As-built drawings (as-builts) are drawings marked up to show how a project was actually built: where pipes, conduits, ducts, valves, utilities and structural elements ended up after RFIs, change orders and field adjustments. Trades keep redline sets during construction, and the GC compiles them into the as-builts delivered at closeout for the owner’s use.
In plain English
Illustrative: the plumbing drawings show a 4-inch sanitary line running straight down the corridor. In the field it had to jog 3 feet east to clear a footing, and an RFI also added a cleanout. The plumber redlines both on the field set that week, with the RFI number. At closeout the GC hands the owner a set where that line is drawn where it really is. Five years later, a tenant buildout cores the slab in the right place instead of hitting the pipe.
Owners operate and renovate buildings using these drawings for decades. Facility teams use them to find shutoff valves, plan tenant improvements and avoid cutting live conduit. Civil and utility as-builts matter even beyond the building: they inform locates, future excavation and connections to the public network.
As-builts vs record drawings vs shop drawings
| As-builts (redlines) | Record drawings | Shop drawings | |
|---|---|---|---|
| Who makes them | Contractor and trades, in the field | Often the architect or engineer, from the as-builts | Subcontractor or fabricator |
| When | Continuously during construction | At or after closeout | Before fabrication, as submittals |
| Shows | What was actually installed | A clean, consolidated set of the final condition | How a component will be built and installed |
| Format | Marked-up paper or PDF sheets | CAD, PDF or a model | PDF or CAD |
The terms are used loosely. Some contracts treat “as-built” and “record” as the same deliverable, so the specification (usually Division 01 closeout) is what decides. See submittal for where shop drawings fit.
Types of as-built drawings
- Redline (field) as-builts: the marked-up contract sheets trades keep during the job. Raw, but the primary evidence.
- Trade as-builts: each discipline’s installed condition, such as mechanical, electrical, plumbing and fire protection, often drawn over the trade’s coordination or shop drawings.
- Civil and utility as-builts: horizontal location and depth of underground lines, structures and grades, often surveyed and tied to coordinates. Many public owners and utilities have their own format requirements.
- Record drawings: the clean, consolidated set, usually prepared by the design team from the redlines.
- As-built models: where the contract requires BIM, the model updated to reflect what was installed, sometimes checked against laser scans.
How it works
- Set up the redline set. Issue a dedicated field set per trade at the start of the job, and agree the color and notation convention.
- Mark changes as they happen. Every RFI answer, ASI, change order and field relocation is drawn on the sheet the week it happens, with the reference number.
- Capture what will be hidden. Before walls close or trenches are backfilled, record location, depth and material, ideally dimensioned from fixed points or survey coordinates, with photos.
- Review monthly. Many owners make current redlines a condition of the monthly pay application. The superintendent spot-checks them against the field.
- Compile at closeout. The GC collects all trade sets, checks them against the RFI and change order logs, and transmits them.
- Produce record drawings. Where required, the design team incorporates the markups into a clean record set. The owner files it with the O&M manuals.
Why as-builts for utilities go wrong
Inaccurate underground as-builts are a known problem for owners and excavators. The usual causes:
- Recorded from memory. The trench is backfilled before anyone measures.
- No fixed reference. Offsets are taken from a fence or curb that later moves.
- Depth missing. Plan location only, so a later excavator still can’t trust it.
- Abandoned lines left off. Dead lines look like live ones on a locate.
- Later repairs never added. A relocation during a repair years later never reaches the drawings.
As-builts don’t replace a locate request. Anyone excavating should still call 811 (in the US) before digging. Good as-builts make those locates, and future design, faster and safer.
Worked example
Illustrative: on a medical office project, an RFI answer adds fire dampers at a rated corridor wall, and a change order prices them. To make room, the sheet metal crew relocates a 24-inch duct 18 inches north. The mechanical as-builts must show the dampers, their access panels and the relocated duct, each tagged with the RFI and change order numbers. Outside, the site contractor reroutes a domestic water line around an unmapped footing; the foreman records the new alignment with offsets from the building grid and a depth of 4 feet before backfill. Ten years later, the owner’s facility team inspects dampers and plans a parking lot expansion from those sheets.
Why it matters
Wrong as-builts mean cut pipes, surprise conduits and expensive investigation later. They are also a common closeout requirement, so incomplete as-builts can hold up final payment and retainage release. The closeout and turnover explainer walks through where they fit with O&M manuals, warranties and the punch list.
Common mistakes
- Leaving redlines until the end of the job, when nobody remembers the changes.
- Not incorporating RFI answers, ASIs and change orders into the drawings.
- Recording underground work without depth or fixed reference points.
- Delivering as-builts in a format the owner can’t use, or without an index.
- Assuming the design team’s record set captures field changes nobody redlined.
