Esc

↑↓ move↵ openIndex · Pagefind
Billing

Pay Application (Pay App)

Definition

A contractor's periodic, itemized request for payment based on work completed and materials stored against the schedule of values.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

Updated

How a G703 continuation sheet rolls up into a G702 pay applicationThe G703 totals show $4.00M of previous work, $0.90M this period and $0.10M stored, for $5.00M completed and stored with $0.50M retainage. On the G702 that becomes $4.50M earned less retainage, minus $3.60M of previous certificates, for $0.90M current payment due. Illustrative numbers.G703 · Continuation sheettotals rowD prevE thisF storedG totalI ret.$4.00M$0.90M$0.10M$5.00M$0.50MG = D + E + F · I = 10% of GG702 · Application summary3 Contract sum to date$10.25M4 Completed & stored$5.00M5 Retainage (10%)−$0.50M6 Earned less retainage$4.50M7 Previous certificates−$3.60M8 Current payment due$0.90M9 Balance to finish incl. retainage $5.75M
The G703 totals feed G702 lines 4 and 5; the payment due is earned-less-retainage minus what was already certified. Illustrative numbers.

A pay application (pay app) is the contractor’s periodic request for payment, usually monthly. It lists each schedule of values line with work completed to date and materials stored, subtracts retainage and amounts already certified, and shows the payment due. On AIA contracts it is the G702 summary plus the G703 continuation sheet.

Free tool: the pay app builder lays out a G702/G703-style application from your schedule of values and does the retainage math.

In plain English

Illustrative: you have a $1,000,000 contract. By the end of April you’ve done 30% of the work, so $300,000 is earned to date. The owner holds back 10% retainage ($30,000), so $270,000 is the most you can have been paid. You were already paid $180,000 on earlier pay apps. April’s pay app asks for the difference: $270,000 − $180,000 = $90,000. That’s the whole idea, repeated every month with one line per item of work.

The owner’s architect or representative reviews the pay app against work in place, certifies an amount, and the owner (and on financed jobs, the lender) pays it, less retainage. For a general contractor it is the single most important cash inflow on a job, and it is also the document that subcontractor billings, lien waivers and the WIP report all hang from. For a guided tour of the form, see Anatomy of a pay app.

How it works

  1. Schedule of values. At the start of the job the contractor breaks the contract sum into billable lines (the schedule of values), approved by the owner’s rep.
  2. Cutoff and sub billings. Before the monthly cutoff, subcontractors submit their own pay apps to the GC, which rolls them up line by line.
  3. Pencil draft. Many teams walk a draft with the owner’s rep or architect to agree percent complete before the formal submission.
  4. G703 continuation sheet. For each line: work completed in previous periods, work this period, materials presently stored, total to date, percent complete, balance to finish and retainage.
  5. G702 summary. The G703 totals roll up into the contract sum to date, total completed and stored, retainage, previous certificates and current payment due.
  6. Backup. Lien waivers (conditional for this period, unconditional for the previous one), stored materials invoices, certified payroll on public work, and executed change orders.
  7. Certification and payment. The architect certifies all or part of the amount; the owner pays within the contract’s terms, subject to any state prompt payment law.

G702 vs G703 at a glance

G702 (Application and Certificate for Payment) G703 (Continuation Sheet)
Purpose One-page summary and certification Line-by-line detail behind the summary
Rows Nine summary lines One row per schedule of values line, plus change orders
Key numbers Contract sum to date, retainage, current payment due Scheduled value, previous, this period, stored, total, %, balance
Signatures Contractor (often notarized) and architect None on its own

The two must tie: the G703 total completed and stored (column G) equals G702 line 4, and the G703 retainage total equals line 5. See AIA G702 and AIA G703 for the forms in more depth.

Formula

  • Total completed and stored to date (G) = previous work (D) + this period (E) + materials presently stored (F)
  • Percent complete = G ÷ scheduled value (C)
  • Balance to finish (H) = C − G
  • Total earned less retainage = G − retainage
  • Current payment due = total earned less retainage − previous certificates for payment

Worked example

Illustrative numbers, not from a real project:

G702 line Amount
1. Original contract sum $10,000,000
2. Net change by change orders $250,000
3. Contract sum to date $10,250,000
4. Total completed and stored to date $5,000,000
5a. Retainage, 10% of completed work ($4,900,000) $490,000
5b. Retainage, 10% of stored material ($100,000) $10,000
6. Total earned less retainage $4,500,000
7. Less previous certificates for payment $3,600,000
8. Current payment due $900,000
9. Balance to finish, including retainage $5,750,000

Behind line 4, the G703 shows $4,000,000 of work from previous periods, $900,000 this period and $100,000 of materials stored on site. The previous certificate was $4,000,000 less 10% retainage, or $3,600,000. The $900,000 due happens to equal this period’s work because the $90,000 of retainage held on the new work is offset by the $90,000 net billed for stored material ($100,000 less its own $10,000 retainage). Use the retainage calculator to try your own rates.

