Esc

↑↓ move↵ openIndex · Pagefind
Billing

Over billing

Definition

When billings to date exceed revenue earned to date on a job; recorded as a liability called billings in excess of costs and estimated earnings.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Payment & liens · Accounting & WIP

Updated

Billed vs earned over two monthsTwo pairs of bars in millions of dollars. In month 1, billed to date is 13.4 and earned revenue 12.5, so the job is over billed by 0.9. In month 2, billed is 14.4 and earned 15.0, so it is under billed by 0.6.$M to date; axis starts at 10Over 0.9Under 0.613.412.514.415.0BilledEarnedBilledEarnedMonth 1Month 2
Illustrative. Billing ran ahead of the work in month 1 and fell behind it in month 2, turning a $0.9M liability into a $0.6M asset.

Over billing happens when you’ve billed the owner for more than you’ve earned based on percent complete. On the balance sheet it’s a current liability, commonly labeled “billings in excess of costs and estimated earnings” (contract liabilities under ASC 606). The formula is simple: billed to date minus earned revenue. A positive result is over billing.

How it works

  1. Measure progress. Calculate percent complete, usually cost to date divided by estimated total cost.
  2. Earned revenue. Multiply percent complete by the current contract value, including approved change orders. This is earned revenue.
  3. Billed to date. Total the pay applications through the same cutoff, gross of retainage.
  4. Compare. Billed to date minus earned revenue. Positive is over billing; negative is under billing.
  5. Book it. On the WIP schedule, the over billed amount becomes a liability, and revenue is adjusted down to earned.
  6. Recalculate every period. The balance is a snapshot. It moves every month with cost, billing and the forecast.

Why it matters

Some over billing is normal and even healthy: front-loaded schedules of values and early mobilization can put cash ahead of cost. But over billing is cash you owe back in work. If a company spends that cash on overhead or other jobs, it has to finance the remaining work later. Large or growing over billings can also signal cost that hasn’t reached the job ledger yet, which is one way fade hides.

Worked example

Illustrative (a separate example job): a $20.0M contract has an estimated total cost of $17.6M. Cost to date is $11.0M, so the job is 62.5% complete and earned revenue is $12.5M. Billed to date is $13.4M.

Over billing = $13.4M minus $12.5M = $0.9M.

If the full $13.4M had been booked as revenue, reported gross profit would be $13.4M − $11.0M = $2.4M, the entire profit expected on the job, with 37.5% of the work left. The WIP adjustment brings revenue down to $12.5M and earned gross profit to $1.5M, which is 62.5% of the $2.4M projected.

Next month, the job spends another $2.2M and bills only $1.0M:

Line Month 1 Month 2
Cost to date $11.0M $13.2M
Percent complete (÷ $17.6M) 62.5% 75.0%
Earned revenue (× $20.0M) $12.5M $15.0M
Billed to date $13.4M $14.4M
Over (under) billing $0.9M ($0.6M)

The $0.9M liability turned into a $0.6M asset in one month. Nothing went wrong on site; the billing simply fell behind the work. That’s why one month’s number tells you little without the trend.

The Riverside Medical Center sample job is the opposite case: $33.0M billed through Pay App #9 against $35.78M earned, so it’s under billed by $2.78M (see under billing).

Over billing vs under billing

Over billing Under billing
Formula Billed − earned > 0 Earned − billed > 0
Balance sheet Liability (contract liability) Asset (contract asset)
Common label Billings in excess of costs and estimated earnings Costs and estimated earnings in excess of billings
Cash effect Cash ahead of work Contractor financing the work
Healthy cause Mobilization, early billing allowed by the SOV Work after the pay app cutoff
Warning sign Cost forecast too low, front-loaded SOV Unbilled change work, cost overrun

Reading over billings in the WIP

  • Compare with cash. Over billings are a claim on future work. If cash on hand is well below total over billings, that money has already gone somewhere else. Sureties often make this comparison.
  • Watch the direction. Over billing that climbs month after month can mean billing is running ahead of the work, or that cost is reaching the job ledger late. Check the cost cutoff and the forecast before treating the cash as spare. If the forecast is also out of date, the correction often arrives later as margin fade.
  • Check the SOV. Heavy over billing in the first months often traces to a schedule of values that loads early line items such as mobilization or general conditions.

Common mistakes

  • Treating over billing as profit, or as free cash.
  • Front-loading the schedule of values so aggressively that the owner’s reviewer starts rejecting pay apps.
  • Not asking why it grew. An over billing jump can mean cost is posting late, not that billing is strong.
  • Netting over and under billed jobs into one figure, which hides both problems.
  • Calculating it with billed amounts net of retainage on one job and gross on another.

For how to read the two balances together, see over billing vs under billing: what your WIP is telling you.

How os.construction handles it

The WIP app compares supported billings with earned revenue on each snapshot. Posting an approved revision books the overbilling contract liability, and reports read the posted result. See the accounting guide.

Watch the explainer · 1:45

Over billing vs under billing on a WIP schedule

  1. 0:00Earned vs billed
  2. 0:13Percent complete and earned revenue
  3. 0:36Over billing
  4. 0:54Under billing
  5. 1:10Reading the trend
  6. 1:26WIP from the posted record
Read the transcript

A WIP schedule compares what you've earned on each job with what you've billed. The gap between those two numbers is over billing or under billing, and it's one of the first things a banker or surety reads.

Start with percent complete. With the cost-to-cost method, it's cost to date divided by total estimated cost. Take an illustrative job: a one million dollar contract with eight hundred thousand dollars of estimated cost. You've spent four hundred thousand, so the job is fifty percent complete, and you've earned half the contract: five hundred thousand dollars.

Now look at billing. If you've billed six hundred thousand, you've billed one hundred thousand more than you've earned. That's over billing. It shows up as a liability, often called billings in excess of costs and estimated earnings, because you still owe the customer that work.

If you've billed only four hundred twenty thousand, you've earned eighty thousand more than you've billed. That's under billing. It's an asset, costs and estimated earnings in excess of billings: revenue you've earned but haven't invoiced yet.

Neither one is automatically good or bad. Some over billing can mean healthy cash flow. Under billing that keeps growing can mean you're slow to bill, or that costs are running ahead of the estimate and profit is fading. Watch the trend, job by job, month by month.

In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.

FAQ

How do you calculate over billing?

Take billed to date and subtract earned revenue to date. Earned revenue is percent complete times the current contract value, where percent complete is usually cost to date divided by estimated total cost. A positive result is over billing; a negative result is under billing.

Is over billing an asset or a liability?

A liability. It's usually labeled billings in excess of costs and estimated earnings, and under ASC 606 it's presented as a contract liability. It represents work the contractor has been paid or billed for but hasn't yet performed.

Is over billing good or bad?

Moderate over billing is common and helps cash flow, especially early in a job. It turns into a problem when the cash has been spent elsewhere, when it comes from an aggressively front-loaded schedule of values, or when it keeps growing because billing is running ahead of the work or cost is posting late.

What journal entry records over billing?

Where billings are first recorded as revenue, the period-end WIP adjustment debits contract revenue and credits billings in excess of costs and estimated earnings for the over billed amount. That brings revenue down to earned revenue. The entry is usually reversed and recalculated each period.

Why do sureties look at over billings?

Over billings are cash collected for work still to be done, so sureties and lenders often compare them with cash and working capital. If over billings are large and cash is thin, the contractor may have spent money it will need to finish the work.

Sources

Open file