Esc

↑↓ move↵ openIndex · Pagefind
Concepts / Pay apps, SOV and retainage

Pay apps, SOV and retainage

How progress billing works with a schedule of values, AIA G702/G703 and retainage, worked through Pay App

On this page

Most commercial contractors get paid through progress billing: once a month, you bill the owner for the share of work completed, line by line, against an agreed schedule of values. This page explains how that works, using Pay App #9 on the Riverside Medical sample job, and how the app assembles it.

The schedule of values

The schedule of values (SOV) breaks the contract sum into billable lines: general conditions, sitework, concrete, steel, mechanical, electrical and so on. Each line has a scheduled value, and the lines add up to the contract sum.

Every month, you report progress on each line: how much was done before, how much this period, and how much material is stored on site. Approved change orders are added as new lines (or adjust existing ones), so the SOV always adds up to the current contract sum.

AIA G702 and G703

Many contracts use the AIA forms, or something modeled on them:

  • G703, Continuation Sheet: the line-by-line detail. One row per SOV line.
  • G702, Application and Certificate for Payment: the one-page summary the architect certifies, built from the G703 totals.

The G703 columns:

Col Meaning
A Item number
B Description of work
C Scheduled value
D Work completed, from previous application
E Work completed, this period
F Materials presently stored (not in D or E)
G Total completed and stored to date (D + E + F), and % (G ÷ C)
H Balance to finish (C − G)
I Retainage

Retainage

Retainage is a percentage of each payment the owner holds back until the job, or a defined part of it, is complete. It protects the owner if work is unfinished or defective. Ten percent is common; many contracts reduce it to five percent at 50% complete, and some states cap it. Retainage is usually released at substantial completion or final completion, once punch list, closeout documents and final lien waivers are in.

You do the same thing downstream: you withhold retainage from your subs per their subcontracts. Tracking both sides, retainage receivable from the owner and retainage payable to subs, is a core part of construction accounting.

Worked example: Pay App #9

Sample data. Riverside Medical’s contract sum is $48.2M plus $1.1M of approved change orders (COs #1–13 plus CO #14). Pay App #9 bills $2,310,400 of work this period, with 10% retainage:

Line G702 item Amount
1 Original contract sum $48,200,000
2 Net change by change orders $1,100,000
3 Contract sum to date $49,300,000
4 Total completed and stored to date $33,000,000
5 Retainage (10%) $3,300,000
6 Total earned less retainage $29,700,000
7 Less previous certificates for payment $27,620,640
8 Current payment due $2,079,360
9 Balance to finish, including retainage $19,600,000

Two lines, including the new change order line (F is materials presently stored: the dampers arrived before install):

Item Description C D E F G % I
23-330 HVAC ductwork · Summit Mech. $3,180,000 $1,590,000 $381,600 $0 $1,971,600 62% $197,160
CO-14 Fire dampers, L3 (CO #14) $86,400 $0 $51,840 $17,280 $69,120 80% $6,912
  • Work this period: $2,310,400
  • Retainage this period: 10% × $2,310,400 = $231,040
  • Net due this period: $2,310,400 − $231,040 = $2,079,360

The G702 gets to the same number the long way: line 6 ($33,000,000 − $3,300,000 = $29,700,000) minus line 7 (what was certified on Pay Apps #1 to #8) equals line 8.

Lien waivers

Owners and lenders usually require lien waivers with each payment: conditional waivers for the current payment, unconditional waivers for payments already received, from you and often from your subs and suppliers. On Riverside Medical, waivers from Apex Steel and CoreDry are missing for Pay App #9. A missing waiver can hold the whole payment, so it pays to see it early. Accounting AP holds a sub’s bill until its waiver is in. Waivers aren’t listed on the pay app itself; see Lien waiver tracking.

Watch a change reach the G702

A worked example on real app screens (sample data, Sandbox Test Project): an executed $18,400 change order shows on the July pay app as line 2, net change by change orders, and line 3 becomes the new contract sum to date. The video opens at that step; the companion page has the full worked example.

The real July pay application G702 panel with lines highlighted in turn: original contract sum $2,400,000, net change by change orders $44,270, contract sum to date $2,444,270.
G702: line 1 + line 2 = line 3 · no sound · ▶️ Watch the full walkthrough on YouTube

How the app builds the pay app

In most stacks, the pay app is a spreadsheet rebuilt every month from the PM tool, the accounting system and a stack of emails. In the app, a pay app is a Payment Application against the prime contract (or a commitment):

  • SOV lines come from the contract’s schedule of values, and executed change orders add to the contract sum.
  • Progress is entered per SOV line: This Period on the continuation sheet.
  • Materials presently stored are entered per line.
  • Retainage is calculated at the application’s rate (10% unless you change it), with separate rates for work and stored materials if you need them, and Retainage Released for amounts you are releasing. Automatic reductions are not built.
  • Previous applications come from the earlier certified applications on the same contract, so column D is never retyped.
  • Lien waivers aren’t checked on the pay app. Accounting AP holds sub bills without a required waiver.
  • Billing the owner. An approved owner pay app becomes a draft AR invoice with Bill in accounting; cost-plus and GMP contracts bill from approved billing terms instead. See Owner billing on GMP jobs.

The pay app page shows the Application & Certificate (G702) summary (original contract sum, net change by change orders, completed and stored to date, retainage on work and on materials, less previous certificates, plus retainage released, current payment due) and the Schedule of Values — Continuation Sheet (G703). Statuses: Draft, Submitted, Approved, Rejected, Paid, Void. The prime contract can be exported to PDF. Step-by-step: Payment applications and Prime contracts.

A Billing agent that drafts the pay app is planned, not built. See Planned agents.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file