A day as a project manager

Seven stops between coffee and the drive home, on the Riverside Medical Center sample job. The point isn't the tools. It's that the RFI, the meeting, the task and the change event are the same linked records all day.

Workflow explainer7 min readSample data · Riverside Medical Center

The day at a glance

Seven stops, three stored links

Times are illustrative. The arcs are links the app stores between records, so a task knows the RFI or meeting topic it came from, and the change event knows its RFI.

Day map: project desktop at 7:00, RFIs at 7:45, submittals at 9:30, daily log at 11:00, OAC meeting at 14:00, tasks at 15:30 and a change event at 16:30. A task is created from the RFI, a task from a meeting topic, and the change event names RFI-212 as its origin.Create taskTask from topicOrigin RFI7:00Project desktop7:45RFIs9:30Submittals11:00Daily log14:00OAC meeting15:30Tasks16:30Change event

The day, stop by stop

7:00 · Project desktop

Start from what's waiting on you

Desktop in the dock is the project home, a board of widgets that sum up the job: revised contract, committed cost, billed to date, margin, My open items with how many are late, open field items by tool, today's daily log and the activity feed. The bell holds assignments, mentions and status changes. Each widget only shows numbers from tools you're allowed to see.

On Riverside this morning: 23 open RFIs, 4 of them overdue (sample data).

Find your way around the app

7:45 · RFIs

An answer lands on RFI-212

The architect's official response is on the RFI: dampers are required. The response sits with the question, ball in court and due date, so nobody has to dig through email for it. Two things start here. Create task opens a follow-up already linked to the RFI. And a change event can name the RFI as its origin, which is where the money side begins.

An RFI record in os.construction with an official response, ball in court, due date and a Related Items panel.
An answered RFI with its official response. Recorded in the app · sample data

Watch the walkthrough · 1:57

Create a draft RFI and open it

  1. 0:00Start a new request for information
  2. 0:27Give the RFI a clear subject
  3. 0:59Write the question
  4. 1:15Save the draft
  5. 1:28Review the saved question
  6. 1:43Open the RFI
Read the transcript

Here we are in the actual os.construction app, using a local sample project. On the New RFI page, we can prepare a question and save it as a draft before opening it.

Use a subject that tells the reviewer what needs clarification. In this example, we are asking about the corridor fire damper detail. The demo adds a unique reference so each recording creates a separate sample record.

State the decision the team needs. Our question asks the reviewer to confirm the required fire damper detail before installation and identify which detail the field team should follow.

Select Create as Draft. The app saves the RFI and opens its detail page. We will check that the Open RFI action is available before moving forward.

The saved record now has its own detail page. Review the subject and question here. A draft gives the team a chance to check the request before opening it.

Select Open RFI. Wait for the Open RFI action to disappear after the update. Close RFI remains available. We have written a request, saved it as a draft, reviewed it, and moved it into the open workflow.

9:30 · Submittals

Log what's due before it's late

Storefront glazing product data is due from the glazing sub. The submittal is created against its spec section, with a type, a responsible contractor and a submittal manager. The submittal log shows each one's status, ball in court and due date, so what's late is visible before it holds up the work.

A submittal record with its spec section, submittal type, responsible contractor and submittal manager.
A submittal tied to its spec section and responsible contractor. Recorded in the app · sample data

11:00 · Daily log

Read the site from the office

The super's daily log is one page per day: weather, manpower by company with cost code and location, notes, deliveries, delays and the rest. Because manpower and quantities carry the job's own cost codes, the field record and the budget speak the same language. Once the day is complete, its entries are locked until someone reopens it.

A sample note visible in the daily log's Notes table.
A note in the day's daily log. Recorded in the app · sample data

Watch the walkthrough · 2:18

Add a note to the daily log

  1. 0:00Confirm the project and day
  2. 0:19Find the Notes section
  3. 0:52Write the field observation
  4. 1:14Save and inspect the entry
  5. 1:32Move to the previous day
  6. 1:48Return to the day
  7. 2:04Read the saved observation again
Read the transcript

Start with the project and date. We are in the local sample project's Daily Log, which opens on today. A useful field note tells the next reader what happened, where, and what needs attention next.

