From RFI to change order: ASI, field order, CCD and CO

A question from the field can end in four different documents. Which one depends on two things: does the change move the contract sum or time, and has anyone agreed the price yet. Here is the decision, the forms side by side, and where the money gets lost between them.

Visual guide13 min read

The short answer

Two questions pick the form

If a change does not move the contract sum or contract time, the design professional issues it alone: an Architect’s Supplemental Instruction on AIA G710 under AIA contracts, or a field order under EJCDC engineering contracts. If it does move sum or time and the price is agreed, it is a change order on AIA G701, signed by owner, contractor and architect. If the work can’t wait for agreement, the owner and architect issue a construction change directive on AIA G714, and the money is settled later.

An RFI sits upstream of all four. It is a question, not a change. Its answer can arrive as a sketch, an ASI, a bulletin issued for pricing, or nothing more than a clarification. The contractor’s job is to read every answer against one test: does this cost money or time? If it does, give written notice before doing the work.

Which change document to useA decision flow. A change shows up from an RFI answer, a design revision or an owner request. First question: does it change the contract sum or contract time? If no, the architect issues an ASI on AIA G710 under AIA contracts, or the engineer issues a field order under EJCDC contracts; neither changes sum or time. If yes, second question: are price and time agreed? If yes, a change order on AIA G701 is signed by owner, contractor and architect. If not yet and the work cannot wait, the owner and architect sign a construction change directive on AIA G714 and the amount is settled later, usually by a change order. If the contractor finds that an ASI or field order does cost money or time, it gives written notice before proceeding and the change moves to the change order path.A change shows upRFI answer · design revision · owner askChanges contractsum or time?NoAIAEJCDCYesPrice and timeagreed?Not yetYesASIAIA G710architect signsno $ or timeField orderEJCDC C-942engineer signsno $ or timeCCDAIA G714owner, architect$ + time laterChange orderAIA G701all three sign$ + time agreedsettled later as a COcosts money or time? notice before proceeding
The question is never which form is handiest. It is whether the change moves money or time, and whether that has been agreed.
Side by side

The forms compared: who signs, what changes, when it’s used

AIA form numbers and A201-2017 sections, with the EJCDC equivalent where one exists. Other families (ConsensusDocs, owner-written forms, federal FAR clauses) use different names for the same ideas.

Change documents compared
DocumentWho issues itWho signsCost or time impactWhen it’s usedContract basis
RFINo standard AIA formContractorNobody signs to change the contractNone by itself. The answer might.The documents are unclear, conflict or are missing information.Contract’s RFI procedure, usually Division 01
ASIAIA G710ArchitectArchitect onlyNone: no change in contract sum or timeClarifications, interpretations and minor changes consistent with the design intent.A201-2017 §7.4 (minor changes)
Field orderEJCDC C-942Engineer (EJCDC); some owners use the term for any field directiveEngineerNone under EJCDC. Owner forms vary.Minor changes on engineering and public works contracts.EJCDC C-700 general conditions
Proposal requestAIA G709Architect, often with a bulletinNobody yet: it asks for a priceProposed, not agreedThe owner wants a price for a change before deciding.Owner’s choice to price a change
CCDAIA G714 · EJCDC C-940 (WCD)Architect prepares; owner directsOwner and architect. Contractor signs only if it agrees.Yes. Amount and time are settled later.Work must proceed before price or time is agreed.A201-2017 §7.3
Change orderAIA G701 · EJCDC C-941Architect preparesOwner, contractor and architectYes: agreed change in sum, time or bothThe parties agree on the change, the price and the time.A201-2017 §7.2

AIA variants follow the same pattern: G701S for contractor-subcontractor change orders, G731 and G733 for the construction manager as adviser editions of the change order and CCD, and G741 for design-build change orders.

Step one

An RFI asks; it never changes the contract

A request for information is the contractor’s written question to the design team: a conflict between drawings, a missing dimension, a detail that won’t build. The RFI itself changes nothing. What matters is the answer, and answers come in different wrappers. A one-line reply that confirms what the drawings already say is just a clarification. A reply with a revised detail usually comes as an ASI. A reply that adds scope may come as a bulletin with a request for price.

Every answer gets the same review before it goes to the trades: does it change quantities, materials, labor, sequence or duration compared with what you bid? Ask the affected subs the same day. If the answer is yes, open a change event and send notice, even if the document says “no change in contract sum.” The RFI response time and ball-in-court guide covers keeping the questions themselves moving.

AIA G710

Architect’s Supplemental Instructions (ASI): the no-cost instruction

An ASI is the architect’s written instruction that clarifies the documents or orders a minor change consistent with the design intent, with no change to contract sum or contract time. AIA’s form for it is G710-2017, Architect’s Supplemental Instructions. The architect prepares it, signs it and sends it to the contractor, with copies to the owner. There is no owner or contractor signature block: the authority comes from the contract, not from agreement.

