A time and materials (T&M) ticket is a daily field record of the labor hours, materials and equipment used on extra or disputed work, signed the same day by someone with authority on the other side, usually the GC’s superintendent or the owner’s rep. Signed tickets are the backup for pricing that work as a change order or T&M billing.
Free template: the printable T&M ticket template.
In plain English
Illustrative: the GC tells your crew to move a run of conduit that’s in the way of a new beam, and nobody has priced it yet. That afternoon your foreman writes down who worked (two electricians, 6 hours each), what was used (60 feet of conduit, fittings, a lift for half a day) and why, and the GC’s superintendent signs it. Next week the office prices that signed sheet at contract rates, about $1,900 with markup, and it becomes the backup for a change order.
T&M tickets are used when work has to proceed before it can be priced: an owner directive, an unforeseen condition, or a dispute about whether the work is in scope. Instead of a lump-sum quote, the cost is built up from what was actually used, so the ticket has to be accurate, contemporaneous and signed.
What goes on a T&M ticket
- Date, project, ticket number and location (floor, grid, room)
- A description of the work and why it’s extra, with the authorizing reference: construction change directive, RFI, field order or change event
- Each worker’s name, classification and hours, split regular and overtime
- Materials with quantities and units
- Equipment with hours or days
- Photos, if the ticket format allows
- Printed name, signature and date of the person signing for the other party
How it works
- Authorize. Get written direction to proceed on a T&M basis before work starts.
- Record daily. The foreman writes the ticket the same day the work is done.
- Sign. The GC superintendent or owner’s rep signs, confirming the labor, materials and equipment used.
- Price. The office applies contract labor rates, material invoice cost, equipment rates and the contract markup.
- Reconcile. Hours are checked against timecards (and certified payroll on public work); materials against invoices.
- Bill. Priced tickets become backup for a change order, or are billed monthly on a T&M contract.
The T&M tickets to priced change explainer follows one ticket through these steps.
T&M ticket vs daily log vs T&M contract
| T&M ticket | Daily log | T&M contract | |
|---|---|---|---|
| What it is | Record of extra work, for payment | Record of the whole day on site | A contract pricing method |
| Signed by the other party | Yes | No | Yes, once at award |
| Covers | One piece of extra work | Weather, crews, deliveries, events | The whole scope |
| Used as | Change order backup | Project record, claim evidence | Basis for all billing |
A daily log entry that mentions the same extra work is useful corroboration if a ticket is disputed.
Pricing formula
T&M price = (labor hours × labor rate) + materials at cost + (equipment time × equipment rate) + markup
The contract defines the labor rate (bare wages plus labor burden, or agreed billing rates) and the markup percentages, which may differ for labor, materials and equipment.
Worked example
Illustrative: a sheet metal crew spends a day relocating duct to make room for new fire dampers under a construction change directive. The foreman writes the ticket: 2 journeymen × 8 hrs, 1 apprentice × 8 hrs, 40 ft of duct plus fittings, one scissor lift for one day. The GC superintendent signs it that afternoon.
| Line | Calculation | Amount |
|---|---|---|
| Journeymen | 2 × 8 hrs × $95.00 | $1,520.00 |
| Apprentice | 1 × 8 hrs × $62.00 | $496.00 |
| Duct | 40 ft × $14.00 | $560.00 |
| Fittings and hangers | per invoice | $240.00 |
| Scissor lift | 1 day × $310.00 | $310.00 |
| Subtotal | $3,126.00 | |
| Markup | 10% per the subcontract (illustrative) | $312.60 |
| Ticket total | $3,438.60 |
All rates and the markup are illustrative; use the ones in your contract. The ticket total goes into the change order backup with the signed ticket attached. The change order calculator can help with markups.
Why it matters
A signed ticket is evidence; an unsigned one is a negotiation. T&M work often grows an overrun in small, unrecorded pieces, and tickets that arrive weeks later are easy to dispute. For the paying party, tickets are also a cost-control tool: they’re where you catch extra hours and idle equipment before they’re billed. Tickets have to match payroll and receipts, or auditors will challenge them.
Common mistakes
- Writing tickets days later from memory.
- Getting a signature from someone without authority to approve extra work.
- Vague descriptions (“misc. work per super”) that can’t be tied to a cause.
- Ticket hours that don’t match timecards or certified payroll.
- Starting T&M work without written direction, then arguing about whether it’s extra.
- Holding signed tickets until closeout instead of pricing them monthly.
