Scheduling / Views and layouts: filters, Group & Sort, columns, Network and Trace Logic

Views and layouts: filters, Group & Sort, columns, Network and Trace Logic

Open and save P6-style layouts for yourself, the project or the company, export and import them as files, build filters with nested All/Any criteria and highlight mode, group and sort to five levels with totals, choose from 45 core columns plus baseline, cost, units and earned value columns, draw a progress line, read the logic in the Activity Network, Trace Logic and Assignments views, and roll the plan up in the WBS window.

On this page

A layout is how you look at a schedule: which columns, filters, grouping, sort, Gantt options and panes are on screen. If you come from P6, the Planner works the way you expect. It opens in Classic Schedule, saves layouts at three scopes and as files, has a filter builder, a Group & Sort dialog, a categorized columns dialog, a progress line, an Activity Network, Trace Logic and an Assignments view. Nothing on this page changes the plan itself.

Layouts

Open, save and share

The layout toolbar has Open Layout…, Save Layout and Save Layout As…. A badge shows where the current layout lives (Built-in, Mine, Project, Shared or Browser), and Modified appears once you change it.

Scope Who sees it Who can save it
Built-in (Global) Everyone Nobody. Use Save As to make your own copy.
Mine Only you, on every project Anyone with access to the Schedule tool
Project Everyone with Schedule access on this project Schedule admins on the project
Shared Everyone in the company with Schedule access Company administrators who are also Schedule admin on the project

There are two built-in layouts:

  • Classic Schedule, the default. Like P6’s Classic Schedule Layout in a new project, it has no grouping; Default (WBS) in Group & Sort groups by WBS in one click. The columns are Activity ID / Activity Name, Original Duration, Remaining Duration, Schedule % Complete, Start, Finish and Total Float. The Gantt is on a week timescale with the data-date line, progress and critical colouring on, the baseline bar, float bar and today line off, and relationships shown for the selected activity. Activity Details is open at the bottom.
  • os.construction Standard: ungrouped, with Duration, Start, Finish, Total float and Critical, and the baseline and today line on.

Which layout opens

The Planner opens your default, then the project default, then Classic Schedule. Use Set as my default, Clear my default or Set as project default in the Open Layout dialog. A personal layout can’t be the project default; save it to Project or Shared first.

What a layout keeps

Columns, widths and title overrides; quick filters and saved filters; Group & Sort; sort keys; collapsed groups; the Gantt timescale, Bar Chart Options (including the progress line) and bar list; the display mode (Grid, Gantt, Grid + Gantt, Network or Assignments); the Assignments view’s columns, grouping and sort; the Resource Usage pane; the Activity Details tab setup; and the Trace Logic levels.

Each scope holds up to 200 layouts. Names are 1 to 80 characters and unique within a scope. If someone else re-saved a layout after you opened it, your save is refused rather than overwriting their change.

Layout files

To move a layout between projects, companies or people outside your company, save it as a file:

  • Export Layout… on the layout bar downloads the current layout, unsaved changes included, as an os.construction layout .json file.
  • Download .json in the Open Layout dialog downloads any layout you can see, built-in ones included.
  • Import Layout… reads a .json layout file, or a P6 .plf layout file, into Mine and opens it. A name that’s already taken gets a number added. Move it to Project or Shared with Save Layout As.

An imported .json file passes the same checks as a saved layout and holds at most 260 KiB. Parts that aren’t valid are reset, and the notice lists them. Exporting a layout and importing it again gives you the same layout back.

P6 .plf layouts

A P6 .plf file (up to 2 MiB) is read on a best-effort basis. Only Activities layouts are accepted. What carries across:

  • Columns, by P6 field name, including baseline columns (BL1–BL3), and activity code and UDF columns matched by title to this schedule’s codes and UDFs.
  • Filters: five of P6’s built-in filters. Group & Sort by WBS or an activity code, with up to four sort keys.
  • Bars: source, visibility and P6’s exact colour, with the nearest theme colour as a fallback.
  • Relationship lines, sight lines, the data-date line, the legend and the timescale (interval, two or three lines, zoom).

The import ends with a summary of what was mapped, what was approximated and what was not imported, such as bars filtered on level-of-effort activities or custom criteria. The summary is also shown in the layout bar. Check the layout, then save it. Layouts can’t be exported to .plf.

Columns

Open the Columns dialog to pick from 45 core columns in categories: General, Durations, Dates, Status, Float, Constraints, Units, Costs and Baselines. The same categories also hold the per-slot baseline columns, the P6 cost and units columns and the Actual This Period units and cost columns, and the Earned Value category holds the earned value columns (see Earned value columns). Codes and UDFs add a column for every activity code type and user-defined field in the plan. Open Comments and Comments count each activity’s discussion, so you can filter or group on them. Use Find a column to search.