Before the owner releases the $900,000, a lender will typically want the GC’s conditional waiver for this period and unconditional waivers from subs paid out of the last draw. A missing waiver from one trade can hold up the whole draw.

Why it matters

The pay app is the GC’s main cash inflow, and the GC usually owes subs whether or not the owner has paid. Errors, missing backup or missing lien waivers delay payment. Billing ahead of work creates over billing; billing behind starves cash and creates under billing on the WIP schedule, which is measured against earned revenue, not billings.

Outside the US the same request goes by other names: an application for payment or interim valuation in the UK, a progress draw in Canada. The US-UK construction term map explains how UK payment notices change the process.

Common mistakes

  • Billing percentages the architect won’t accept because they don’t match work in place.
  • Billing change orders before they are executed, or forgetting to add executed ones as new lines.
  • Front-loading the schedule of values so early lines are overvalued, which owners increasingly reject.
  • Math that doesn’t tie between the G702 and G703 after a late edit.
  • Sending the pay app without sub billings and waivers rolled up.
  • Treating billings as revenue in the books instead of reconciling to earned revenue.

How os.construction handles it

Payment applications are live in the project app. A pay app is built in the AIA G702/G703 layout: lines come from the contract’s schedule of values, executed change orders are added for you, retainage is calculated per line, and stored materials are carried with their own retainage. Pay apps can be made against a prime contract, a subcontract or a purchase order. See Payment applications and Pay apps, SOV and retainage.

Project pay app status does not automatically post a company AR journal entry. In the Accounting module, a certified owner pay app can draft an AR invoice through the billing bridge; see Progress billing (G702/G703). Owners reviewing a pay app can use the owner’s review checklist.

Watch the explainer · 2:02

What is a schedule of values?

  1. 0:00The contract sum, line by line
  2. 0:18Who prepares it
  3. 0:39Billing against the lines
  4. 0:57Change orders get their own lines
  5. 1:17Front-loading
  6. 1:39The SOV in os.construction
Read the transcript

A schedule of values, or SOV, breaks the contract sum into line items, such as general conditions, sitework, concrete, steel, mechanical and electrical, each with a dollar value. The lines add up to the contract sum, and every pay app bills against them.

The contractor prepares it. Under AIA A201, section nine point two, on stipulated sum and GMP contracts, the contractor submits it before the first application for payment. The architect reviews the values and can ask for backup. Once it's accepted, it's the basis for reviewing every pay app.

Each month, the continuation sheet reports every line: work from previous applications, work this period, materials stored, total to date, percent complete, balance to finish and retainage. The summary page rolls those columns up into the current payment due.

Approved change orders change the contract sum, so each one is added, usually as its own line. On the sample Riverside job, change order fourteen, eighty-six thousand four hundred dollars for fire dampers, becomes its own line, and the SOV now totals forty-nine point three million. Pending changes stay off the bill.

Front-loading means putting more value on early lines, like mobilization or general conditions, than the work is worth, so more is billed early. It helps the contractor's cash flow, but leaves the owner paying ahead of the work, which is why architects look for it. A good SOV has lines you can measure progress on, each tied to cost codes.

In os.construction, prime contracts, subcontracts and purchase orders each hold a schedule of values. Payment applications fill the continuation sheet from the contract's SOV, add executed change orders and carry the previous column forward, so nobody retypes the SOV each month.

FAQ

What does pay app mean in construction?

A pay app (payment application) is the contractor's formal request to be paid for work done during a billing period, usually a month. It lists every schedule of values line with work completed to date and materials stored, subtracts retainage and earlier payments, and arrives at the amount due. The architect or owner's rep reviews and certifies it before payment.

What is the difference between AIA G702 and G703?

The G702 is the one-page summary: contract sum, change orders, total completed and stored, retainage, previous certificates and the current payment due. The G703 is the continuation sheet behind it, with one row per schedule of values line. The G703 column totals feed the G702, so the two must always tie.

How often are pay applications submitted?

Most contracts call for monthly pay apps, often on a fixed cutoff date such as the 25th, with a pencil draft reviewed with the owner's rep before the final is submitted. The contract sets the cutoff, the review period and the payment terms, and many states have prompt payment laws that set outer limits.

Can you bill for stored materials on a pay app?

Often, yes, if the contract allows it. Materials delivered to the site or a bonded warehouse but not yet installed are billed in the G703 materials presently stored column. Owners and lenders usually require invoices, proof of insurance and sometimes a bill of sale or inspection before they pay for stored materials.

Why do pay applications get rejected?

Common reasons are percent complete that the architect disagrees with, change orders billed before they are executed, missing lien waivers from the GC or subs, math that does not tie between G702 and G703, and missing backup for stored materials. Most rejections are avoided by walking a pencil draft with the owner's rep first.

Do I have to use the AIA pay app forms?

Only if the contract requires them. Many private and public contracts call for AIA G702/G703 or the owner's own form, and lenders often specify their draw format. Other jobs accept any itemized request that shows the schedule of values, work to date, retainage and amount due. AIA forms are licensed documents; free builders produce the same layout but are not official AIA documents.

Sources

Keep exploring

Related across os.construction

Open file