How to price a change order: labor, material, subs and markup, worked line by line

Owners review change order proposals line by line, so price them that way: define the scope, read the changes clause, cost labor at burdened rates, add material, equipment and sub quotes, then apply the contract's markups in order. Here is each step and a full worked example from direct cost to the final number.

Charley Forey6 min readChange ordersEstimatingBilling
On this page
  1. Step 1: Pin down the scope of the change
  2. Step 2: Read the changes clause before you price
  3. Step 3: Take off quantities and price labor at the burdened rate
  4. Step 4: Add material, equipment and other direct costs
  5. Step 5: Get sub quotes and check them
  6. Step 6: Apply the markups in the contract’s order
  7. Step 7: Add the time, the backup, and log it
  8. Worked example: adding a storage room
  9. Common mistakes
  10. How os.construction handles it
  11. FAQ

To price a change order, define exactly what changed, read the contract’s changes clause, price the direct cost line by line (labor at the fully burdened rate, material with tax and delivery, equipment, and subcontractor quotes), then apply the contract’s markups in the order it sets: usually overhead and profit on your own work, a lower markup on sub work, then insurance and bond on the total. Add any schedule time and attach the backup.

A change order proposal gets reviewed line by line by someone whose job is to find what doesn’t belong. A price built the same way, with every number traceable to a quote, a timecard rate or a contract clause, gets approved faster and with fewer cuts. The free change order markup calculator runs the same math in your browser.

Step 1: Pin down the scope of the change

Write a short scope description: what’s being added, deleted or changed, where, and which document caused it, such as an RFI answer, an ASI, a construction change directive or an owner request. List what’s excluded. Most pricing disputes start with two parties pricing different scopes.

If you haven’t already, log it as a change event the day you learn about it, before the price exists. The change event log is a simple way to do that.

Step 2: Read the changes clause before you price

The contract decides more of the number than the estimate does. Look for:

  • Allowable markups, for your own work and for subcontracted work, and whether they’re tiered by size.
  • What counts as cost. Some contracts allow supervision, small tools or general conditions on changes; others fold them into the markup.
  • Insurance and bond. Whether they’re added as percentages or included in overhead.
  • Required backup and format.
  • Notice deadlines and how time is to be requested.

Reviewers will apply the clause line by line, so you might as well price to it.

Step 3: Take off quantities and price labor at the burdened rate

Take off the work and estimate hours by task. Price labor at the full cost of an hour: base wage plus labor burden (payroll taxes, workers’ compensation, insurance, benefits or union fringes).

labor cost = hours × base wage × (1 + burden %)

Using the base wage alone is the most common way to underprice a change. The labor burden calculator works out the percentage from your own costs.

Step 4: Add material, equipment and other direct costs

Price material from current quotes, with sales tax where it applies, delivery and a reasonable waste factor. Add equipment at your rates or rental invoices, and any permit fees, disposal or testing the change requires. Don’t forget the small things that are easy to leave out: cleanup, protection, mobilization if a crew has to come back.

Step 5: Get sub quotes and check them

Ask each affected sub for a priced breakdown, not a lump sum. Check their scope matches yours, their exclusions don’t leave a gap, and their markup follows the flow-down of the prime contract’s changes clause. A sub quote already includes the sub’s overhead and profit, which is why most contracts allow the GC a smaller markup on it.

Step 6: Apply the markups in the contract’s order

A common order:

  1. Overhead and profit on self-performed direct cost.
  2. GC markup on subcontract cost.
  3. Insurance on the subtotal.
  4. Bond on everything before it, since bond premiums are usually charged on total contract value.

Check whether profit is on cost alone or compounds on cost plus overhead, and match the contract’s wording. Remember that markup on cost isn’t margin on the price; the post on markup vs margin on change orders shows why a 15% markup is a 13% margin.

Step 7: Add the time, the backup, and log it

If the change affects completion, request days with the price and support them with a schedule analysis. If you can’t assess the time yet, say so in the proposal and reserve the right to request it, in whatever form the contract requires. Attach the backup, number the proposal, and add it to your change order log as pending so it shows in the forecast until it’s signed.

Worked example: adding a storage room

Illustrative numbersA made-up change on a lump-sum contract. The markup rates are examples, not industry standards; use the ones in your contract.

The owner asks for a new storage room off a corridor: one new partition, a door, and power. The GC self-performs the door, frame and hardware; drywall and electrical are subcontracted. The contract allows 10% overhead and 5% profit on self-performed cost (not compounded), 5% on subcontract cost, 1% insurance and 0.8% bond.