  • Reorder with the arrow buttons. Activity ID and Activity Name stay frozen at the left.
  • Give any column a title override (up to 60 characters) and an alignment. Both are saved in the layout, so a Classic-style “Original Duration” title doesn’t rename the column for everyone else.
  • Drag a header’s right edge, or use the arrow keys, to set a width from 48 to 640 px. Automatic column widths, Default columns and Standard titles and alignment reset each part.

Values the engine hasn’t calculated show Unknown, and values that don’t apply show —. Both sort last.

Earned value columns

The Earned Value category adds P6’s per-activity earned value columns: Budget At Completion (BAC), Planned Value Cost (BCWS), Earned Value Cost (BCWP), Actual Cost (ACWP), Cost Variance, Schedule Variance, Cost Performance Index, Schedule Performance Index, Cost Variance Index, Schedule Variance Index, To Complete Performance Index, Accounting Variance, Estimate To Complete Cost, Estimate At Completion Cost, Variance At Completion Cost, Performance % Complete, Duration % of Planned and the labor units family (planned value, earned value, variances, indices, ETC, EAC and VAC in labor units). The Costs and Units categories add cost and units % complete by resource type, Cost % of Planned and the cost and units variances against the project baseline. Period performance and earned value gives every formula.

  • BAC is the budgeted cost of the activity’s resource assignments and expenses, and ACWP their actual cost. These are schedule actuals, not Accounting ledger postings. The Total Cost columns include activity expenses too, as P6’s do.
  • Planned value uses the project baseline set in Assign Baselines: its budgeted cost spread evenly over the baseline dates’ working days, up to the data date. With no project baseline assigned, the current schedule is the basis, as in P6. An activity missing from the baseline has no planned value.
  • Earned value is BAC × the performance % complete of the project’s earned value technique, or its WBS’s. CV = EV − AC, SV = EV − PV, CPI = EV ÷ AC and SPI = EV ÷ PV. EAC is actual cost + the estimate to complete under the ETC technique.

The values are worked out on the server for the saved version and reload after each save, so draft edits show once you save and calculate. An activity without resource costs shows —. Actual This Period Units and Actual This Period Cost read the latest stored financial period; see Period performance and earned value.

Filters

Default filters

Twelve read-only filters are ready to use: Critical, Near critical (total float of 10 days or less), Negative float, Longest path, Not started, In progress, Completed, Unfinished, Milestones, Constraint present, Open ends and 3-week lookahead. Copy to edit turns one into your own.

Build your own

  1. Open Filters and choose New, or From quick filters to start from what’s already on screen.
  2. Add criteria. Each row is a parameter, an operator and a value. You can filter on any column, activity code or UDF. Operators include equals, contains, is any of, is within range of, is under (or equals) for WBS and code hierarchies, is within N days of data date, is empty, and date operators such as is on or before.
  3. Group criteria under All of the following (AND) or Any of the following (OR). Groups nest up to five levels deep.
  4. Choose how to apply it. Show only matching activities replaces the view. Highlight activities which match criteria keeps every activity and marks the matches.
  5. Combine filters with All selected filters or Any selected filter, then Apply filters.

Filters are saved in the layout, up to 50 per layout. A criterion on a calculated field never matches an activity whose value is unknown, such as an uncalculated or stale one. A filter can’t hide a missing number by accident.

Group and Sort

Group & Sort groups the activity table and the Gantt together.

  • Up to five group levels, by WBS, any activity code, any UDF or any activity field. Default (WBS) and No grouping reset it.
  • Group Interval for numbers (a band size) and dates (day, week, month, quarter or year; weeks start on Monday). To Level (1 to 20) cuts a WBS or code hierarchy at a depth.
  • Per-level options: show the ID and name, the ID or the name; band colour; ascending or descending; indent; hide if empty; bold; and page break for printing.
  • Show Group Totals (on by default), Show Grand Totals and Show Summaries Only.
  • Sort within groups by up to four keys. In the grid you can also click a header, and Shift+click to add a key.

Grouping a 25,000-activity plan with totals takes about a tenth of a second.

Totals line up under their columns. Units and costs are summed, and cost totals include activity expenses. Earned value indices, percentages and variances aren’t totalled, because P6 works them out from the band’s own totals. Start shows the earliest date and Finish the latest. Total and free float show the minimum. Duration shows the band’s working-day span, and % complete is weighted by duration. Totals count only the activities the filters show. Every group band gets a summary bar in the Gantt.

Gantt

The Gantt keeps the day-to-year zoom presets, Fit schedule, data-date and today lines, critical colouring, progress fill, float bars and dependency arrows. See Activity grid and Gantt. Layouts add P6’s timescale, Bar Chart Options and bar list.

