress) schedule is a report, usually monthly, that lists every open contract with its contract value, estimated total cost, cost to date, percent complete, earned revenue, billings to date and the resulting over or under billing. It turns job cost data into the revenue and balance sheet numbers on the financial statements.
Is a WIP report the same as a WIP schedule?
Yes. Contractors, CPAs and sureties use WIP report, WIP schedule and schedule of contracts in progress for the same thing. Some reserve schedule of contracts in progress for the version attached to audited or reviewed financial statements, with a separate schedule of completed contracts.
How do you calculate over and under billing on a WIP schedule?
Percent complete = cost to date ÷ estimated total cost. Earned revenue = percent complete × contract value. Over or under billing = billed to date − earned revenue. A positive number is an overbilling (a contract liability); a negative number is an underbilling (a contract asset).
Why do sureties ask for a WIP schedule?
The WIP shows whether reported profit is supported by the cost forecast, whether billing is running ahead of or behind the work, and how much gross profit is left in backlog. Sureties use it, with the financial statements, to judge working capital, margin fade and how much more work a contractor can take on.
How often should a WIP schedule be prepared?
Monthly is common practice, with a reviewed version at each quarter or year end for the surety and lender. A WIP is only as good as its estimated total cost, so the cost-to-complete review on each job should happen before the WIP is run.
What is the difference between a WIP schedule and a cost report?
A cost report looks inside one job, by cost code: budget, committed, actual and forecast. A WIP schedule looks across all jobs, one row per contract, and converts each job's forecast into earned revenue and over or under billing for the company's books.
