A daily log, or daily report, is the official day-by-day record of what happened on a jobsite. A good one lists weather, crew counts by company, work performed by area, equipment on site, deliveries, inspections, safety events, visitors, delays and any conditions that differ from the documents, usually with photos. The superintendent normally keeps it, and it is written on the day, by someone who was there.
What to record
| Section | What good looks like |
|---|---|
| Weather and site conditions | Temperature, precipitation, wind, and the effect on work (“ground too wet to excavate north pad”) |
| Manpower | Each company on site, headcount and hours, by trade |
| Work performed | What was done, by whom, where (level, grid, area), and quantities where they matter |
| Equipment | What was on site, what was working, what sat idle and why |
| Deliveries | What arrived, from whom, any damage or shortage |
| Inspections and tests | Who inspected what, and the result |
| Visitors and meetings | Owner, architect, inspectors, utility crews |
| Safety | Observations, incidents, near misses, toolbox talks |
| Delays and issues | What stopped or slowed work, the cause, who was told |
| Instructions and changes | Direction received in the field, by whom, and whether it was in writing |
| Photos | Dated and tied to the entries they support |
The test for each entry: would someone who wasn’t on site understand what happened, where and why, a year from now?
How it works
- Capture during the day. Notes, photos and headcounts as things happen, not reconstructed on Friday.
- Collect sub input. Foremen report crews, hours and progress, either directly or through their own daily reports.
- Write it up the same day. The superintendent completes the log before leaving site.
- Flag what needs action. A differing condition becomes an RFI. Extra work becomes a T&M ticket or a change event. A delay becomes a notice, if the contract requires one.
- Share and file it. The PM, the project engineer and, where the contract requires, the owner receive it. It becomes part of the project record.
Worked example
Illustrative, on Riverside Medical Center (sample data). The superintendent’s log for the day reads:
Level 3, grid C/4: rated wall framed, duct penetrations installed, no fire dampers shown or on site. Photos 14–17 attached. Mechanical foreman notified. RFI to be issued.
That single entry dates the discovery, names the location, identifies who was told, and points to photos. It supports RFI-212, the change event and eventually CO #14 at $86,400.
The same day’s manpower section can feed production tracking. Suppose the framing sub logs 6 carpenters for 8 hours, 48 labor hours, and the work section records 1,200 square feet of wall framed. That is 25 square feet per labor hour. If the estimate assumed 30, the framing cost code is trending about 20% over on labor hours, and the PM can see it weeks before the sub’s invoice or the payroll report shows it.
Why it matters
When there is a dispute, the daily log is often the best evidence anyone has. Records made at the time generally carry more weight than reconstructions made later.
- Change orders. A log entry that dates a discovery and names who was told supports the change and the notice.
- Delay claims. Weather, idle crews and late information recorded day by day are the raw material of a delay claim or a defense to one. Weather entries can be compared with any weather allowance in the contract.
- T&M and back charges. Crew counts and hours corroborate time and materials tickets and back charges.
- Schedule updates. Actual starts and finishes for the monthly update come from the logs, statused to the data date.
- Safety and insurance. Incident and observation entries support investigations and claims.
- Job cost. Crew hours against work in place show whether a cost code is trending over long before the invoice arrives.
Common mistakes
- Copy-pasting yesterday’s log, so entries stop meaning anything and the one that matters is buried.
- Recording “no issues” on a day a crew stood around waiting.
- Logging by memory at the end of the week instead of daily.
- Vague locations, such as “worked on 3rd floor”, that can’t be tied to a drawing.
- Opinions instead of facts. “Electrician is incompetent” helps nobody. “Electrical crew of 2 arrived 10:30; scheduled 7:00” does.
- Photos with no context, undated or not tied to an entry.
- Never reading them. Logs that nobody in the office reviews miss the early warnings they contain.
For more, read why daily logs are financial documents and daily reports that hold up, or start from the daily log checklist template.
For a section-by-section guide and a complete sample report, see how to write a daily construction report.
The safety section usually records the morning toolbox talk; how to run a toolbox talk covers running one and keeping the sign-in.
How os.construction handles it
The daily log is live in a phone or desktop browser: one page per day by log type, copy from previous day, complete and reopen a day, and export to PDF or CSV. Offline capture is planned. See Daily log.
FAQ
What is a daily log in construction?
A daily log, also called a daily report or site diary, is the dated record of what happened on a jobsite each day: weather, crews and headcount by company, work performed and where, equipment, deliveries, inspections, visitors, safety events, delays and problems. It is usually kept by the superintendent and is one of the project's main records.
What should be included in a construction daily report?
At minimum: date, weather and site conditions, each company on site with headcount and hours, work performed by area, equipment in use or idle, deliveries, inspections and results, visitors, safety observations or incidents, delays and their causes, instructions received, conditions that differ from the documents, and photos tied to the entries.
Who is responsible for the daily log?
On most projects the general contractor's superintendent keeps the daily log, with input from foremen and subcontractors. Many subcontracts also require subs to submit their own daily reports. The contract may set the format and how often logs must be delivered to the owner.
Why are daily logs important in a dispute?
They are contemporaneous: written on the day by someone who was there. Records made at the time generally carry more weight than reconstructions made later, so a specific, dated log entry can support or undermine a change order, a delay claim, a back charge or an insurance claim.
What is a daily log called in the UK?
UK sites usually say site diary or daily site report. Canadian projects typically use daily report or superintendent's daily report. The content is the same.