That authority is A201-2017 Section 7.4, which lets the architect order minor changes in the work that don’t adjust sum or time and aren’t inconsistent with the intent of the documents. The same section says that if the contractor believes a proposed minor change will affect sum or time, it must notify the architect and not proceed. That sentence is the whole ballgame for a GC. An ASI built without objection is, in practice, accepted as free.

What an ASI form typically carries: the project and contract, an ASI number and date, a description of the instruction, attached sketches or revised sheets, and the architect’s signature. Many firms use their own ASI template instead of the AIA form, and some number revised sheets under the ASI. If the ASI involves real cost, the architect usually withdraws it or reissues the change through a proposal request and change order. The glossary entry on ASIs has an ASI log checklist and a worked example.

EJCDC C-942

What is a field order in construction?

A field order is a written order for a minor change in the work that doesn’t change the contract price or contract times. It is the engineering-contract twin of the ASI. Under the EJCDC family, which is common on water, wastewater and other public works, the engineer issues field orders on form C-942, alongside the C-940 Work Change Directive (the CCD equivalent) and the C-941 Change Order.

Outside EJCDC the term is looser. Some public owners and many private ones call any directive written on site a field order, including ones that will be priced on T&M tickets. That is a real difference: one is free by definition, the other is a directive with a price to follow. Read your contract’s definition before you treat a field order as either. The field order glossary entry covers what a good one contains.

AIA G709 and bulletins

Pricing a change before anyone commits

When the owner is considering a change and wants a price first, the architect sends a proposal request. AIA’s form is G709-2018, Work Changes Proposal Request, and it usually travels with a bulletin, a package of revised drawings and specification sections. Nothing is authorized yet. The contractor prices it, often as a potential change order built from sub quotes, and the owner decides whether to proceed.

Contractors use the same pricing step from the other direction: a change order request when the contractor believes a change happened, whether from an ASI, a hidden condition such as differing site conditions, or owner direction. Our printable change order request lays out the cost breakdown, markups and schedule impact, and the change order markup calculator does the math.

AIA G714

Construction change directive: do the work, settle the price later

A CCD orders changed work when the owner and contractor haven’t agreed on price, time or both, and the work can’t wait. AIA’s form is G714-2017, Construction Change Directive, governed by A201-2017 Section 7.3. The architect prepares it and the owner and architect sign it. Once the contractor receives it, the contractor must proceed promptly.

The form proposes how the adjustment will be priced: a lump sum, unit prices, or cost plus a fee, matching the methods in Section 7.3.3. The contractor has a signature block too, but signing means it agrees with the proposed adjustment, and that agreement is then recorded as a change order. If the contractor doesn’t agree, it doesn’t sign, the work goes ahead anyway, and the architect determines the adjustment from the contractor’s documented cost plus allowed overhead and profit, subject to the claims process.

CCDs keep a job moving but they put the cost risk on the contractor’s cash. Two habits protect it. First, give CCD work its own cost code and collect signed daily T&M tickets from day one. Second, bill it: A201-2017 Section 7.3.9 lets the contractor request payment for CCD work pending the final number, with the architect making an interim determination for monthly certification. The T&M tickets to a priced change walkthrough shows the ticket side.

AIA G701

Change order: the only document that changes the contract by agreement

A change order is a written instrument, prepared by the architect and signed by the owner, contractor and architect, stating their agreement on the change in the work, the adjustment to the contract sum and the adjustment to the contract time (A201-2017 Section 7.2). AIA’s form is G701-2017, Change Order. It shows the original sum, the net of prior change orders, this change and the new sum, plus the time adjustment and new completion date. On a GMP job it shows the GMP the same way.

Once signed it is final for what it covers, so read any release or reservation language before signing. If the time impact isn’t known, say so on the document rather than writing zero days. After execution, the change order flows into the budget, the subcontract changes and the next pay app; Life of a change order follows one through every one of those, and change events vs change orders explains the records that come before it.

Worked example · illustrative

One RFI, three possible endings

On our sample job, Riverside Medical Center, the mechanical sub finds ductwork at a rated corridor with no fire dampers shown. The GC sends RFI-212. Here is how the same question could end, depending on the answer:

Ending A · ASI

Dampers are already in the spec

The architect replies with an ASI pointing to a specification section the sub missed and a revised detail. No new scope, so no change in sum or time. The GC distributes it, the sub builds it, and the drawing log records the revision.

Ending B · CO

Dampers are new scope

The answer adds dampers that weren’t in the documents. The GC opens a change event, gives notice, prices it with the sub and submits a change order request. Owner, contractor and architect sign a change order for $86,400. That is the path in field question to paid change order.