Scroll to Notes. This section has its own entry form. Keep an observation specific enough that another team member can understand the location, the time, and the next check without asking you to reconstruct the day.

Our invented example records an access check at the east corridor, the time, and a follow-up before the delivery. The unique demo reference distinguishes this sample note from other recordings. Replace the example with facts you actually observed on your project.

Select Create in the Notes form. Wait for the new row to appear, then read the saved comment. Checking the row confirms the submitted text reached the day's log instead of remaining only in the form.

Use Previous Day to leave this day's view. Each day has its own log. The Today link lets us return to the day where we created the note and check that the saved entry is still there.

Select Today to return to the day where we created the note. Check the displayed date, then return to Notes to find the saved observation.

Here is the same note in the Notes table after returning to the day. Read the time, location, observation, and next check. We have saved a specific field note and confirmed that another reader can find its context again.

14:00 · Meetings

Run the OAC meeting from the record

The weekly OAC meeting is part of a recurring series. Agenda topics have a category, a priority, a due date and an assignee, and open topics carry forward to next week. On a topic, Create task turns a decision into a follow-up that remembers which meeting and topic it came from.

A meeting record in Agenda status with an overview, attachments, an Add Topic form and a Convert to Minutes button.
A weekly OAC meeting, ready for agenda topics. Recorded in the app · sample data

15:30 · Tasks

Move follow-ups to closed

The tasks from the morning's RFI and the afternoon's meeting land on one list with an owner, a due date and a status, on a list or a board. A comment says what happened and what's next; assignees and the creator are notified.

Sample progress comment saved in the task's Comments section, naming the next check.
A progress comment on a task, naming the next check. Recorded in the app · sample data

Watch the walkthrough · 2:33

Create a task and post a progress update

  1. 0:00Start a project task
  2. 0:22Name the follow-up clearly
  3. 0:49Describe what the follow-up needs
  4. 1:09Save the task and inspect its detail page
  5. 1:25Move the sample task into progress
  6. 1:49Write a useful progress comment
  7. 2:05Save the update
  8. 2:18Review the saved progress context
Read the transcript

Open Create Task in the sample project. A useful task names a specific follow-up and gives the next reader enough context to understand what needs to happen. We will save this example, change its status, and add an update.

Give the task an action-oriented title. Confirm delivery window tells the reader what needs attention. The unique demo reference distinguishes this sample record from other recordings.

Use Description to explain the expected result. Our invented example asks for the delivery window, the agreed time, and access instructions. Review the task's other fields before saving. This recording leaves assignees and distribution empty.

Select Create and wait for the task detail page. Confirm the title and description. The saved record now has a task number and a current status that the project team can use to track the follow-up.

For this sample, select In Progress. Check the current status in the task header after the update. A status change records the stage of the task; the delivery window itself still needs confirmation.

Add a comment that explains the next check. Our sample update says that the delivery window needs confirmation and identifies who to check with. This gives the reader more context than the status alone.

Select Add Comment. Wait for the text to appear in the saved comment list. Read the saved update so you can confirm the task contains the information you intended to leave.

Here is the saved update on the task. We have created a specific follow-up, moved its status into progress, and recorded the next check. Keep updating the record as the work changes so another reader can understand what remains.

16:30 · Change events

Put the exposure on the record today

Before leaving, the PM opens a change event with RFI-212 as its origin and a rough line by cost code, so the exposure is on the record the day it's known. The RFI lists the change event; the change event shows its whole chain to PCOs, change orders and the budget.

A change event record showing a chain strip of change event, RFQs, PCOs, change orders and budget change, with a cost line item.
A new change event with its chain strip. Recorded in the app · sample data

Follow it to a paid change order

What the day didn't need

No re-keying between tools

  • The task didn't need the RFI number typed into its title. It's linked.
  • The change event didn't need a note saying "see RFI-212". It names its origin.
  • The meeting's decision didn't live in minutes only. It's a task with an owner.

Company Accounting covers the ledger, AP, AR and payroll. AI agents that prepare this kind of work remain planned. See how agents will work.

Keep going

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

RFIs, submittals, daily logs, meetings, tasks and change events are live. Company Accounting covers the books; AI agents remain planned.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are illustrative sample data, not a real project. Contract terms and state law decide how retainage, stored materials and change orders work on your job. Check both.