- Step 1: Check the contract, the period and the previous amounts
- Step 2: Verify progress with the field
- Step 3: Allow only executed change orders
- Step 4: Check stored materials against the backup
- Step 5: Apply the subcontract’s retainage
- Step 6: Confirm compliance before it reaches AP
- Step 7: Check the math
- Step 8: Approve, adjust or return, and record why
- Worked example: a mechanical subcontractor’s Pay App #5
- Common mistakes
- How os.construction handles it
- FAQ
To review a subcontractor pay application, confirm it bills against the current subcontract and only executed change orders, verify each line’s progress with the superintendent, check any stored materials against their backup, apply the subcontract’s retainage rate, confirm insurance, lien waivers and other compliance documents are current, and check that every column foots. Then approve the amount you can support, line by line, and send the subcontractor the reasons for any change.
Subcontractor billing is usually the largest group of payments on a general contractor’s job. Every dollar approved over what’s earned is a dollar you’ve paid ahead of the work, and possibly ahead of what the owner will pay you. The owner’s reviewer will apply the same scrutiny to your pay application; the owner pay app review explainer shows what they check. Reviewing the subcontractor’s billing with the same discipline keeps the two in step.
Step 1: Check the contract, the period and the previous amounts
Before looking at progress, confirm the basics:
- The pay app is against the right subcontract and covers the right period.
- The schedule of values matches the approved one: same lines, same scheduled values.
- The contract sum equals the original subcontract plus executed commitment change orders.
- The “from previous” amounts equal what you approved last month, not what the subcontractor asked for last month.
If any of these fail, return the pay app before spending time on the rest.
Step 2: Verify progress with the field
Send each line to the superintendent, or walk it together. For each one, compare the billed percent complete to what’s in place, using installed quantities where the work can be counted: linear feet of duct, fixtures set, floors framed. Also compare against the schedule, and against what you’re billing the owner on the corresponding lines. If you’re billing the owner 60% on mechanical and approving the mechanical subcontractor at 75%, one of those numbers is wrong. The earned value calculator helps when you want to compare earned progress against cost by line.
Step 3: Allow only executed change orders
Change order lines on the pay app should match commitment change orders that are executed. A pending change, a disputed T&M ticket or a change still being priced doesn’t belong on the bill yet. Once a change order is executed, verify its progress like any other line. How to price a change order covers how it gets there.
Step 4: Check stored materials against the backup
If the subcontractor bills stored materials, the subcontract should require the same backup the owner requires of you: invoices, proof of delivery, insurance, photos and approval for any off-site storage. Don’t approve stored material the owner won’t pay you for. How to bill stored materials covers the backup and how to move it to installed.
Step 5: Apply the subcontract’s retainage
Apply retainage at the rate in the subcontract, including any separate rate for stored materials and any reduction the subcontract allows after a milestone. Check that retainage to date is calculated on total completed and stored to date. The retainage calculator and how to calculate retainage cover the arithmetic, including flow-down.
Step 6: Confirm compliance before it reaches AP
Check what the subcontract requires with each payment. Common items:
- A current certificate of insurance with the required additional insured endorsements.
- A conditional lien waiver for this payment and an unconditional lien waiver for the last payment, once it has cleared. Some states require specific statutory forms.
- Waivers from lower-tier subcontractors and major suppliers, if required.
- Certified payroll on prevailing wage work; see the WH-347 guide.
- A current license, and any other documents the subcontract lists.
Missing documents usually mean the payment is held until they arrive, not that the work isn’t approved. Record which applies.
Step 7: Check the math
Foot each column and cross-foot each line: from previous plus this period plus stored equals total completed and stored, and scheduled value minus that total equals the balance to finish. Check the summary: total completed and stored, less retainage, less previous certificates, equals the amount due. Arithmetic errors are common and easy to fix before payment and harder after.
Step 8: Approve, adjust or return, and record why
Approve the amount you can support. Where you adjust a line, note the reason next to it, and send the approved version back to the subcontractor so their next pay app starts from your numbers. Payment timing then follows the subcontract terms, including any pay-when-paid clause. Pay-when-paid vs pay-if-paid explains how those clauses differ, and prompt payment laws in some states and on public work may set deadlines. Ask counsel if you plan to withhold beyond what the subcontract plainly allows.