Timescale

  • Two or three lines. Choose a date interval (Year/Quarter, Year/Month, Quarter/Month, Month/Week, Week/Day or Day/Hour), or Automatic, which follows the zoom as before. Three lines add the next coarser unit above the pair.
  • Calendar or fiscal years and quarters. Fiscal years are named by the calendar year they end in, so with a July start FY2027 runs from July 2026 to June 2027. The start month comes from the layout, else the project’s fiscal-year setting, else January.
  • Ordinal dates (Day 1, Week 1 …), counted from the data date or a day you choose.
  • Week starts on any day; Monday is the default.
  • Timescale start: the earliest dated activity, the data date (with an offset in days), or a fixed date.

Bar Chart Options

Sight lines (major and minor, at the tiers of the timescale); the data-date line’s style (solid, dashed or dotted), colour and width; horizontal lines every N rows and above summary rows; and the legend on or off.

Bars

Bars is an ordered list, as in P6. Each bar has:

  • a source: current, remaining, actual, primary, secondary or tertiary baseline, total float, negative float, summary or % complete;
  • an optional filter (any default or saved filter), so a bar draws only for matching activities;
  • an optional activity type, such as Level of effort, so a bar draws only for that type of activity (P6’s Level of Effort bar filter);
  • a style: shape (solid, outlined, dashed, hatched, a line, or none for labels only), colour, thickness and row position;
  • labels left, right, above, below or in the centre, from any column, code or UDF.

Lower rows draw on top. Start from Default (os.construction) or P6 classic colours, then edit. P6 classic colours draws P6’s exact colours: actual work #0000FF blue, remaining work #80FF80 light green, critical remaining work #FF0000 red, summary black, actual level of effort #000080 navy and remaining level of effort #008000 dark green (limited to level of effort activities and drawn over the work bars), and yellow primary, secondary and tertiary baseline bars that start hidden. Picking a theme colour for a bar replaces its exact colour. Theme colours follow the light and dark themes, and shapes, patterns and the legend name every bar, so colour is never the only cue. Up to 40 bars.

For example, to pick out near-critical work, add a bar with source Remaining, the Near critical filter, amber colour and the activity name as its right label, and move it below Remaining Work in the list so it draws on top.

Baselines

Open Assign Baselines in the Planner to choose:

  • the Project baseline, shared by everyone on the project. Changing it is audited.
  • your own Primary, Secondary and Tertiary baselines. These are personal and never change what anyone else sees. If you don’t choose a primary, it’s the project baseline, as in P6.

Up to three baseline bars draw on the Gantt, one for each slot, through the bar list. The columns dialog adds 14 columns for each of BL1, BL2 and BL3: start, finish and duration; start, finish and duration variance; BLn Total Cost; and the variance of total, labor, nonlabor, material and expense cost and of labor and nonlabor units. Variances are the baseline value minus the current one, as in P6. Date variances are in calendar days (negative is late). Duration variance is the baseline duration minus the at completion duration (actual plus remaining), in working days. Cost and units variances compare the baseline’s planned values with the current at completion values. A slot without a baseline, or a baseline without that activity, shows —. Assigning baselines never changes a schedule or a baseline.

Dragging bars

You can drag bars. The move mode decides what a drag means:

  • Start no earlier than sets a start-no-earlier-than constraint on the day you drop. Predecessors can still hold the activity later.
  • Adjust predecessor lag changes the working-day lag of the activity’s single predecessor, so the network stays logic-driven.
  • Select only turns bar moves off. You can still drag duration and links.

Every drag is an undoable draft edit. Dates change only when you save and recalculate.

Progress line

P6’s progress line is in the Progress Line panel beside Bar Chart Options, and it’s saved with the layout. The line runs down the chart through the data date, or a fixed date you choose, and bends out to each activity’s progress point. A point to the right of the line is ahead of plan, and a point to the left is behind. Within half a day counts as on plan.

  • Progress point based on: Percent complete (the bar’s start plus % complete of its length), Remaining duration (the bar’s finish minus the remaining duration) or Difference between baseline and current start/finish (the line date plus the start variance before the activity starts, else the finish variance).
  • Reference: Project baseline, Primary baseline or Fixed date. Points sit on that baseline’s bar for the activity. An activity without a baseline bar uses its current bar, except under the baseline-difference basis, which needs a baseline and gives no point without one.
  • Which activities: those in progress, and those whose reference bar spans the line date.
  • Line style and colour: solid, dashed or dotted, in one of the theme colours.

A legend entry and a summary line go with it, for example Progress line: 2 ahead, 3 behind, 1 on plan at the data date. If the chosen baseline isn’t loaded, a note says so; assign one in Assign Baselines. The print Gantt draws the same line when you print with a layout that has it on, and so does the touch Gantt.

Limits: remaining duration is converted to bar length in proportion to the original duration, not by walking the activity calendar; group summary rows get no point; and with unsaved edits the line is off on changed rows until you recalculate.

