Project management

Request for Information (RFI)

Definition

A formal written question from the contractor to the design team asking them to clarify, fill a gap in, or resolve a conflict in the contract documents.

Part of: From RFI to change order: ASI, field order, CCD and CO

Topic: Changes & claims · Field operations

Updated

RFI lifecycle and ball in courtThree swimlanes: field, general contractor and design team. The field finds a question; the GC reviews and submits the RFI, and the ball moves to the design team, which answers by the due date. The GC distributes the official answer, the field builds to it, and if the answer changes scope the GC opens a change event that becomes a change order.FIELDGCDESIGN TEAMQuestionSubmitAnswerdue dateDistributeBuild itScopechanged?changeevent → COball: GCball: design
Ball in court moves with each hand-off. Track the due date while the design team holds it, and open a change event when the answer adds scope.

A request for information (RFI) is a formal, numbered question a contractor sends to the architect or engineer when the drawings or specifications are unclear, incomplete or in conflict. The design team’s written answer becomes part of the project record. RFIs are tracked on a log with ball in court, due dates and any cost or schedule impact.

Free template: the RFI writing checklist covers the fields an RFI needs and a sample question.

In plain English

Illustrative: the floor plan shows a door 3 feet wide, but the door schedule says 3 feet 6 inches, and the framer needs to know which before building the opening. Instead of guessing, the contractor sends the architect RFI-047: “Sheet A-201 shows door 112 at 3’-0”; door schedule A-601 says 3’-6”. Which governs? Proposed: 3’-6” per the schedule. Needed by Tuesday.” The architect answers “3’-6”” in writing two days later, and everyone builds to the same answer.

RFIs usually flow from the field to the general contractor, which reviews and forwards them to the architect; the architect answers or routes them to the right consultant. Good RFIs are specific, reference the sheet and spec section, include a photo or sketch and propose a solution. Many owners also use RFI counts and response times as a measure of drawing quality.

How the RFI process works

  1. Identify the question. A superintendent, foreman or sub finds a conflict, gap or ambiguity in the documents.
  2. Draft the RFI. Question, drawing and spec references, photos, a proposed solution, the date an answer is needed, and whether cost or schedule may be affected. Ball in court: the GC.
  3. GC review. The PM checks that the answer isn’t already in the documents, then numbers and submits it. Ball in court moves to the design team.
  4. Design team response. The architect or engineer answers in writing, sometimes with a sketch or a supplemental instruction such as an ASI.
  5. Distribute. The GC sends the official answer to every affected trade and updates the drawings (and later the as-builts).
  6. Assess impact. If the answer changes scope or time, open a change event, then a potential change order.
  7. Close. The RFI is closed once the answer is accepted and distributed.

The RFI response time and ball in court explainer shows the hand-offs in more detail, and field question to paid change order follows an RFI all the way to billing.

RFI vs submittal vs change order

RFI Submittal Change order
Purpose Clarify design intent Show how specs will be met Change contract scope, price or time
Starts with Contractor Contractor (often a sub) Either party; signed by owner and contractor
Answered by Architect or engineer Architect or engineer review Owner approval
Changes the contract No, by itself No Yes

Response time formula

  • Days to answer = date answered − date submitted (calendar or working days, per the contract).
  • Days overdue = today − due date, for open RFIs past due.
  • Average response time = total days to answer ÷ RFIs answered.

Illustrative: five RFIs answered in 3, 6, 8, 12 and 16 working days. Average = 45 ÷ 5 = 9.0 days; median = 8. If the contract allows 10 working days, two of five (40%) were late, and those two are the ones to document for schedule impact. Try the RFI response time calculator.

Worked example

Illustrative: on a medical office project, the superintendent finds that the mechanical drawings show duct penetrations through a rated wall with no fire dampers. The PM issues RFI-212: “Confirm fire damper requirement at rated wall, grid C/4. Proposed: provide 1.5-hour dynamic dampers per spec 23 33 00. Answer needed by Friday to hold ceiling close-in.” The engineer confirms dampers are required. Because that work isn’t in the contract, RFI-212 opens a change event and is later priced as CO #14 at $86,400. The project has 23 open RFIs, 4 overdue, which the PM reviews with the architect at the weekly OAC meeting.

Why it matters

RFIs are where cost and schedule risk first show up. A slow answer can stall a crew. An answer that changes scope is the start of a change order. Unanswered or late RFIs are also evidence in delay claims, so the dates matter as much as the content. A high RFI count on a trade or a set of sheets is an early signal of coordination problems.