Worked example: a mechanical subcontractor’s Pay App #5
The mechanical subcontract is $1,180,000, plus executed commitment change order #2 for $36,000, for a revised subcontract of $1,216,000. Previously approved work is $362,000: $210,000 on ductwork and $152,000 on piping.
| Line | Scheduled value | Billed this period | Approved this period | Reason |
|---|---|---|---|---|
| Ductwork | $420,000 | $84,000 | $63,000 | Field at 65%, not 70% |
| Piping | $380,000 | $76,000 | $76,000 | Verified |
| Equipment, stored | $300,000 | $150,000 | $150,000 | Invoice, delivery, insurance on file |
| Controls | $80,000 | $20,000 | $0 | Not started |
| CCO #2 | $36,000 | $36,000 | $18,000 | Field at 50% |
| CO #3 (pending) | n/a | $18,000 | $0 | Not executed |
| Total | $1,216,000 | $384,000 | $307,000 |
The ductwork arithmetic:
billed to date = ($210,000 + $84,000) ÷ $420,000 = 70%
field-verified to date = 65% × $420,000 = $273,000
approved this period = $273,000 − $210,000 = $63,000
The change order line: 50% × $36,000 = $18,000.
The amount due.
total completed and stored to date = $362,000 + $307,000 = $669,000
retainage to date at 10% = $66,900
earned less retainage = $669,000 − $66,900 = $602,100
less previous approvals ($362,000 − $36,200) = $325,800
current amount due = $602,100 − $325,800 = $276,300
That equals this period’s approved $307,000 less its $30,700 of retainage. The subcontractor had asked for $384,000 less $38,400 of retainage, or $345,600, so the review approves $69,300 less than requested. The job is now $669,000 ÷ $1,216,000 = 55.0% complete on this subcontract.
Accounts payable then confirms the insurance certificate is current, the conditional waiver for this payment and the unconditional waiver for Pay App #4 are on file, and the subcontract’s pay-when-paid clause ties this payment to the owner’s payment on your corresponding pay app. The approved G703, with a reason on each changed line, goes back to the subcontractor.
Common mistakes
- Starting from last month’s billed amounts instead of last month’s approved amounts.
- Approving percent complete from the office without a field check.
- Paying pending change orders because the work was done.
- Approving stored materials the owner won’t pay you for.
- Missing a retainage reduction or a separate stored materials rate in the subcontract.
- Releasing payment without current insurance or waivers, then chasing them afterwards.
- Cutting lines without saying why, which turns the next pay app into an argument.
How os.construction handles it
On a subcontract or purchase order, a sub invoice opens with a line for each schedule of values item, with From Previous, This Period, Materials Stored, Total Completed and Stored, percent, Balance to Finish and Retainage; retainage on each line is the total completed and stored times the commitment’s rate. In company Accounting, AP matches bills to the commitment and receipts, holds bills for missing compliance documents or lien waivers, and on release re-checks pay-when-paid bills against the owner payments received. Automatic invoice checks inside the commitments tool itself are still planned. See three-way match for construction AP, retainage, lien waivers and pay apps on one record, the life of an invoice explainer, and construction accounting software. For change orders, see change order software.
FAQ
Who should review a subcontractor's pay application?
Usually the project manager checks the contract, change orders and amounts, the superintendent confirms progress in the field, and accounts payable checks retainage, compliance documents and the math before payment. Splitting the checks this way means no one person both approves the work and releases the money.
How do you verify a subcontractor's percent complete?
Compare what the subcontractor billed on each schedule of values line with what the superintendent observes in place, using installed quantities where you can. Check it against the schedule and, where the lines correspond, against what you are billing the owner for the same work.
Can a general contractor reduce a subcontractor's pay application?
Generally the subcontract lets the contractor approve the amount it believes is earned and documented, and to reject or reduce items that are not. Adjust line by line, state the reason for each change in writing and send the approved version back to the subcontractor. Read your subcontract, and ask counsel about disputes or withholding.
Should pending change orders be paid on a subcontractor pay app?
Usually not. Only change orders that have been executed and added to the subcontract belong on the pay app. Pending or disputed changes should be priced and approved through the change order process first.
What lien waivers should come with a subcontractor pay app?
A common practice is a conditional waiver for the payment being requested and an unconditional waiver for the previous payment once it has cleared, plus waivers from lower-tier subcontractors and major suppliers if the subcontract requires them. Some states prescribe statutory waiver forms, so check the rules where the project is located.