A construction change directive (CCD) lets the owner order changed work to proceed when the parties have not yet agreed on cost or schedule. Under AIA contracts the standard form is G714. The contractor must perform the work, and the final price is set later, often by unit prices, an agreed lump sum, or actual cost plus markup documented on time and materials tickets.
How a CCD differs from an ASI and a change order, and who signs each, is covered in AIA G710 vs G714 vs G701.
Why it matters
CCDs keep a job moving when a negotiation would otherwise stop it. But they shift pressure onto the contractor’s cash flow: you are spending money on work with no agreed price. Without disciplined cost tracking you can lose the argument when the price is finally settled.
Worked example
Illustrative: had the owner on Riverside Medical Center disputed the price of the fire damper work from RFI-212 but needed it done before ceilings closed, they could issue a CCD. The GC would set up a dedicated cost code, collect signed daily T&M tickets from the mechanical sub, and later convert the documented cost plus contract markup into a change order.
Common mistakes
- Not setting up a separate cost code, so CCD costs blend into base scope.
- Missing daily signatures on T&M tickets.
- Billing CCD work without checking what the contract allows for interim payment on directed work.
How os.construction handles it
A directed change is tracked on a change event and a potential change order, which can sit in Proceeding status while the price is open, with line items by cost code. T&M tickets record the labor, equipment and material spent with a field sign-off; they don’t link to the change event automatically yet, so the approved ticket is the backup when you price the change. See Change events and change orders.
Watch the explainer · 2:00
ASI vs field order vs CCD vs change order
- 0:00Four change documents
- 0:14ASI (AIA G710)
- 0:35Field order (EJCDC)
- 0:53CCD (AIA G714)
- 1:13Change order (AIA G701)
- 1:30Recap
- 1:41One change chain
Read the transcript
Four documents can change what gets built on a job: the ASI, the field order, the construction change directive and the change order. They differ in who issues them, and whether the price or the schedule moves.
An architect's supplemental instruction, or ASI, comes from the architect. On AIA contracts it's form G710. It clarifies the documents or orders a minor change, with no change to the contract sum or time. If you think it does cost money or time, say so in writing before you proceed.
A field order plays the same role on many engineering contracts. Under EJCDC general conditions, the engineer issues it for a minor change with no change in price or times. Some owners use the term loosely, for work directed now and priced later, so read how your contract defines it.
A construction change directive, or CCD, is for real changes when the price isn't agreed yet. The owner and architect sign it, AIA form G714, and the contractor proceeds. The price is settled later, often from documented time and materials, so track that cost on its own code.
A change order is the agreement itself. The owner, contractor and architect sign it, AIA form G701, and it adjusts the contract sum, the contract time, or both. A CCD usually ends up as a change order once the price is settled.
So, ASI and field order: minor, with no price or time change. CCD: do the work now, settle the price later. Change order: the signed change to price or time.
In os.construction, a potential change starts as a change event, linked to the RFI behind it, gathers pricing and T&M tickets, and carries through to a change order on the same project record.
Video page with chaptersMore in Construction concepts explained
