Technology

Building Information Modeling (BIM)

Definition

A process of creating and managing a shared 3D model of a building that carries data about its parts, not just geometry.

Topic: Field operations · Technology & data

Updated

Building information modeling (BIM) is the practice of designing, coordinating and managing a building through a shared, data-rich digital model. Each element, such as a duct, a beam or a fire damper, is an object with properties like size, system, material, manufacturer and location. Teams use the model for design, clash detection, quantity takeoffs, sequencing (4D) and cost (5D), and hand it to the owner for operations.

The National BIM Standard-United States describes a building information model as a digital representation of the physical and functional characteristics of a facility. The modeling is the process; the model is the product.

How it works

  1. Plan it. A BIM execution plan sets who models what, in which software, to what level of development, how files are exchanged, and what the owner receives at the end.
  2. Model by discipline. Architects, structural engineers and MEP engineers each build their own model. On many projects, trade contractors then build fabrication-level models of their own work.
  3. Federate and coordinate. The models are combined into one federated model. Clash detection checks for hard clashes (physical overlaps) and clearance clashes (not enough room for access, insulation or code clearances). The team groups the results and resolves the real ones in coordination meetings.
  4. Use the data. Quantities feed takeoffs and budgets. Linking elements to schedule activities gives a 4D sequence. Linking them to cost gives 5D.
  5. Build from it. Coordinated models drive shop drawings, prefabrication and field layout.
  6. Hand it over. The owner receives an as-built model and structured asset data, often in COBie format, alongside as-built drawings and O&M manuals.

Models are exchanged in native formats or through IFC (Industry Foundation Classes), the open standard maintained by buildingSMART and published as ISO 16739.

Level of development (LOD)

LOD What the element represents
100 Conceptual: a symbol or mass showing something exists
200 Generic system with approximate size, shape and location
300 Specific element with accurate size, shape, location and orientation
350 LOD 300 plus interfaces with other systems, such as supports and connections
400 Fabrication and installation detail
500 Field-verified as-built (used in contracts; not defined in the BIMForum specification)

The level is set per element and per stage. A model can hold LOD 400 ductwork next to LOD 200 casework, and that is fine if the BIM execution plan says so.

Worked example

Illustrative: on Riverside Medical Center (sample data), the mechanical model did not include fire dampers at rated wall penetrations. The super found the gap in the field, which led to RFI-212 and CO #14 for $86,400. If the model had carried a rule-based check, such as “every duct crossing a rated wall needs a damper”, the gap would have shown up before the ductwork went up.

A typical coordination cycle on a mid-rise building, also illustrative: a clash test between the mechanical and structural models returns 1,240 raw clashes. Most are duplicates or tolerances, such as the same duct touching the same beam at many points. Grouped by location and system, they become 85 issues. The coordination meeting resolves 60 by rerouting or resizing, sends 18 to the engineer as RFIs, and accepts 7 as field-fit items. The raw count says little; the grouped issues and their resolution are what matter.

BIM in UK and Canadian practice

In the UK, BIM practice is organized around the ISO 19650 series, which grew out of BS 1192 and PAS 1192. The UK government required BIM on centrally procured public projects from 2016. ISO 19650 talks about the project information model during delivery and the asset information model in operation. Canadian practice uses the same terms as the US and increasingly references ISO 19650.

Why it matters

Clashes found in the model are cheap. Clashes found in the field become RFIs, change orders and schedule hits. BIM also gives estimators and project managers quantities they can trust, if the model is maintained. For owners, a structured handover model can feed facility management and, in some cases, a digital twin. Collaborative delivery methods such as IPD and design-build lean heavily on a shared model.

Common mistakes

  • Letting the model go stale during construction, so it stops matching what is built.
  • Assuming “BIM” means coordinated. Many models are 3D drawings with little data and no clash process behind them.
  • No execution plan, so nobody agrees on LOD, file exchange or who owns the model.
  • Counting raw clashes as a measure of progress instead of tracking grouped issues to resolution.
  • Disconnecting the model from cost and schedule, so its quantities never reach the budget.
  • Asking for “BIM” in the contract without saying which deliverables, formats and LOD the owner needs at handover.
  • Treating model quantities as exact. Takeoffs from the model are only as good as what was modeled.

How os.construction handles it

We’re not building a modeling tool. We’re designing the data core so model-derived records like RFIs, quantities and locations can link to the same job cost and schedule records, working this out with contractor input.

FAQ

What is BIM in construction?

Building information modeling (BIM) is the process of designing, coordinating and managing a building through a shared digital model in which each element, such as a wall, beam, duct or valve, is an object carrying data: its type, size, system, material, manufacturer and location. Teams use the model for design, coordination, quantities, sequencing and handover to the owner.

What is clash detection?

Clash detection is the automated check of a combined (federated) model for conflicts between trades. Hard clashes are physical overlaps, such as a duct running through a beam. Soft or clearance clashes are elements too close for access, insulation or code clearances. Coordination teams review and group the results and resolve real conflicts before the work is built.

What does LOD mean in BIM?

LOD stands for level of development: how complete and reliable a model element's geometry and data are. The common scale runs from LOD 100 (conceptual) through 200, 300, 350 and 400 (fabrication-ready), with 500 used for field-verified as-built elements. The BIMForum LOD Specification defines the levels. Contracts and BIM execution plans say which LOD each element must reach at each stage.

What are 4D and 5D BIM?

4D links model elements to schedule activities so the build sequence can be simulated over time. 5D links them to cost, so quantities from the model drive the estimate or budget. Higher numbers, such as 6D and 7D, are used for sustainability and facility management, but their meaning varies from source to source.

What is ISO 19650?

ISO 19650 is an international series of standards for managing information over the life of a built asset using BIM. It grew out of the UK's BS 1192 and PAS 1192 standards and sets out how information is specified, produced, shared and handed over. The UK government required BIM on centrally procured public projects from 2016, and ISO 19650 now underpins UK practice.