How to run a preconstruction meeting, with a sample agenda

The preconstruction meeting is the last chance to agree how the job will run before anyone is on site under pressure. Here is who should attend, a sample agenda covering scope, schedule, submittals, RFIs, changes, payment, safety and site logistics, how to write it up, and a worked example of a subcontractor precon.

Charley Forey6 min readMeetingsProject managementPreconstruction
On this page
  1. Step 1: Read the documents before you write the agenda
  2. Step 2: Invite the people who will do the work
  3. Step 3: Send the agenda ahead
  4. Sample preconstruction meeting agenda
  5. Step 4: Run the meeting
  6. Step 5: Write and send the minutes
  7. Worked example: a mechanical subcontractor precon
  8. Common mistakes
  9. How os.construction handles it
  10. FAQ

A preconstruction meeting is held after award and before work starts, so everyone agrees how the job will run: contacts, scope, schedule, submittals, RFIs, changes, payment, insurance, safety, site logistics, inspections and closeout. Send the agenda ahead, bring the people who will actually do the work, write minutes with owners and due dates, and send them within a couple of days.

Most problems in the first month of a job come from things nobody said out loud: the sub didn’t know submittals were due in two weeks, the foreman didn’t know deliveries had to be booked a day ahead, the PM didn’t know lien waivers had to come with every pay application. A precon puts those rules on the table while there’s still time to plan around them.

There are two common kinds. The owner’s precon is held with the general contractor, often required by the specifications on public work, sometimes alongside the notice to proceed. The subcontractor precon, or kickoff, is run by the GC with each trade before it mobilizes. The agenda below works for both; adjust the depth to the audience.

Step 1: Read the documents before you write the agenda

The agenda should come from this contract, not a generic list. Pull out of the contract and the general requirements specifications:

  • Submittal procedures and review times.
  • RFI procedure and response times.
  • Change order and notice requirements, including deadlines for written notice.
  • Payment terms: pay application date, retainage, lien waivers, certified payroll if it applies.
  • Insurance requirements and certificates of insurance.
  • Site-specific rules: working hours, noise, parking, security, owner occupancy.
  • Closeout requirements: O&M manuals, warranties, as-builts, attic stock, training.

How to read construction contract payment terms covers the payment side in detail.

Step 2: Invite the people who will do the work

For a subcontractor precon, the sub’s estimator or owner alone isn’t enough. You need the project manager who will process their paperwork and the foreman who will run their crews. For an owner precon, the owner’s decision-maker or owner’s rep, the architect, and the consultants whose submittals and RFIs will matter most (often structural and MEP).

Step 3: Send the agenda ahead

Send it a few days before, with the documents people should read: the schedule, the site logistics plan, the submittal register for their scope, and the site safety rules. People who have read the logistics plan ask better questions.

Sample preconstruction meeting agenda

Sample agendaAdjust items and depth to your contract and to whether it’s an owner or subcontractor precon.
# Item What to cover
1 Introductions and contacts Names, roles, phone and email. Who can sign for what. After-hours emergency contacts.
2 Scope review The scope of work, exclusions, alternates and allowances. Interfaces with other trades. Anything the sub priced differently from the drawings.
3 Schedule Start date, milestones, the sub’s activities and durations, long-lead items, the look-ahead process, and when the sub’s schedule input is due.
4 Submittals Required submittals for this scope, due dates, format, who reviews and typical review time. Nothing ordered or fabricated before review.
5 RFIs How to submit, who to send them to, response times, what goes in one.
6 Changes No extra work without written direction. How to give notice, the deadline for it, T&M tickets signed daily, how to price a change.
7 Payment Pay application date, format, schedule of values, retainage, lien waivers, certified payroll if required, when payment follows.
8 Insurance and compliance Certificates of insurance, additional insured requirements, licenses, any required safety or drug-testing documents.
9 Safety Site-specific safety plan, orientation for every new worker, PPE, toolbox talks, incident reporting, the sub’s competent persons where required.
10 Site logistics Working hours, access and parking, laydown, deliveries and booking, hoisting, temporary power and water, sanitation, waste, security, protection of finished work.
11 Quality and inspections Mock-ups, testing, who calls inspections, hold points, the punch process.
12 Daily reports and meetings Daily report requirements from the sub, weekly subcontractor meeting time and place.
13 Closeout What the sub owes at the end: O&M manuals, warranties, as-builts, attic stock, training. Raised now so it’s collected along the way.
14 Open questions and action items Everything raised, with an owner and a due date.

Step 4: Run the meeting

Keep to the agenda and the clock. An hour to an hour and a half is usually enough for a subcontractor precon; an owner precon on a larger job can run longer. Walk the site afterwards if you can, especially for laydown, access and deliveries. Pointing at the gate is clearer than describing it.

