AIA G714Construction change directive: do the work, settle the price later
A CCD orders changed work when the owner and contractor haven’t agreed on price, time or both, and the work can’t wait. AIA’s form is G714-2017, Construction Change Directive, governed by A201-2017 Section 7.3. The architect prepares it and the owner and architect sign it. Once the contractor receives it, the contractor must proceed promptly.
The form proposes how the adjustment will be priced: a lump sum, unit prices, or cost plus a fee, matching the methods in Section 7.3.3. The contractor has a signature block too, but signing means it agrees with the proposed adjustment, and that agreement is then recorded as a change order. If the contractor doesn’t agree, it doesn’t sign, the work goes ahead anyway, and the architect determines the adjustment from the contractor’s documented cost plus allowed overhead and profit, subject to the claims process.
CCDs keep a job moving but they put the cost risk on the contractor’s cash. Two habits protect it. First, give CCD work its own cost code and collect signed daily T&M tickets from day one. Second, bill it: A201-2017 Section 7.3.9 lets the contractor request payment for CCD work pending the final number, with the architect making an interim determination for monthly certification. The T&M tickets to a priced change walkthrough shows the ticket side.