Using the app / Commitments and sub invoices

Commitments and sub invoices

Set up subcontracts and purchase orders with a schedule of values, change them with commitment change orders, and enter sub invoices with retainage.

Preview

Partly in the app today. Items marked Planned are not built yet.

On this page

A commitment is what you owe someone else on the job: a subcontract or a purchase order. The Commitments tool holds the contract, its schedule of values (SOV), its change orders and the invoices billed against it. Approved commitments are what the Budget shows as Committed Costs. For the concepts, see Subcontracts and commitment changes.

Open it from the project: Tools → Commitments. The tabs are Subcontracts, Purchase Orders and Invoices.

Create a subcontract or PO

  1. Create

    Click Create Subcontract or Create Purchase Order. Pick the Contract Company (a vendor from the directory), a Number and Title.

  2. Set the terms

    For a subcontract: Default Retainage (%), Inclusions, Exclusions and the contract dates (start, estimated completion, signed contract received, execution). For a purchase order: delivery date, ship via, payment terms, ship to and bill to.

  3. Build the SOV

    On the Schedule of Values tab, add line items: Cost Code, Description, Qty, UoM, Unit Cost ($) and Amount ($) (leave it blank to use quantity × unit cost).

  4. Move it through status

    Subcontracts go Draft, Out For Bid, Out For Signature, Approved, Complete (or Terminated or Void). Purchase orders go Draft, Processing, Submitted, Partially Received, Received, Approved, Closed. Set Executed (and the execution date) when it’s signed.

A commitment counts as committed cost once it’s approved (or complete, for a subcontract). Before that, its lines show as Pending Cost Changes in the budget.

Check Private contract under Contract access to keep a contract to the people who need it. Someone without access to the SOV sees the general information only.

Change a commitment

The Change Orders tab shows two lists:

  • Approved Change Orders: PCOs against this contract from the Change Orders tool, usually created from the same change event as the owner change.
  • Commitment Change Orders: direct changes. Enter a Title, Cost Code and Amount ($) and click Create CCO. CCOs go Draft, Pending, Approved, Rejected or Void.

The Revised Contract card adds them up: Original Contract Amount, Approved PCOs, Approved CCOs, Approved Change Orders and Revised Contract Amount.

Enter a sub invoice

  1. New Invoice

    On the commitment’s Invoices tab, fill in Invoice #, Period Start, Period End and Billing Date.

  2. Bill against the SOV

    The invoice opens with a line for each SOV item: Description of Work, Scheduled Value, From Previous, This Period, Materials Stored, Total Completed & Stored, %, Balance to Finish and Retainage. Enter This Period and Materials Stored; the rest calculates.

  3. Retainage

    Retainage on each line is total completed and stored × the commitment’s retainage rate. The Invoice Summary shows retainage withheld to date.

  4. Review

    Invoice statuses: Draft, Submitted, Under Review, Revise and Resubmit, Approved, Approved as Noted and Pending Owner Approval.

The project-level Invoices tab lists every sub invoice with contract, contract company, billing period, status and amount.

Export

Select rows in a list and use Export CSV. See Export to CSV and PDF.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file