How os.construction handles it
T&M tickets are live: labor, equipment and material lines with quantities, unit costs and cost codes, the field signer’s typed name at submit, and review to Approved. Tickets don’t link to change events automatically yet, so the approved ticket is the backup when you create the change. See how tickets fit an electrical job’s money flow in electrical contractor software. See T&M tickets and Change orders.
Watch the explainer · 2:59
Time and materials contracts explained: rates and NTE
- 0:00Paying for time and materials
- 0:22What's in the billing rate
- 0:42The not-to-exceed cap
- 1:03Daily signed tickets
- 1:25One illustrative invoice
- 1:46Watching the cap
- 2:01T&M versus lump sum and cost-plus
- 2:30T&M tickets in os.construction
Read the transcript
A time and materials contract pays the contractor for the hours actually worked, at agreed hourly billing rates, plus materials and equipment, usually with a markup. It's used when the scope can't be defined well enough to price a lump sum: emergency repairs, service calls, investigative demolition, or early work before the design is done.
The hourly billing rate is usually fully loaded. It covers the worker's wage, labor burden like payroll taxes and insurance, plus overhead and profit. The contract sets a rate for each labor class, like foreman, journeyman and apprentice, along with overtime multipliers, equipment rates and the material markup.
Owners usually cap the total with a not-to-exceed amount. The contractor bills actual hours and materials up to that figure, and must stop or get written approval before going past it. If the work costs less, the owner pays less. Many contracts also require notice when billing reaches a set share of the cap.
Because the owner carries the cost risk, T&M lives or dies on documentation. Each day's work goes on a ticket: the date, location and a clear description, the crew by name and labor class with regular and overtime hours, equipment hours, and materials with quantities. Someone with authority on the other side signs it the same day.
Here's an illustrative three-day emergency repair. Forty-eight journeyman hours at ninety-eight dollars an hour is four thousand seven hundred four dollars. Twenty-six hundred dollars of materials, marked up fifteen percent, is two thousand nine hundred ninety. Add seven hundred fifty dollars of equipment, and the total is eight thousand four hundred forty-four dollars.
Against a ten thousand dollar not-to-exceed, that's eighty-four percent of the cap. If the contract requires notice at eighty percent, the contractor should already have told the owner on day three. Work past the cap without written authorization may simply not be paid.
How does T&M compare? In a lump sum, the contractor carries the cost risk for a fixed price. In cost-plus, the owner reimburses actual cost and pays a separate fee. In T&M, profit sits inside the hourly rates and the markup, and the owner carries the cost risk up to the cap. On federal work, FAR Part sixteen allows T&M only when the work can't be estimated with reasonable confidence, and requires a ceiling price.
In os.construction, crews record T&M tickets the day the work happens, with labor, equipment and material lines on cost codes and a field sign-off name. Tickets go through review to approved. And a prime contract set to time and material billing can price the period's tickets, with markups and the cap, into a draft invoice. General information; your contract sets the rates.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a T&M ticket in construction?
A time and materials ticket is a daily record of extra or disputed work: the workers and hours, materials and equipment used, the location and a description of what was done. It is written the day the work happens and signed by someone with authority on the other side, usually the GC's superintendent or the owner's rep, and becomes backup for payment.
Does signing a T&M ticket mean the work is approved for payment?
Usually it confirms only that the listed labor, materials and equipment were used on the described work. Whether the work is extra to the contract, and at what rates, is often decided later through a change order. Many tickets say this explicitly. Check the contract and the ticket wording, and don't treat a signature as a priced change.
What should be on a time and material ticket?
Date, project, ticket number, location, a clear description of the work and why it is extra, each worker's name, trade classification and hours (regular and overtime), materials with quantities, equipment with hours, a reference to the directive, RFI or change event that authorized it, and the printed name, signature and date of the person signing.
How are T&M tickets priced?
Labor hours are multiplied by the contract's labor rates, which may be bare wages plus burden or agreed billing rates, materials are priced at invoice cost, and equipment at agreed rental rates. The contract's markup for overhead and profit is then applied. The priced tickets become the backup for a change order or a monthly T&M billing.
How long do you have to submit T&M tickets?
The contract or subcontract sets it, and many require tickets daily or within a short window, with the priced change submitted within a set number of days. Late tickets are easy to reject and hard to prove, so the safest practice is to write and sign the ticket the same day the work happens.
Is there a free T&M ticket template?
Yes. The os.construction T&M ticket template is a printable daily ticket with the fields that usually decide whether a ticket gets paid: authorizing reference, location, description, crew by name and class with regular and overtime hours, materials, equipment, and a signature block for the other party. Whatever form you use, check it against your contract's requirements before the first ticket is written.