AIA Document G702, Application and Certificate for Payment, is the one-page summary of a progress billing on an AIA contract. It rolls the totals from the G703 continuation sheet into nine lines, from the original contract sum down to the current payment due. The contractor signs it, usually before a notary, and the architect certifies the amount the owner should pay.
Owners and lenders look at the G702 first. Every number on it should tie to the G703 detail, the executed change orders and the previous month’s application. When one line doesn’t tie, the whole pay application tends to come back.
The nine lines
- Original contract sum. The amount in the owner-contractor agreement.
- Net change by change orders. The total of executed change orders, additions less deductions. A summary box on the form splits them between previous months and this month.
- Contract sum to date. Line 1 plus line 2.
- Total completed and stored to date. The G703 column G total: work completed in previous periods, this period, and stored materials not yet installed.
- Retainage. Split into (a) a percentage of completed work and (b) a percentage of stored material, then totaled. It should match the G703 retainage column.
- Total earned less retainage. Line 4 less line 5.
- Less previous certificates for payment. Line 6 from the prior application, as certified.
- Current payment due. Line 6 less line 7.
- Balance to finish, including retainage. Line 3 less line 6.
Below the lines sit the contractor’s certification that the work is complete as stated and that previous payments went to the people they were for, a notary block, and the architect’s certificate with an “amount certified” field.
How it works in the billing cycle
Under AIA A201-2017, the contractor submits its application at least ten days before the payment date, based on the agreed schedule of values. The architect then has seven days to certify the amount it judges due or to explain why it is withholding some or all of it, for example for defective work or third-party claims. The owner pays the certified amount within the time the agreement sets.
The application usually travels with conditional lien waivers for this period and unconditional waivers for the last, plus any stored-materials backup the contract requires.
Why it matters
The G702 is where arithmetic errors become payment delays. A change order total that doesn’t match the executed COs, a retainage line that disagrees with the G703, or a “previous certificates” figure that doesn’t match what was actually certified last month will all get the application rejected, and in many contracts the payment clock restarts when it’s resubmitted.
It also feeds the contractor’s own books. The total billed to date on line 4 is what the WIP schedule compares with earned revenue to find over billing or under billing.
Worked example
Illustrative, using fictional Riverside Medical Center sample data for Pay App #9, with 10% retainage on the prime contract.
| G702 line | Amount |
|---|---|
| 1. Original contract sum | $48,200,000 |
| 2. Net change by change orders | $1,100,000 |
| 3. Contract sum to date | $49,300,000 |
| 4. Total completed and stored to date | $33,000,000 |
| 5. Retainage (10%) | $3,300,000 |
| 6. Total earned less retainage | $29,700,000 |
| 7. Less previous certificates for payment | $27,620,640 |
| 8. Current payment due | $2,079,360 |
| 9. Balance to finish, including retainage | $19,600,000 |
Line 2 is COs #1-13 at $1,013,600 plus CO #14 at $86,400. Line 9 is $49,300,000 less $29,700,000. As a cross-check, this period’s billing on the G703 is $2,310,400; less $231,040 retainage, that is the same $2,079,360 on line 8.
Common mistakes
- A change order total on line 2 that doesn’t match the executed COs, or that includes pending ones.
- Retainage on line 5 that doesn’t tie to the G703 retainage column, often because stored material was retained at a different rate.
- Line 7 taken from what was applied for last month instead of what was certified.
- Billing stored materials without the insurance, title or location backup the contract requires.
- Missing signature, notary stamp or lien waivers that the owner or lender requires with the form.
- Using an outdated or altered copy of the form when the contract calls for the current AIA edition.
The anatomy of a pay app explainer walks the G702 and G703 together, and the getting paid guide shows where the form fits with retainage and lien waivers.
How os.construction handles it
The Payment Applications tool calculates the G702 summary from the G703 lines as you type. Executed change orders on the contract are added to line 2 automatically, retainage is split between work and materials, and line 7 includes any retainage released. The G702 is on screen in the pay app; printing or exporting the G702/G703 isn’t available yet, and the signed, notarized form and lien waivers stay outside the app for now. A certified owner pay app can draft an AR invoice in Accounting through the billing bridge, which rechecks the G702 math before drafting; see project progress billing and accounting.
FAQ
What is an AIA G702?
AIA Document G702, Application and Certificate for Payment, is the one-page summary sheet of a progress billing on an AIA contract. It takes the totals from the G703 continuation sheet, adds approved change orders, subtracts retainage and previous certificates, and arrives at the current payment due. The contractor signs it and the architect certifies the amount.
What is the difference between G702 and G703?
The G703 continuation sheet lists every schedule of values line with work completed this period, previous work, stored materials, percent complete and retainage. The G702 is the summary that rolls those columns into a single payment calculation and carries the contractor's signature and the architect's certification.
How do you calculate the current payment due on a G702?
Start with the contract sum to date (original contract sum plus net change orders). Take the total completed and stored to date from the G703, subtract retainage to get total earned less retainage, then subtract previous certificates for payment. The result is line 8, current payment due.
Does the G702 need to be notarized?
The form includes a notary block for the contractor's signature, and many owners and lenders require it. Some private owners waive notarization. Check the contract and the lender's draw requirements; a missing notary stamp is a common reason pay apps come back.
Can the architect certify a different amount than the contractor applied for?
Yes. Under AIA A201 the architect certifies the amount it believes is due and can certify less, explaining why, for example because of defective work, third-party claims or work not done. The G702 has an amount certified field and asks the architect to explain any difference.
Which change orders go on line 2 of the G702?
Only change orders that have been fully executed. Pending or proposed change orders, and work done under a construction change directive that hasn't been converted, are typically billed separately or left off until signed, depending on the contract.