Ending C · CCD, then CO

Price disputed, ceilings closing

The owner agrees dampers are needed but disputes the price, and ceilings close in ten days. The owner and architect issue a CCD on a cost-plus-fee basis. The GC opens a separate cost code, collects signed T&M tickets daily, bills the work on the interim determination and later signs a change order for the documented cost plus fee.

The leak

An ASI built without notice

Ending A goes wrong when the revised detail adds work nobody priced and the sub builds it anyway. Without written notice before proceeding, the GC is left arguing a constructive change after the fact, which is slower and far less certain.

Riverside Medical Center is a sample project. Figures are illustrative.

Notice

The deadlines that decide who pays

Most money lost on changes is lost on paperwork timing, not on price. Three clocks matter on an AIA job, and your contract may shorten any of them:

  1. Before proceeding with an ASI or field order you disagree with. A201-2017 Section 7.4 says notify the architect and don’t proceed. Many Division 01 sections add a response period in days.
  2. Claims. A201-2017 Section 15.1.3 generally requires a claim to be initiated within 21 days after the event giving rise to it, or after the claimant first recognizes the condition, whichever is later. Supplementary conditions often change this.
  3. Hidden conditions. For concealed or unknown conditions, A201-2017 Section 3.7.4 requires notice before the conditions are disturbed and no later than 14 days after first observing them.

Owner-written contracts and subcontracts are often stricter, and subcontracts flow these deadlines down with a few days taken off so the GC can meet its own. Log the date every notice goes out.

Down the chain

Every owner change has a subcontract twin

Each owner-side change usually needs a matching change on the cost side: a subcontract change order (AIA’s contractor-subcontractor variant is G701S) or a purchase order change, so the commitment, the budget and the sub’s billing stay in line. Changes also run the other way. When a sub causes cost, the GC recovers it with a deductive subcontract change, a back charge; our guide to issuing and disputing back charges and the back charge notice and log template cover that side.

In os.construction

How the chain looks in the app

RFIs are live, with ball in court, due dates and official responses. When an answer changes cost or time, a change event records it with the RFI as its origin and a rough cost by cost code. From there a potential change order prices it against the prime contract or a subcontract; PCO statuses include Pricing, Proceeding and Approved, and an approved PCO or package is executed as the change order. Executed changes post to the budget, the commitment and the pay app without retyping.

There isn’t a dedicated ASI or CCD record yet. Teams file the G710 or G714 in Documents, upload revised sheets as a drawing revision, and track directed work as a PCO marked Proceeding with its T&M tickets. See change order software for the full product page.

FAQ

Common questions

What is an AIA G710?

AIA Document G710, Architect’s Supplemental Instructions, is the AIA’s standard form for an architect to issue additional instructions, interpretations or minor changes in the work during construction. It is issued and signed by the architect and is not meant to change the contract sum or contract time. The current edition is G710-2017, used with the A201-2017 general conditions.

What are architectural supplemental instructions?

Architect’s (often called architectural) supplemental instructions, or ASIs, are written instructions from the architect that clarify the drawings and specifications or make minor changes without changing the contract sum or time. Under AIA A201-2017 Section 7.4 the architect can order minor changes on its own authority. If the contractor believes an ASI changes cost or time, it should notify the architect before proceeding.

What is a field order in construction?

A field order is a written order for a minor change in the work, usually issued by the engineer under EJCDC contracts on its form C-942, without a change in contract price or contract times. It plays the same role as an ASI under AIA contracts. Some owners use “field order” more loosely for any directive written in the field, with price settled later, so read the contract’s definition.

What is the difference between AIA G714 and G701?

A G714 construction change directive orders the contractor to perform changed work before the owner and contractor agree on price or time; the owner and architect sign it and the adjustment is settled later. A G701 change order records an agreed change in the work, the contract sum and the contract time, and is signed by the owner, contractor and architect. A CCD is commonly closed out later by a change order.

Does the contractor have to sign a construction change directive?

No. Under AIA A201-2017 a CCD takes effect when the owner and architect sign it, and the contractor must proceed with the change. The contractor signs only if it agrees with the proposed adjustment in sum and time; if it does, that agreement is recorded as a change order. If it doesn’t agree, the adjustment is determined under the contract’s methods.

Who signs a change order?

Under AIA A201-2017 a change order is a written instrument prepared by the architect and signed by the owner, contractor and architect, stating their agreement on the change in the work, the amount of any adjustment to the contract sum and the extent of any adjustment to the contract time. Other contract families use similar three-party or two-party signatures.

Keep going

Sources and further reading

General information only, not legal advice. Contract terms, notice periods and change procedures vary by contract, owner and jurisdiction.

Want this on live job data?

RFIs, change events, potential change orders and executed change orders are live in os.construction, linked from the origin RFI to the budget and the pay app.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

General information, not legal advice. Your contract, its supplementary conditions and the law where the project sits decide how changes, notices and claims work. AIA and EJCDC documents are copyrighted; get them from the publishers and read the edition your contract uses.