When someone raises something that conflicts with the contract (“we usually bill on the 30th”), don’t settle it by agreement in the room. Note it, then resolve it in writing under the contract.

Step 5: Write and send the minutes

Number each item to match the agenda. For each one, record what was said, any decision, and any action with an owner and a due date. Send the minutes within a couple of days, ask attendees to report corrections by a set date, and carry the open actions into the first weekly meeting. The meeting minutes template and the action item tracker are set up for this.

Where the precon sitsA timeline from award to mobilization. After award, the documents are read and the agenda is written and sent. The precon meeting is held before mobilization. Its minutes and action items carry into the first weekly subcontractor or OAC meeting once work has started.AWARDREAD, AGENDAsent days aheadPRECONmeeting + site walkMOBILIZEwork startsMINUTES + ACTIONScarried into the first weekly meeting
The precon happens before mobilization, and its open actions don’t stop at the meeting.

Worked example: a mechanical subcontractor precon

Illustrative exampleA made-up project, companies and dates.

The job: a three-storey medical office building. The mechanical sub is due to start underground rough-in in five weeks.

Attendees: GC project manager, superintendent and project engineer; the mechanical sub’s PM and its foreman.

What came out of it:

  • Scope. The sub’s bid excluded the condensate pumps shown on two drawings. Logged as action: GC PM to check the bid leveling sheet and either confirm the exclusion with the owner or add it as a change, by Friday.
  • Submittals. Of 22 required submittals, the rooftop units have the longest lead time. The sub committed to submit them in ten days. The project engineer will flag the review to the architect in advance.
  • Changes. The superintendent explained that T&M tickets have to be signed the same day by the GC superintendent. A ticket signed only by the sub’s own foreman won’t be accepted.
  • Payment. Pay applications due on the 20th. Conditional waivers with every application. The sub’s PM asked for the schedule of values format; the project engineer will send it.
  • Logistics. Deliveries booked a day ahead through the superintendent. The sub asked for a container in the laydown area; the superintendent showed the spot on the site walk.
  • Closeout. O&M manuals and the test and balance report are required before substantial completion. The sub will start collecting product data now.

The minutes went out two days later with nine action items. Seven were closed before mobilization; the condensate pump question went to the first OAC meeting.

Common mistakes

  • A generic agenda. Rules from the last job, not this contract.
  • The wrong people in the room. The foreman who will run the work hears about deliveries for the first time on day one.
  • Agreeing to things that conflict with the contract. Raise it, then fix it formally.
  • No minutes, or minutes without owners. A precon nobody wrote up is a conversation, not a record.
  • Leaving closeout for the end. The O&M manual chase starts here.
  • One precon for everyone. A ten-trade meeting covers nothing in depth. Hold one per major trade.

After the precon, the weekly meeting takes over. How to run an OAC meeting covers the agenda and minutes for the owner meeting, and how to track submittals covers the register you’ll set up in the first weeks.

How os.construction handles it

The Meetings tool holds the agenda as topics with an owner and a due date, records attendance and minutes, and carries open topics into a follow-up meeting, so precon actions don’t have to be retyped. Topics can link to the RFI or submittal they’re about. For what to look for in a submittal or RFI tool generally, see construction submittal software and construction RFI software.

FAQ

What is a preconstruction meeting?

A preconstruction meeting, or precon, is held after the contract is awarded and before work starts on site. The parties walk through how the job will be run: contacts, scope, schedule, submittals, RFIs, changes, payment, safety, site logistics and closeout. Owners often hold one with the general contractor, and general contractors hold one with each subcontractor before it mobilizes.

Who attends a preconstruction meeting?

For an owner-led precon: the owner or owner's representative, the architect and key consultants, and the general contractor's project manager and superintendent. For a GC-led subcontractor precon: the GC's project manager, superintendent and project engineer, and the subcontractor's project manager and the foreman who will run the work. Safety staff join when site rules or a site-specific safety plan are covered.

What should be on a preconstruction meeting agenda?

Introductions and contacts, contract scope and exclusions, schedule and milestones, submittals and long-lead items, the RFI process, the change process, payment applications and lien waivers, insurance, safety and site rules, site logistics, quality and inspections, daily reports, meetings, and closeout requirements.

Is the preconstruction meeting the same as preconstruction services?

No. Preconstruction services are the estimating, constructability and planning work done during design, often for a fee. The preconstruction meeting is a single meeting, or a short series, after award and before work starts, about how the job will be administered.

Do preconstruction meeting minutes change the contract?

Generally not by themselves. The minutes record how the parties intend to run the job, but changing price, time or scope usually needs a signed change order or amendment under the contract's terms. If something said at the meeting conflicts with the contract, flag it in writing and resolve it formally.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Open file