On this page
AIA G710 is the Architect’s Supplemental Instructions form: the architect signs it alone, and it does not change the contract sum or time. G714 is the Construction Change Directive: the owner and architect sign it to order changed work before the price is agreed. G701 is the Change Order: owner, contractor and architect all sign it to record an agreed change in the work, the sum and the time. Pick by asking two questions: does the change move money or time, and has the price been agreed?
All three are current AIA Contract Documents editions built to work with the A201-2017 general conditions: G710-2017, G714-2017 and G701-2017. They are copyrighted, so this post describes what they do rather than reproducing them. Get the forms from AIA Contract Documents and read the edition your contract names.
Who signs what
The fastest way to tell the three forms apart is the signature blocks.
| G710 · ASI | G714 · CCD | G701 · Change order | |
|---|---|---|---|
| Full name | Architect’s Supplemental Instructions | Construction Change Directive | Change Order |
| Prepared by | Architect | Architect | Architect |
| Signed by | Architect only | Owner and architect; contractor if it agrees | Owner, contractor and architect |
| Contract sum or time | No change | Changes; amount settled later | Changes by agreement |
| Contractor must proceed? | Yes, unless it believes sum or time is affected and gives notice | Yes, promptly | Yes, it agreed to it |
| A201-2017 basis | §7.4 minor changes | §7.3 | §7.2 |
| Typical trigger | RFI answer, clarification, small design tweak | Price dispute or no time to negotiate | Priced and accepted proposal |
G710: the architect’s instruction that should cost nothing
An ASI clarifies the documents or orders a minor change that fits the design intent. A201-2017 §7.4 gives the architect that authority on its own, as long as the change doesn’t adjust sum or time. That is why there is no owner or contractor signature block on G710: it doesn’t need anyone’s agreement, because by definition it doesn’t change the deal.
The catch is in the same section. If the contractor thinks a proposed minor change does affect sum or time, it has to notify the architect and not proceed. Build the ASI without that notice and you have, in practice, accepted it as free. On a job with dozens of ASIs, that is where change order money disappears. The ASI glossary entry has an ASI log layout and a worked example.
G714: proceed now, price later
A construction change directive is how the owner keeps the job moving when it and the contractor can’t agree on price or time, or haven’t had time to try. The owner and architect sign it, and once the contractor receives it, the contractor must proceed.
The form states a proposed basis for the adjustment: a lump sum, unit prices, or cost plus a fee, matching the methods in A201-2017 §7.3.3. The contractor has a signature block, and here is the detail people get wrong: signing it means the contractor agrees with that proposed adjustment, and the agreement is then recorded as a change order. If you don’t agree, you don’t sign, you do the work anyway, and the architect determines the adjustment from your documented cost and allowed markup.
Two things protect the contractor on a CCD:
- Cost tracking from the first hour. A separate cost code and signed T&M tickets every day. When the architect sets the adjustment, your records are the evidence.
- Billing while you wait. A201-2017 §7.3.9 lets the contractor request payment for CCD work before the final number is settled, with the architect making an interim determination for monthly certification. Don’t carry the cost on your own balance sheet for months.
G701: the agreed change
A change order is the document that changes the contract by agreement. Under A201-2017 §7.2 it is prepared by the architect and signed by owner, contractor and architect, stating the change in the work, the adjustment to the contract sum and the adjustment to the contract time. G701-2017 shows the arithmetic: the original sum, the net of previous change orders, the sum before this change, this change, and the new sum, with the time change and new completion date. On a GMP job the form tracks the GMP the same way.
Because all three parties sign, a change order is usually final for what it covers. Read any release or reservation language before you sign, and if the time impact is still unknown, say so rather than writing zero days. A CCD you couldn’t agree on at the start often ends as a G701 once the documented cost is in.
The forms people mix up with these three
- G709, Work Changes Proposal Request. The architect asks for a price on a proposed change, often with a bulletin. It authorizes nothing. Your answer is a proposal, usually a potential change order.
- G701S. The contractor-subcontractor variation of the change order, for the cost side of the same change.
- G731, G733 and G741. The construction manager as adviser editions of the change order and CCD (formerly G701CMa and G714CMa), and the design-build change order.
- Field order. Not an AIA form. On EJCDC engineering contracts the engineer issues field orders (C-942) for minor changes, alongside a Work Change Directive (C-940) and Change Order (C-941). See what is a field order in construction.
Worked example: the same RFI, three forms
The mechanical sub sends RFI-212: ductwork crosses a rated corridor and the drawings show no fire dampers.
- If the specs already required dampers and the detail was just missing, the architect answers with a G710 and a revised detail. No change in sum or time, and nobody argues.
- If dampers are new scope, the GC opens a change event, gives notice, prices it with the sub and gets a G701 signed for $86,400. That chain is drawn step by step in field question to paid change order.
- If the owner agrees dampers are needed but disputes the price, and ceilings close in ten days, the owner and architect sign a G714 on a cost-plus-fee basis. The GC tracks cost on its own cost code, bills the work on the architect’s interim determination, and settles it later with a G701.
Mistakes that cost money
- Building an ASI that adds work, without written notice first.
- Signing a G714 to “acknowledge receipt” when you don’t agree with the proposed amount. Your signature is agreement.
- Mixing CCD cost into base-scope cost codes, so the documented cost can’t be separated later.
- Writing zero days on a G701 when the schedule impact isn’t known yet.
- Forgetting the subcontract side: every owner change usually needs a matching subcontract change, or the sub’s next invoice won’t fit its commitment.
For how these forms sit in the whole path from question to paid change, read our guide from RFI to change order: ASI, field order, CCD and CO.
How os.construction handles it
RFIs, change events and change orders are live. A change event records the origin RFI and a rough cost; a potential change order prices it against the prime contract or a subcontract and moves through statuses including Pricing, Proceeding and Approved; executing it posts to the budget and the commitment. There isn’t a dedicated ASI or CCD record yet: teams file the G710 or G714 in Documents and track directed work as a PCO marked Proceeding, with its T&M tickets as backup.
General information, not legal advice. Your contract’s edition, supplementary conditions and the law where the project sits control. Sources: AIA G710-2017, G714-2017, G701-2017, G709-2018, A201-2017 and the AIA G-series form list.
See how changes move from RFI to pay app on one record: change order software.