How os.construction handles it
The Drawings tool (live) keeps the current sheet set and every revision behind it: uploading a revision makes it current while earlier ones are kept, you can compare any earlier revision with the current one, and you can mark up sheets on personal or published layers. An RFI can be linked to the exact revision it concerns, and a released revision can be distributed to chosen recipients with a record of who received it. RFIs link to the drawings, submittals and change events they touch, so the changes that should reach the as-builts can be traced from the project record. There is no dedicated as-built or record drawing workflow today, and closeout requirement tracking is planned. See Documents and drawings and Closeout and retainage release.
Watch the explainer · 2:56
As-built drawings explained: redlines to record set
- 0:00What as-builts are
- 0:19Redlines, as-builts and record drawings
- 0:44Where the changes come from
- 1:05Capture it before it's covered
- 1:26An illustrative example
- 1:49Why utility as-builts go wrong
- 2:12Closeout and final payment
- 2:33Drawings in os.construction
Read the transcript
As-built drawings, often just called as-builts, show a building as it was actually constructed, not as it was designed. Every moved duct, rerouted pipe and field change ends up on them, and the owner relies on them for decades to operate, maintain and renovate the facility.
The terms get used loosely. Commonly, the trades mark up a field set in red as work happens: those are the redlines. The general contractor compiles them into the as-built set. Record drawings are often the clean set the architect or engineer prepares from those markups at closeout. Your specifications, usually Division 01, decide what is actually owed.
Changes reach the drawings from many places. An RFI answer adds a fire damper. An architect's supplemental instruction revises a detail. A change order adds scope. And sometimes the crew simply relocates a duct to clear a beam. Each one should be drawn on the sheet the week it happens, tagged with its reference number.
Underground and in-wall work is the hardest part, because it gets covered fast. Before a trench is backfilled or a wall is closed, record the location, the depth and the material, measured from fixed points such as the building grid or survey coordinates, and take photos. Offsets taken from a fence or a curb can drift when those move.
Here's an illustrative example. On a medical office job, the sheet metal crew moves a twenty-four inch duct eighteen inches north to make room for new fire dampers. Outside, the site contractor reroutes a water line around an unmapped footing, four feet deep. Both changes go on the redlines, tagged with the RFI and change order numbers, before anything is covered.
Utility as-builts are often wrong, for predictable reasons. They were drawn from memory after backfill. They show plan location but no depth. Abandoned lines were left off, so dead lines look live. And later repairs never made it onto the drawings. As-builts also never replace a locate: in the U.S., call eight-one-one before you dig.
As-builts are a common closeout deliverable, and many specifications list them among the items required before final payment or retainage release. Some owners make current redlines a condition of each monthly pay application. Keeping them current every month is far cheaper than reconstructing a year of changes at the end.
In os.construction, the Drawings tool keeps the current sheet set and every revision behind it, with markups on personal or published layers, and RFIs linked to the exact revision they concern. That keeps the changes that belong on the as-builts traceable from the project record.
Video page with chaptersMore in Construction concepts explained
FAQ
What does as-built drawings mean?
As-built drawings show a building or site as it was actually constructed, not as it was designed. They capture every field change, RFI answer, change order and relocation, such as a duct moved to clear a beam or a water line rerouted around a rock outcrop. They are delivered at closeout so the owner can operate, maintain and renovate the facility.
What is the difference between as-builts and record drawings?
Usage varies, but commonly the contractor's marked-up set showing field changes is the as-built or redline set, and record drawings are the clean set the architect or engineer prepares from those markups at closeout. Some contracts use the terms interchangeably, so check the specifications, usually Division 01 closeout requirements, for what is actually owed.
Who is responsible for as-built drawings?
The contract decides. Under common general conditions the contractor keeps a current marked set at the site showing field changes, and each trade redlines its own work. The GC collects and delivers them. The design team may then produce record drawings. Utility and civil as-builts are sometimes surveyed by a licensed surveyor.
Why are utility as-builts often outdated or inaccurate?
Underground work is covered up quickly, so locations recorded from memory days later drift. Common causes are redlines made at the end of the job, measurements without fixed reference points or coordinates, depth not recorded, abandoned lines not shown, and later repairs never added. Recording location, depth and material when the trench is still open is the fix.
Do as-built drawings hold up final payment?
Often. Many specifications list as-builts or record drawing markups among closeout submittals required before final payment or retainage release. If the owner or architect will not accept the set as complete, the final pay application can stall, which is why tracking redlines monthly is cheaper than reconstructing them at the end.
Is it as-built or as-build?
As-built. The term describes the project as it was built, past tense, so "as-built drawings" or "as-builts" is the standard spelling in specifications and contracts. "As-build" is a common typo. You will also see "as-constructed" in civil and UK usage and "record drawings" for the clean set prepared at closeout.
What counts as as-built documentation besides drawings?
Depending on the specifications: survey data with coordinates and elevations for underground utilities, an updated model where the project uses BIM, photos of work before it was concealed, the final RFI, ASI and change order logs the drawings reference, equipment schedules with installed makes and model numbers, and test and inspection reports. Division 01 closeout sections list what is actually owed.