Self-performed direct cost

Item Calculation Amount
Carpenter labor 40 h × $38.00 × 1.45 (45% burden) $2,204.00
Hollow metal frame, door, hardware quote $1,850.00
Sales tax on material $1,850.00 × 7% $129.50
Scissor lift 1 week rental $425.00
Self-performed cost $4,608.50

Subcontract cost

Sub Scope Amount
Drywall sub Framing, board, tape and finish, 42 LF partition $6,400.00
Electrical sub Two receptacles, one light fixture, switch $2,150.00
Subcontract cost $8,550.00

Markups, in order

Line Calculation Amount Running total
Self-performed cost $4,608.50 $4,608.50
Overhead, 10% $4,608.50 × 10% $460.85 $5,069.35
Profit, 5% $4,608.50 × 5% $230.43 $5,299.78
Subcontract cost $8,550.00 $13,849.78
GC markup on subs, 5% $8,550.00 × 5% $427.50 $14,277.28
Insurance, 1% $14,277.28 × 1% $142.77 $14,420.05
Bond, 0.8% $14,420.05 × 0.8% $115.36 $14,535.41
Change order total $14,535.41
From direct cost to change order totalDirect cost of 13,158.50 dollars, made up of 4,608.50 self-performed and 8,550 subcontracted, plus 691.28 overhead and profit on self-performed work, 427.50 markup on subs, 142.77 insurance and 115.36 bond, totals 14,535.41 dollars.COST13,158.50OH&P691.28SUB MKUP427.50INS142.77BOND115.36TOTAL14,535.41MARKUPS ADD 1,376.91: 10.5% ON COST, 9.5% OF PRICE
Each markup sits on the base the contract names, in order. Bar heights not to scale for the small items. Illustrative.

Direct cost is $13,158.50 ($4,608.50 + $8,550.00) and markups add $1,376.91, so the blended markup is 10.5% on cost and the margin is 9.5% of the price. If the contract instead allowed profit on cost plus overhead, profit would be 5% × $5,069.35 = $253.47, $23.04 more. Small on one change, but worth getting right across a job’s worth of them. The animated how a change order is priced explainer builds this same example one layer at a time.

Notice what isn’t in the price: superintendent time and general conditions. On this contract they’re covered by the overhead percentage. If your contract lets you price supervision as a direct cost on changes, add it as its own line with hours and rate. And if the room had moved the completion date, the proposal would also ask for days.

Common mistakes

  • Pricing labor at the base wage. Burden is real cost.
  • Full markup on sub quotes. The sub’s markup is already inside; reviewers will cut it back to the contract rate.
  • Markups in the wrong order, or bond calculated before insurance when the contract says otherwise.
  • Leaving out the small direct costs: cleanup, protection, delivery, equipment, return trips.
  • No time request. Signing a change order without addressing time can settle the time question too.
  • Missing the notice deadline while waiting for a complete price. Give notice on time, then price.
  • Lump sums without backup. They take longer to approve and get cut harder.

How os.construction handles it

In Change Orders, a change event records the change and its rough cost by cost code, and can name the RFI it came from. A potential change order copies those line items against the prime contract or a subcontract, with a grand total that includes any markup and tax on the lines, plus a schedule impact in days. Executed change orders update the contract sum and budget, and PCOs can be grouped into a package so the owner gets one change order. The life of a change order guide shows the full path.

FAQ

How do you price a change order in construction?

Define the changed scope, read the contract's changes clause for allowable costs and markups, take off quantities, price labor at the fully burdened rate, add material with tax and delivery, equipment and subcontractor quotes, then apply the contract's markups in order: overhead and profit on self-performed work, a separate markup on subcontracted work, then insurance and bond. Add any time impact and attach the backup.

What is a typical markup on a change order?

There is no single typical figure; the contract usually sets it. Many contracts allow a percentage for overhead and profit on the contractor's own work and a lower percentage on subcontracted work, since the sub's quote already includes its own markup. Read the changes clause and any markup schedule before pricing.

Should overhead and profit be compounded on a change order?

Only if the contract allows it. Some contracts allow overhead and profit as two separate percentages of cost; others allow profit on cost plus overhead, which compounds slightly. 10% and 5% on cost is 15%; 5% profit on cost plus 10% overhead is 15.5%.

Should a change order include schedule time?

If the change affects the completion date, yes. Request the time with the price, supported by a schedule analysis. If you can't assess time yet, say so in the proposal and reserve the right to request it, in whatever form the contract requires. A signed change order with no time is often treated as settling the time question.

What backup should go with a change order proposal?

Whatever the contract asks for, which commonly includes a labor breakdown with hours and rates, material quotes or invoices, equipment rates, subcontractor quotes with their own breakdown, the markup calculation, and the RFI, directive or other document that caused the change.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Keep readingAll articles →
Open file