Progress Spotlight on the Gantt

With Progress Spotlight on, the Gantt tints the window from the data date to the proposed new data date, and you can drag its dashed edge by whole timescale intervals. Range selection, fill down, Excel paste, copying activities and Global Change are covered in Editing and progress tools.

Assignments view

Choose Assignments as the display mode for P6’s Assignments window: one row per resource assignment across the plan.

  • Columns cover the activity (ID, name, WBS, calculated start and finish, status and duration type), the resource (ID, name, type and role), budgeted, actual, remaining and at-completion units and cost, units per day, price per unit, curve, Lag (h), Remaining Lag (h) and Drive Activity Dates. Choose them under Assignment columns.
  • Group by resource, role, activity or any activity code, with group totals and a grand total. Find an assignment searches the rows. Click a header to sort, and Shift+click to add up to four keys.
  • Edit in place: budgeted and remaining units, units per day, price per unit, budgeted and remaining cost, the curve, the lag and remaining lag, and the Drive Activity Dates check box. Remaining lag follows the lag until the activity starts. Each units, rate or cost edit follows the activity’s duration type, exactly as on the Activity Details Resources tab, and is one undo step. Budgeted values are read-only once an activity has started, and remaining values follow budgeted until it starts.

The grouping, sort and columns are saved in the layout. Rows show 200 at a time, with Previous and Next. Dates come from the last calculation. To see a resource’s load over time, open Resource Usage.

WBS window

Choose WBS as the display mode for P6’s WBS window: one row per WBS node, with values rolled up from every activity beneath it, a project total row, and a WBS Gantt of summary bars.

  • Dates and durations: earliest start and latest finish, and original and remaining duration in working days of the plan’s default calendar over that span (remaining counts from the day after the data date).
  • Float and progress: the smallest total float, with critical nodes in red, and % complete weighted by original duration.
  • Costs and units: budgeted, actual, remaining and at-completion total cost and units from resource assignments plus activity expenses, and budgeted expense cost on its own. An unknown value stays blank rather than counting as zero.
  • Columns chooses the column groups. Show WBS Gantt, Expand all and Collapse all set the rest. All of it is saved in the layout.

The rows follow the layout’s filters, so a filtered layout gives a filtered rollup. Select a node to rename it, change its code, Move up, Move down or Move under another node, or set its earned value technique, custom percent complete, ETC technique and performance factor. Each field shows what it inherits from the parent WBS or the project until you set it; choose Inherit to go back. Each change is one undo step. Go to first activity selects it in the grid. Dates come from the last calculation; after edits, save and calculate to refresh them.

Line of Balance

Choose Line of Balance as the display mode to see locations against time, with one sloped line per trade, conflicts, buffers, crossings and takt planning. See Location-based planning.

Activity Network

Switch the display mode to Network to see the filtered, sorted and grouped activities as boxes in a left-to-right logic diagram. Each box shows the ID, name, start and finish, and original duration, remaining duration and total float. Critical boxes are red, driving relationships are drawn heavy, and links show their type and lag when they aren’t FS 0. Turn on Label every relationship to label all of them.

The layout is deterministic: boxes are placed by their longest path from the start, with crossings reduced, so the same plan always draws the same way. Groups become bands. A relationship loop shows a warning. Zoom with +, −, Fit and 100%, Ctrl+wheel or pinch. Pan by dragging. Export network SVG saves the diagram, and Print network opens the browser print dialog, where you can save a PDF.

Trace Logic

Trace Logic opens under the table and draws a small network around the selected activity. It shows 1 predecessor level and 1 successor level by default; use − and + to set each from 0 to 10. Driving relationships come from the engine’s last calculation and are drawn heavy. Without driving data, links are dashed rather than guessed.

Click a box, or press Enter, to select it and re-centre the trace. Why this date? opens the full date trace for that activity, and Export trace SVG saves the picture. The levels are saved in the layout.

What’s not here yet

  • Exporting to P6 .plf. Layouts export as os.construction .json only, and .plf import is best effort.
  • Choosing a layout in the touch view. The touch Gantt draws with the desktop Planner’s working layout, else your default layout; see Touch view.
  • Views saved in the browser (from earlier releases, and the touch view’s own saved views) don’t store the timescale, Bar Chart Options or bars. Server layouts do.
  • Mistake: Saving over Classic Schedule

    In the app: Built-in layouts are read-only. Use Save Layout As and pick Mine, Project or Shared.

  • Mistake: Hiding everything that isn’t critical before a review

    In the app: Use Highlight mode, so reviewers see the critical work in context.

  • Mistake: Reading a group total as a sum of durations

    In the app: Duration totals are the band’s working-day span, not a sum. Units and costs are sums.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file