Common mistakes

  • Asking vague questions without a proposed solution, drawing reference or photo.
  • Asking questions the documents already answer, which erodes the design team’s goodwill.
  • Bundling several unrelated questions into one RFI, so the easy answer waits for the hard one.
  • Not tracking the response time the contract requires, then losing the delay argument.
  • Treating an RFI answer that adds scope as “free” instead of opening a change event.
  • Distributing the answer to the asking trade only, so other trades build to the old detail.

For a step-by-step guide with a before-and-after example, see how to write an RFI that gets answered.

How os.construction handles it

RFIs are live. Each RFI has an RFI manager, assignees and a distribution list, and the log shows status, ball in court, assignees and due date, with filters for ball in court, cost code and overdue only. A due date turns red with “(overdue)” when an open or draft RFI is past it. Schedule and cost impact are recorded in days or dollars, the answer that settles it can be marked official, and RFIs link to the drawings, submittals and change events they touch. A change event can name the RFI as its origin so the cost side stays linked to the question. See RFIs and Change orders.

FAQ

What is an RFI in construction?

An RFI, or request for information, is a formal written question a contractor sends to the architect or engineer when the drawings or specifications are unclear, incomplete or in conflict. Each RFI is numbered and logged, has a due date, and the design team's written answer becomes part of the project record that tells the field how to build.

Who answers an RFI?

Usually the architect, who answers directly or routes the question to the right consultant, such as the structural or MEP engineer. Subcontractors normally submit RFIs through the general contractor rather than to the design team directly, and the owner may be copied or asked to decide questions that affect cost or program.

How long should an RFI response take?

The contract or project procedures usually set the response time, often a number of working days from receipt, with a faster path for urgent field questions. There is no universal standard. Whatever the period, tracking the date sent, date answered and days overdue matters, because late answers can support schedule extensions and delay claims.

What is the difference between an RFI and a submittal?

An RFI asks a question about the design intent. A submittal sends product data, shop drawings or samples to show how the contractor will meet the specifications, for the design team's review. Both are logged with ball in court and due dates, but an RFI answer clarifies the documents while a submittal review approves what will be installed.

Can an RFI change the contract price?

An RFI answer is not a change order by itself. If the answer adds work, changes scope or affects time, the contractor should promptly open a change event or notice of change under the contract's procedures, price it and get a change order. Treating a scope-changing answer as free is a common way to lose money.

Is a construction RFI the same as an RFI in procurement?

No. In procurement, a request for information is an early step before a request for proposal: a buyer asks vendors to describe their capabilities. In construction, an RFI is a question during design or construction about the contract documents, sent to the architect or engineer. Same three words, different job. Bid-phase questions about the documents are often called pre-bid RFIs and answered by addendum.

What should an RFI template include?

A number, date, project, who is asking and who must answer, the drawing sheet and spec section, the question stated so it can be answered in one reply, a photo or sketch, a proposed solution, the date an answer is needed and why, and fields for possible cost and schedule impact. The response block needs the answer, who gave it and the date.

Sources

See it in the app

Request for Information (RFI) in os.construction

Draft an RFI, open it to the people who owe the answer, and mark the response that settles it as official. Read the guide: RFIs.

  1. 1Draft
  2. 2Open to assignees
  3. 3Response
  4. 4Closed

Watch the walkthrough · 1:57

Create a draft RFI and open it

  1. 0:00Start a new request for information
  2. 0:27Give the RFI a clear subject
  3. 0:59Write the question
  4. 1:15Save the draft
  5. 1:28Review the saved question
  6. 1:43Open the RFI
Read the transcript

Here we are in the actual os.construction app, using a local sample project. On the New RFI page, we can prepare a question and save it as a draft before opening it.

Use a subject that tells the reviewer what needs clarification. In this example, we are asking about the corridor fire damper detail. The demo adds a unique reference so each recording creates a separate sample record.

State the decision the team needs. Our question asks the reviewer to confirm the required fire damper detail before installation and identify which detail the field team should follow.

Select Create as Draft. The app saves the RFI and opens its detail page. We will check that the Open RFI action is available before moving forward.

The saved record now has its own detail page. Review the subject and question here. A draft gives the team a chance to check the request before opening it.

Select Open RFI. Wait for the Open RFI action to disappear after the update. Close RFI remains available. We have written a request, saved it as a draft, reviewed it, and moved it into the open workflow.

The New RFI form with a subject and a question asking which fire damper detail to follow.
Writing an RFI in the app. Sample data.

Try it on the sample project in a free trial.